Zinnwald Lithium plc announced its final audited results for the year ended 31 December 2025, highlighting significant progress on its integrated Zinnwald Lithium Project in Germany. The company published a Pre-Feasibility Study confirming the project's technical and financial viability, projecting a pre-tax NPV of €3.3 billion and an IRR of 23.6%, with a maiden ore reserve of 128 Mt grading 4,428ppm Li₂O. The project boasts a mine life exceeding 40 years, with Phase 1 production targeting 18,000 tpa of battery-grade lithium hydroxide, expandable to 35,100 tpa. Key milestones included achieving permitting and ESG objectives, securing strong government backing, and completing a £3.4 million fundraise. The company also reported an operating loss of €3.5 million for the year, compared to €3.1 million in 2024, with cash balances at €2.7 million.