ICSID Suspension – Potential Negotiated Settlement

AI SummaryClose X

Zenith Energy reports its approximately US$573 million ICSID arbitration claim against the Republic of Tunisia has been suspended effective today after Tunisia failed to pay its required advance on costs; Procedural Order No.5 confirms Tunisia owes 50% of procedural costs. The suspension may delay the Tribunal’s previously expected final award (May 2027) by several months. Zenith will not advance Tunisia’s share at this stage but may do so again to resume proceedings; it remains willing to pursue good-faith settlement discussions facilitated by CNQ Global Advisors while reserving all rights and seeking the Tribunal to account for Tunisia’s non-payment in any cost allocation.