Operational Update - Dubhe-1

Summary by AI BETAClose X

Pantheon Resources plc provided an operational update on the Dubhe-1 well, noting that clean-up operations are ongoing with intermittent oil and increasing gas production since early November, with approximately 40% of injected water now produced. The final cost for drilling and completing Dubhe-1 was approximately $33 million, including a pilot hole and contingency measures, exceeding the initial estimate of around $10 million for drilling and $15 million for completion, with the new pad costing an additional $2.5 million. The company aims to determine a representative oil flow rate as clean-up continues, acknowledging that the multi-stage completion may result in a different clean-up profile compared to previous wells.