La India Development Update

AI SummaryClose X

Metals Exploration Plc has provided a positive update on its La India gold project, with first gold production still on track for December 2026. The company has secured a US$27 million equipment loan from a local Nicaraguan bank, with an initial US$20.2 million drawn down, significantly strengthening its cash position. Construction progress is substantial, with the process plant SMPEI approximately 50% complete, civil works 92-93% complete, and site infrastructure nearing completion. The mining fleet is expanding, with 10 haul trucks and two excavators on site, though some delivery delays have been experienced due to international shipping disruptions. Runruno production is forecast to be at the upper end of guidance for 2026.