INTERIM RESULTS FOR SIX MONTHS ENDED 30 JUNE 2026

Summary by AI BETAClose X

Zanaga Iron Ore Company Ltd has reported interim results for the six months ended 30 June 2026, highlighting significant progress in its project development strategy which has identified US$2.2 billion in cash cost savings and increased revenue potential by US$11,325 million over the mine's life due to the ability to produce DRI-grade pellet feed. The company also advanced its funding strategy, signing a binding term sheet with Red Arc Minerals LLC for a strategic investment, with RAM providing evidence of a potential US$500 million financing from a development finance institution, and extended the transaction deadline to 30 November 2026. Furthermore, ZIOC successfully raised £5.6 million (approximately US$7.6 million) in May 2026 to fund a bulk sampling program, which has commenced mobilization. The company reported a cash balance of US$5.4 million as of 30 June 2026 and a net loss of US$4.2 million for the period.

Disclaimer*

Zanaga Iron Ore Company Ltd
29 September 2026
 

THIS ANNOUNCEMENT CONTAINS INSIDE INFORMATION FOR THE PURPOSES OF ARTICLE 7 OF THE MARKET ABUSE REGULATION (EU) 596/2014 AS IT FORMS PART OF UK DOMESTIC LAW BY VIRTUE OF THE EUROPEAN UNION (WITHDRAWAL) ACT 2018 ("MAR"), AND IS DISCLOSED IN ACCORDANCE WITH THE COMPANY'S OBLIGATIONS UNDER ARTICLE 17 OF MAR

29 September 2026

Zanaga Iron Ore Company Limited

(“ZIOC” or the “Company”)

INTERIM RESULTS FOR THE SIX MONTHS ENDED 30 JUNE 2026

Zanaga Iron Ore Company Limited (AIM: ZIOC) is pleased to announce its unaudited interim results for the six months ended 30 June 2026, together with an update on post-reporting period events to the date of this announcement.

Highlights

Project Development Strategy

      Four targeted, high-impact initiatives were identified at the beginning of 2025. Throughout 2025 and H1 2026, the costing and feasibility of these initiatives were completed, delivering US$2.2 billion in cash cost savings1.

1) Direct Reduction Iron ("DRI") product quality test work:

o        Positive test work results confirming the ability of the Zanaga Iron Ore Project (the "Zanaga Project" or the "Project") to produce DRI-grade pellet feed concentrate with low impurities:

        Stage One (hematite) concentrate grade results: 68.5 %Fe, 1.05 %SiO₂, 0.47 %Al₂O3, 0.034 %P

        Stage Two (magnetite) concentrate grade results: 69.1 %Fe, 1.96 %SiO₂, 0.40 %Al₂O3, 0.028 %P

o        Confirmation of DRI-grade pellet feed has increased the Project's revenue potential by US$11,325 million[1],[2] over the initial 30-year life of the mine.

2) Pellet Plant Feasibility Study:

o        A feasibility study was completed to verify the likely costs to construct and operate both 2.5 Mtpa hot and 2.5 Mtpa cold pellet plants in the Republic of Congo.

3) Single Pipeline Feasibility Study:

o        A feasibility study was commissioned in Q2 2025 to evaluate the construction of a buried 30 Mtpa pipeline within the Stage One scope.

o        One pipeline requires US$986 million in upfront capex, adding US$349 million to Stage One but reducing total capex by US$357 million across the 30 Mtpa, two-stage estimate. It could also eliminate a booster station and its energy use, potentially lowering operating costs by US$950 million over the mine's first 30 years.

o        While the incremental NPV impact is limited—higher Stage One cash investment offsets Stage Two savings—the Group sees strategic value in a single pipeline configuration and will keep evaluating this option within recommendations of a construction decision.

4) Tailings Management:

o        A study was initiated in Q2 2025 to revise the 2014 Feasibility Study tailings storage facility (“TSF”) design to align with international best practices.

o        Thickened and dry tailings facilities compliant with global standards have the potential to reduce cash expenditure by US$1,280 million over the mine’s initial 30-year life.

Strategic Investment in Zanaga Project

      In February 2026, ZIOC and its wholly owned subsidiary, Jumelles BVI Limited, signed a binding term sheet with Red Arc Minerals LLC ("RAM"), a private investment company backed by leading mining industry executives and focused on the development of strategic-scale high-grade iron ore assets, for a proposed strategic investment in the Zanaga Project.

o           In May 2026 and subject to entering definitive documents for the proposed transaction, RAM agreed it will refund the Company expenses incurred in connection with the bulk sampling programme and Zanaga Project in-country overheads from 1 July 2026 up to a maximum of US$2.0 million. 

o           On 31 July 2026, RAM provided evidence of a Letter of Intent (“LOI”) for potential strategic financing of up to US$500 million for the Zanaga Iron Ore Project and its associated infrastructure from a large western government-backed development financing institution ("DFI").  LOI was issued by DFI and discussions continue.

o           On 31 July 2026, RAM and ZIOC agreed to extend the period within which RAM may conclude the proposed transaction and make the first Tranche One payment to 30 November 2026.

April 2026 Economic Update

      The Group announced updated Project economics following completion of the project development strategy programme and the results of a technical and commercial evaluation of the process flowsheet for producing premium-quality DRI pellet feed concentrates. This update has increased confidence in the Project's economic prospects. The feasibility of producing DRI pellet feed at the mine demonstrates strong value creation, as shown below:

 

 

April 2026

Economic Update

Previous Studies

Change vs 2024 Feasibility Update

Financial Metric

 

2026[3]

Based on DRI product

2024[4]

Feasibility Study Update

20144

Feasibility Study

%

Stage One

 

Capex (US$m)

2,174

1,935

2,196

+12.4%

NPV (US$m)

2,539

1,939

2,132

+30.9%

IRR (%)

22.5

21.4

22.9

+1.1%

Avg. Product Grade (%Fe)

68.5

65.9

65.9

+2.6%

Stage One and Two

 

Expansion Capex (US$m)

+1,871

+1,871

+2,488

-

Combined NPV (US$m)

4,897

3,784

4,026

+29.4%

Combined IRR (%)

24.3

23.0

23.9

+1.3%

Avg. Product Grade (%Fe)

68.8

67.2

67.2

+1.6%


Project NPV increased in the April 2026 update, but higher upfront Stage One investment restricted the growth of IRR.

May 2026 Equity Raise

        Successfully raised aggregate gross proceeds of £5.6 million (approximately US$7.6million) through a placing, subscription, and retail offer, issuing 142 million shares at four pence each (“May 2026 Equity Raise”).

Bulk Sampling Programme

        Part of the proceeds from the May 2026 Equity Raise have been invested into a Bulk Sampling Programme.  The Company agreed commercial terms with a prominent civil earthwork’s contractor in the Republic of Congo, following which mobilisation to the Zanaga Project site commenced in July 2026.

 

        The bulk sampling programme is designed to obtain composite samples of the hematite zone, targeted for Stage One operations at 12Mtpa. The ensuing metallurgical test work programme aims to confirm Zanaga’s revised DRI flowsheet at pilot scale, providing adequate quantities of concentrates for specification characterisation, process engineering design, and product customer testing to be launched with steel mill customers, independent laboratories and offtakers.

 

Cash balance

        Cash balance of US$5.4 million as of 30 June 2026 and cash balance of US$3.7 million as of 17 September 2026.

Annual General Meeting

        Annual General Meeting to be held in December 2026, with the requisite notice to be sent to shareholders in due course.

Clifford Elphick, Non-Executive Chairman of ZIOC, commented:

“I am pleased to report strong progress on the Zanaga Iron Ore Project during the first half of 2026. Successful project development strategies identified approximately US$2.2 billion of potential life-of-mine cash cost savings which supported the April 2026 economic update, which substantially increased the Project's NPV.

 

“We have continued to advance the Project’s funding strategy, including the proposed strategic investment by Red Arc Minerals. In July 2026, RAM provided evidence of a potential strategic financing of up to US$500 million from a Western government-backed development finance institution, with discussions ongoing and the transaction timetable extended to 30 November 2026. The Company also raised £5.6 million in May to support the bulk sampling programme which represents a significant physical step forward for the project’s development. We remain focused on advancing Zanaga towards Final Investment Decision and maximising value for shareholders.”

 

Copies of the unaudited interim results for the six months ended 30 June 2026 are available on the Company's website at www.zanagairon.com

 

For further information, please contact:

Zanaga Iron Ore Company Limited

 

Andrew Trahar

+44 20 3916 5021

Panmure Liberum Limited

Nominated Adviser, Financial Adviser and Joint Broker

Scott Mathieson / John More

+44 20 3100 2000

Tamesis Partners LLP

Joint Broker

Richard Greenfield / Charles Bendon

+44 203 882 2868

Shard Capital Partners LLP

Joint Broker

Damon Heath

+44 20 7186 9952

BlytheRay

Public Relations

Megan Ray / Will Jones

+44 20 7138 3204

Zanaga@BlytheRay.com

ENDS

About ZIOC:

Zanaga Iron Ore Company Limited (AIM ticker: ZIOC) is an iron ore exploration and development company, with its flagship asset being the 100% owned Zanaga Iron Ore Project, located in the Republic of Congo. The Government Mining Licence, Environmental Permit and Mining Convention are all in place for the Project.

The Zanaga Iron Ore Project is a globally significant asset with a 6.9 billion tonne resource and a 2.1 billion tonne reserve, targeting 30Mtpa production of high-grade DRI pellet feed with very low impurity levels. When fully developed, Stage One (12Mtpa) and Stage Two (18Mtpa expansion) together could establish Zanaga as one of the world’s largest iron ore mines. With all key permits secured, Zanaga is well positioned to benefit from increasing demand for high-quality, low-impurity iron ore, supported by low operating costs and an efficient slurry pipeline to port.

In the context of the global transition towards lower-carbon steel production, the Zanaga Project is well positioned to become one of the largest producers of high-grade, premium DRI pellet feed iron ore concentrate.

The Zanaga Iron Ore Company Limited LEI number is 21380085XNXEX6NL6L23.

 


Business Review – Operations update

Iron Ore Market[5]

Seaborne iron ore entered the 2026 calendar year with a firmer cost floor than at the start of 2025. Approximately 260 Mt of supply is now estimated to need more than US$80/t Cost and Freight (“CFR”) to stay economic, versus approximately 180 Mtpa a year earlier. The lift reflects persistent energy and freight inflation since the Middle East conflict commenced, along with new volume from African developments and Australian juniors that sit higher on the cost curve.

Cost pressure is not only cyclical; established resource origins are ageing: grades are declining, and replacement capital costs are escalating. By late 2025, the 90th-percentile cost of supply was about 40% above pre-pandemic levels in nominal terms, while over 2026–2035, approximately 250 Mt of current operating seaborne capacity is expected to drop out through depletion. Sustaining output from long-established resources will therefore require heavier investment, which creates a higher long-run cost structure and increases the strategic need to secure, high-grade supply.

Demand has not followed the weakest part of the Chinese cycle. Property remains soft, yet crude steel output in China has held near 1 Btpa since 2018. Policy emphasis on advanced manufacturing, digitalisation, infrastructure modernisation and industrial upgrading all point towards Chinese steel production sustaining this volume through the rest of the decade.

Growth outside China is more structural; India increased steelmaking capacity to approximately 220 Mtpa in FY2026, a 10% increase on the prior year, and is aiming for 500 Mtpa by 2047 — roughly a 4% compound annual growth rate. Southeast Asia is the other incremental centre with approximately 90 Mtpa of new steel capacity planned by the mid-2030s, of which around 30% is non-blast furnace installations, as governments seek to lock in domestic manufacturing to meet rising regional demand.

Taken together, a rising seaborne cost support band, visible depletion of existing mines, significant capacity growth in India and EAF growth in Southeast Asia form the base case for iron ore through the second half of the decade.

Project Development Strategy

During the period, the Group completed its project value enhancement initiative, first announced on 18 March 2025. The workstreams have delivered significant value enhancement and strategic benefits across multiple areas of the Zanaga Iron Ore Project.

Detailed design and costing assessments were completed with industry experts across the following workstreams:

1)   Product quality enhancements - Direct Reduced Iron test work

2)   Pellet plant feasibility study

3)   Single 30Mtpa capacity pipeline feasibility study

4)   Thickened and dry tailings facility study

The completion of these workstreams has not only improved the economic potential of the Zanaga Project but has also established a robust engineering and design foundation as the Group progresses the Project.

The key overall economic highlights reported in the table below are in comparison to the previous feasibility model updated in 2024:

 

Area

Outcome

Potential impact over 30 years of mine life

% Change

  1.  

Revenue Potential

Increases

US$11,325 million

16%

  1.  

Total Capital Expenditure

Reduces

US$352 million

(9)%

  1.  

Total Cash Cost

Reduces

US$2,235 million

(10)%

 

  1. Sustaining Capital Expenditure

Reduces

US$1,505 million

(39)%

 

  1.  Operating Expenditure

Reduces

US$731 million

(4)%

 

Strategic Investment in the Zanaga Project

      In February 2026, ZIOC and its wholly owned subsidiary, Jumelles BVI Limited, signed a binding term sheet with RAM, a private investment company backed by leading mining industry executives and focused on the development of strategic-scale high-grade iron ore assets for a proposed strategic investment in the Zanaga Project.

o           Tranche One investment of up to US$25 million in cash to advance the Zanaga Project to FID and acquire an aggregate 20% interest in Jumelles (to be funded in five equal sub-tranches).

o           Tranche Two investment at the option of RAM of US$125 million via a cash payment to ZIOC (at RAM's option) to acquire an incremental 67.5% fully diluted ownership of Jumelles from ZIOC (resulting in aggregate RAM ownership of Jumelles of 87.5%), exercisable within 18 months of completion of the full US$25 million Tranche One.

o           Royalty to be granted to ZIOC on the closing of Tranche Two of 1.0% of Net Sales Revenue ("NSR") on all iron ore concentrate sales from the Project, subject to a partial buy-back at RAM's option (US$50 million for 0.50% NSR).

      Rationale for the transaction structure

The Transaction, as envisaged, has been structured to achieve multiple objectives for ZIOC shareholders, which are summarised below:

1.   Limiting dilution to ZIOC shareholders

o        The transaction envisaged would not result in direct dilution to ZIOC shareholders as it is an investment at the Jumelles subsidiary level and the Tranche One investment may only potentially be converted into ZIOC shares by either ZIOC or RAM at 15 pence per share (and subject to certain conditions and restrictions).

2.   Advance the Zanaga Project to FID

o        Tranche One is expected to fully fund the Project through FEED completion to FID, including capital available for contingency and continued Jumelles project working capital costs to cover the final financing negotiation phase of the Project post FEED.

3.   Near-term path to significant floor price cash value (via Tranche Two payment)

o        If RAM exercises the Tranche Two option, US$125 million in cash will be received by ZIOC, which may be distributed to ZIOC shareholders in due course or utilised for retaining an equity stake in the Zanaga Project.

o        ZIOC intends to retain this cash on the Group's books until such time as the Zanaga Project FID is taken, in order to consider the attractiveness of investing it to retain an equity stake in the Zanaga Project going forward (such decision will depend on the project economics at the time of the Project's FID).

4.   Optionality to retain 12.5% project ownership

o        The envisaged transaction has been structured to enable ZIOC to fully fund its pro-rata 12.5% share of an estimated US$1 billion total project equity contribution required from the final equity investors in the Project at construction.

o        In the event that ZIOC elects to fund such pro-rata 12.5% final equity contribution at construction, ZIOC would have retained a sizeable share of a fully financed strategic iron ore asset with highly attractive economics.

o        By way of illustration, if the Zanaga Project generates EBITDA of US$2 billion per annum in Stage Two, ZIOC's attributable share of such EBITDA would equate to US$250 million per annum.

5.   Royalty upside to ZIOC shareholders only

o        Upon Completion of the Tranche two Investment, the transaction structure envisages a 1% NSR royalty to be paid to ZIOC only (subject to a partial buy-back at RAM's option of US$50 million for 0.50%), which enables additional substantial value upside that is indifferent to the Project's economics.

o        ZIOC is not expected to invest further in the Zanaga Project to receive this annual royalty payment.

o        By way of illustration, based on a 1% NSR royalty if the Zanaga Project generates US$3,246 million of net sales revenue per annum in Stage Two, the NSR royalty payable to ZIOC would equate to US$32.5 million per annum. Following a US$50 million buy-back of 0.50% NSR, the royalty payable would halve to c.US$16.2 million per annum.

      In May 2026 and subject to entering into definitive documents for the proposed transaction, RAM agreed that it will refund the Company expenses incurred in connection with the bulk sampling programme and Zanaga Project in-country overheads from 1 July 2026 up to a maximum of US$2.0 million. 

      On 31 July 2026, RAM provided evidence of a LOI for potential strategic financing of up to US$500 million for the Zanaga Iron Ore Project and its associated infrastructure from a large western government-backed DFI.  The DFI has issued a LOI and discussions  continue.

      RAM and ZIOC have agreed to extend the period within which RAM may conclude the proposed transaction and make the first Tranche One payment to 30 November 2026.

April 2026 Economic Update

      Strategic Advancement to DRI Product

Following successful laboratory-scale DRI test work completed in mid-2025, ZIOC commissioned detailed conceptual and feasibility-level designs to refine capital and operating cost estimates to ±20% accuracy.

 The updated development strategy incorporates:

o        A modular 12Mtpa hematite concentrator complex consisting of three 4Mtpa lines

o        A two-stage, 12Mtpa and 18Mtpa, pipeline system, with optional single 30Mtpa slurry pipeline system

o        Thickened tailings storage facilities

o        A 12Mtpa filter plant and covered concentrate handling facilities

The Group's DRI product strategy positions the Zanaga Project to benefit from:

o        Increasing demand for premium iron ores, particularly DRI-grade iron ore

o        Global steel sector decarbonisation via growth in Electric Arc Furnace ("EAF") steel production

o        Firm positioning in the lowest cost quartile of iron ore producers

       Stage One Processing Facility Capital and Operating Cost Overview

The updated Stage One processing capital expenditure estimate (April 2026 Economic Update Case[6]) totals approximately US$753.7 million for processing, filtration and concentrate handling facilities, contributing to a total expected Stage One capital requirement of US$2.17 billion[7].

Operating unit processing, filter plant and product handling costs for Stage One are estimated at US$11.97 per tonne of concentrate[8].

Stage One processing operating costs and capital expenditure estimates have increased moderately compared with previous studies. For example, DRI-grade product premiums significantly improves the Project's Stage One NPV by approximately 31% relative to the 2024 Feasibility Study Update.  Refer to the April 2026 Economic Update within the ‘Highlights’ section of this announcement.

May 2026 Equity Raise

The Group raised equity capital through a placing, subscription and retail offer of new ordinary shares of an aggregate of £5.6 million (approximately US$7.6 million).

The net proceeds of the Capital Raising will be used to:

o        progress the bulk sampling campaign, including earthworks and sampling;

o        support Zanaga Project in-country overheads; and

o        support ZIOC corporate overheads and general working capital requirements.

 

Bulk Sampling Programme

Part of the proceeds from the May 2026 Equity Raise have been invested into a Bulk Sampling Programme.  The Company agreed commercial terms with a prominent civil earthworks contractor in the Republic of Congo, following which mobilisation to the Zanaga Project site commenced in July 2026.

 

The bulk sampling programme is designed to obtain composite samples of the hematite zone, targeted for Stage One operations at 12Mtpa. The ensuing metallurgical test work programme aims to confirm Zanaga’s revised DRI flowsheet at pilot scale, providing adequate quantities of concentrates for specification characterisation, process engineering design, and product customer testing to be launched with steel mill customers, independent laboratories and offtakers.

 

As of 28 September 2026, vegetation and topsoil have been removed in accordance with the appropriate permits granted by the respective Ministries of Environment and Mining Industries, awarded to the Company following the mandated cycles of positive State and community consultation, and bulk excavation was well advanced.

 

The programme remains on schedule, and the Company is confident it will meet its ESG, schedule, sample quality and budget commitments.

 

Cash Reserves and Zanaga Project Funding

The Company and Group had cash reserves of US$5.4 million as at 30 June 2026 and a cash reserve of US$3.7 million as at 17 September 2026.

 

Following the completion of the May 2026 Fundraise, the Company is in a significantly stronger financial position. Based on the current cost base at the Zanaga Project, the board of directors of ZIOC believes that the Company and its Group will be sufficiently positioned to support its operations in the near future.

 

The Fundraising has eliminated any material uncertainty that might have caused significant doubt regarding the Company and Group’s ability to continue as a going concern. Therefore, it believes that the Company will be able to realise its assets and settle its liabilities in the normal course of business. The Board is satisfied that the Company and Group will have sufficient funds to meet their own working capital needs up to, and beyond, twelve months from the date of approval of these accounts.

 

Financial overview

Results from operations

The financial statements contain the results for ZIOC for the first half of 2026. ZIOC made a loss in the half-year of US$4.2m compared to a loss of US$3.7m for the comparative period to 30 June 2025. A loss of US$7.2m was made for the full year ended December 2025. The loss for the 2026 half-year period comprised:

 

 

1 January to
30 June
2026

Unaudited

US$000

1 January to
30 June
2025

Unaudited

US$000

1 January to
31 December
2025

Audited
US$000

General expenses

(4,017)

(3,506)

(7,148)

Interest received

18

15

39

Net foreign exchange gain / (loss)

(207)

(1)

50

 

 

 

 


(Loss) before tax

(4,206)

(3,492)

(7,059)

Other comprehensive income (OCI)

(20)

(208)

(161)

Total Comprehensive income

(4,226)

(3,700)

(7,220)






 

General expenses of US$4.0m (H1-2025: US$3.5m), consisting of: Directors’ fees of US$1.3m (2025: US$0.1m). US$0.7m of the Directors’ fees paid in 2026 were in relation to deferred fees since Feb 2023, professional fees of US$1.4m (2025: US$2.5m) and US$1.3m (2025: US$0.9m) of other general operating expenses, including studies.

 


Financial position

ZIOC’s net asset value (“NAV”) of US$90.4m is comprised of US$85.3m exploration and evaluation assets, US$0.4m of property, plant and equipment (“PPE”), US$5.4m of cash balances and US$0.6m of other net current liabilities.

 

 

30 June 2026

Unaudited
US$m

30 June 2025

Unaudited
US$m

31 December 2025

Audited
US$m

Exploration and Evaluation

85.3

85.3

85.3

PPE

0.4

0.5

0.5

Cash

5.4

3.9

1.3

Other net current assets/(liabilities)

(0.6)

0.4

(0.5)

Non-current liabilities

(0.1)

(0.1)

(0.1)

Net assets

90.4

90.0

86.5

 

Cash flow

Cash balances have increased by US$4.1m since 31 December 2025. This was primarily driven by an issue of shares, which raised aggregate gross proceeds of £5.6m (approximately US$7.6m), less book runner fees of US$0.5m and payments of US$2.5m for operating activities.

 

30 June 2026

Unaudited
US$m

30 June 2025

Unaudited
US$m

31 December 2025

Audited
US$m

GBP Balances

3.3

0.4

0.3

 

 

 

 

*USD value of GBP balances

4.3

0.5

0.4

USD value of other currencies

0.5

0.1

0.2

USD balances

0.6

3.2

0.7

Cash Total

5.4

3.9

1.3

 

*Exchange rates applied:

Date

Historical rate

Inverse

30 June 2026

1 GBP = 1.325016 USD

1 USD = 0.754708 GBP

31 December 2025

1 GBP = 1.344764 USD

1 USD = 0.743625 GBP

30 June 2025

1 GBP = 1.3731 USD

1 USD = 0.728279 GBP


Consolidated Statement of Comprehensive Income for the six months ended 30 June 2026

 

Note

1 January
to

30 June 2026

Unaudited

 US$000

1 January
to

30 June 2025

Unaudited

 US$000

1 January

 to
31 December 2025

Audited

US$000

General and administrative expenses

 

(4,224)

(3,507)

(7,098)

Operating loss

 

(4,224)

(3,507)

(7,098)

Finance Income

 

18

15

39

(Loss) before tax

 

(4,206)

(3,492)

(7,059)

Taxation

5

-

-

 

(Loss) for the period

 

(4,206)

(3,492)

(7,059)

Other comprehensive income (OCI)

 

(20)

(208)

(161)

Total comprehensive (loss)

 

(4,226)

(3,700)

(7,220)

(Loss)/Earnings per share (Cents)

 

 

 

 

Basic

7

(0.5)

(0.5)

(0.9)

Diluted

7

(0.5)

(0.5)

(0.9)

 

Note: Other comprehensive income (OCI), Foreign currency translation loss for the period = $20k (H1-2025: $208k)

 

Loss and total comprehensive loss for the period are attributable to the equity holders of the Parent Company and are from continuing operations.


Consolidated Statement of Changes in Equity

for the six months ended 30 June 2026

 

 

 

 

Foreign

 

 

 

 

currency

 

 

Share

Retained

translation

Total

 

capital

earnings

reserve

Equity

 

US$000

US$000

US$000

US$000

Balance at 1 January 2025

319,057

 (233,435)

 (80)

85,542

Issued Capital

-

-

-

-

Issue of shares

21,572

-

-

21,572

Glencore buy-back

(15,000)

 

 

(15,000)

Equity settled share-based payment

1,620

-

-

1,620

Loss for the period

 -

(3,492)

 -

(3,492)

Other comprehensive (loss)/ income

 -

-

(208)

(208)

Total comprehensive (loss)/income

8,192

(3,492)

(208)

 4,492

 

 

 

 

 

Balance at 30 June 2025

327,249

 (236,927)

(288)

90,034

 

 

 

 

 

Issued Capital

-

 -

 -

-

Loss for the period

 -

(3,567)

 -

(3,567)

Other comprehensive (loss)/income

 -

 -

47

47

Total comprehensive (loss)/income

 

(3,567)

47

(3,515)

 

 

 

 

 

Balance at 31 December 2025

327,249

 (240,494)

(241)

86,514

 

 

 

 

 

Issue of shares

7,180

-

-

7,180

Equity settled share-based payment

1,351

-

-

1,351

    Joint bookrunner placing fees

(550)

-

-

(550)

    Loss for the period

-

(4,206)

203

(4,002)

Other comprehensive (loss)/income

 -

-

(20)

(20)

Total comprehensive (loss)/income

 7,981

(4,206)

183

 3,958

 

Balance at 30 June 2026  

335,230

 (244,700)

(58)

 

90,472

              


Consolidated Balance Sheet

as at 30 June 2026

 

 

 

30 June 2026  Unaudited

30 June 2025

Unaudited

31 December 2025

Audited

 

Note

US$000

US$000

US$000

Non-current asset

 

 

 

 

Exploration and evaluation assets

6

85,300

85,300

85,300

Property, plant and equipment

 

439

516

477

 

 

85,739

85,816

85,777

Current assets

 

 

 

 

Other receivables

 

28

419

403

Cash and cash equivalents

 

5,387

3,936

1,276

 

 

5,415

4,355

1,679

Total Assets

 

91,154

90,171

87,456

 

 

 

 

 

Non-current liabilities

 

 

 

 

Lease liability

 

54

79

61

 

 

 

 

 

Current liabilities

 

 

 

 

Loans and borrowings

 

-

-

-

Trade and other payables

 

612

62

865

Lease liability

 

16

-

16

Total liabilities

 

682

141

942

Net assets

 

90,472

90,034

86,514

 

Equity attributable to equity holders of the parent

 

 

 

 

Share capital

 

335,230

327,249

327,249

Retained earnings

 

(244,700)

(236,927)

(240,494)

Foreign currency translation reserve

 

(58)

(288)

(241)

Total equity

 

90,472

90,034

86,514

 

 

Consolidated Cash Flow Statement

for the six months ended 30 June 2026

 

 

 

1 January

1 January

1 January

 

 

to

to

To

 

 

30 June

30 June

31 Dec

 

 

2026

Unaudited

2025

Unaudited

2025

Audited

 

 

US$000

US$000

US$000

Cash flows from operating activities

 

 

 

 

Profit/(Loss) for the year

 

(4,206)

(3,492)

(7,059)

 

 

 

 

 

Adjustments for:

 

 

 

 

Share-based payments

 

1,351

-

1,620

Interest received

 

(18)

(15)

(39)

Depreciation add-back

 

49

25

55

(Increase)/decrease in other receivables

 

375

(64)

(48)

Increase/(decrease) in trade and other payables

 

(284)

(638)

178

Net exchange (profit)/loss

 

207

1

(50)

Net cash from operating activities

 

(2,526)

(4,183)

(5,343)

 

 

 

 

 

Cash flows from financing activities

 

 

 

 

    Glencore buy-back

 

-

(15,000)

(15,000)

    Issue of shares

 

7,180

23,010

21,572

    Joint bookrunner placing fees

 

(550)

-

-

    Principal portion of lease payments

 

(7)

-

14

Net cash from financing activities

 

6,623

8,010

6,586

 

 

 

 

 

Cash flows from investing activities

 

 

 

 

Interest received

 

-

-

-

Acquisition of property, plant and equipment

 

-

-

-

Net cash from investing activities

 

-

-

-

Net increase/(decrease) in cash and cash equivalents

 

4,097

3,827

1,243

Cash and cash equivalents at the beginning of period

 

1,276

110

110

Effect of exchange rate difference

 

14

(1)

(77)

Cash and cash equivalents at end of period

 

5,387

3,936

1,276

These financial statements were approved by the Board of Directors on 28 September 2026.


Notes to the financial statements

1. Business information and going concern basis of preparation

The Directors have prepared the accounts on a going concern basis. At 30 June 2026 the Company and Group had cash reserves of US$5.4m. The Company had cash reserves of US$3.7m as at 17 September 2026.

Following the completion of the 2026 Fundraise, the Company and Group are in a significantly stronger financial position. Based on the current cost base at the Zanaga Project, the board of directors of ZIOC believes that the Company and its Group will be adequately equipped to support its operations in the near future.

The Fundraising has removed any material uncertainty that could give rise to significant doubt over the Company and Group’s ability to continue as a going concern. Therefore, it believes that the Company and Group will be able to realise its assets and discharge its liabilities in the normal course of business. The Board is satisfied that the Company will have sufficient funds to meet its own working capital requirements up to, and beyond, twelve months from the approval of these accounts.

The Company and Group continue to review operational costs to conserve cash resources, with weekly management reviews on cash held and forecast.

 

2. Accounting policies

The principal accounting policies applied in preparing these financial statements are outlined below. These policies have been consistently applied to all the periods presented, unless otherwise stated.

3. Basis of preparation

These financial statements have been prepared in accordance with the International Financial Reporting Standards as adopted by the United Kingdom (“UK Adopted IFRS”). UK Adopted IFRS comprise standards and interpretations approved by the International Accounting Standards Board (“IASB”) and the International Financial Reporting Interpretations Committee (“IFRIC”) as adopted by the United Kingdom.

 

These consolidated financial statements comprise the Company and its subsidiaries (together referred as the ‘Group’).

In accordance with the AIM Rules for Companies, the condensed set of financial statements has been prepared in applying the accounting policies and presentation that were used in the preparation of the Company’s published consolidated financial statements for the year ended 31 December 2025. The comparative figures for the financial year ended 31 December 2025 are not the Company’s statutory accounts for that financial year. The Company’s auditors have reported on the 2025 accounts. The report of the auditors was (i) unqualified and (ii) did not include a reference to any matter to which the auditors drew attention by way of emphasis without qualifying their report.

4. Segmental reporting

The Company has one operating segment, its investment in the Zanaga Project, held through Jumelles.

5. Taxation

The Company is exempt from most forms of taxation in the British Virgin Islands (“BVI”), provided that the Company does not conduct business in the BVI and does not have any employees working in the BVI. All dividends, interest, rents, royalties and other expense amounts paid by the Company, and capital gains realised with respect to any shares, debt obligations or other securities of the Company, are exempt from taxation in the BVI.

The effective tax rate for the Group is 0.00% (as of December 2025: 0.00%).

​

6 Property, Plant and Equipment

 

 

Motor vehicles US$000

Right of use asset US$000

Fixtures and fittings US$000

Exploration assets US$000

Total US$000

Cost

 

 

 

 

 

Balance as at 30 June 2025

43

100

603

85,300

86,046

Additions

-

-

16

-

16

Disposals

-

-

(6)

-

(6)

Balance as at 31 December 2025

43

100

613

85,300

86,056

Additions

-

-

11

-

11

Disposals

-

-

-

-

-

Balance as at 30 June 2026

43

100

624

85,300

86,067

 

 

 

 

 

 

Depreciation

 

 

 

 

 

Balance as at 30 June 2025

43

29

158

-

230

Charge for period

-

14

41

-

55

W/back charge on disposals

-

-

(6)

-

(6)

Balance as at 31 December 2025

43

43

193

-

279

Charge for period

-

7

42

-

49

W/back charge on disposals

-

-

-

-

-

Balance as at 30 June 2026

43

50

235

-

328

 

 

 

 

 

 

Net book value

 

 

 

 

 

Balance as at 30 June 2025

-

71

445

85,300

85,816

Balance as at 31 December 2025

-

57

420

85,300

85,777

Balance as at 30 June 2026

-

50

389

85,300

85,739

The Right-of-use assets consist of office space and airstrip.

 

7. Loss per share

 

 

30 June

2026

Unaudited

US$000

30 June

2025

Unaudited

US$000

31 December 2025

Audited

US$000

Profit/(Loss) (Basic and diluted) (US$000)

(4,226)

(3,700)

(7,220)

Weighted average number of shares (thousands)

 

 

 

Basic and diluted

 

 

 

Issued shares at beginning of period

832,380

675,793

675,793

Shares bought back

-

(290,844)

(290,844)

Shares issued during the year

158,722

447,430

447,430

Weighted average of new shares issued

(123,450)

(176,195)

(26,188)

Weighted average number of shares at end of period – basic

867,651

656,185

806,192

 (Loss)/Earnings per share (Cents)

 

 

 

Basic

(0.5)

(0.5)

(0.9)

Diluted

(0.5)

(0.5)

(0.9)


8. Related parties

The following transactions occurred with related parties during the period:

 

 

 

Transactions for the period to:

 

 

Closing balance

 

 

30 June

2026

Unaudited

30 June

2025

Unaudited

31 December

2025

Audited

 

 

30 June

2026

Unaudited

30 June

2025

Unaudited

31 December

2025

Audited

 

US$000

US$000

US$000

 

US$000

US$000

US$000

Funding:

Glencore buy-back of shares *

-

15,000

15,000

 

 -

 -

 -

 

 

 

 

 

 

 

 

Shares issuance to directors

 

 

 

 

 

 

 

Martin Knauth (CEO)**

270

400

400

 

670

400

400

Clifford Elphick (Chairman & NED)***

344

-

-

 

344

-

-

Clinton Dines (NED)***

230

-

-

 

230

-

-

Jonathan Velloza (NED)***

230

-

-

 

230

-

-

Phillip Mitchell (NED)***

84

-

-

 

84

-

-

* As of February 2025, Glencore’s control was removed following the share buyback arrangement.

** The Company’s CEO, Martin Knauth, participated through share subscription in the May 2026 Equity Raise for a total amount of US$270,000 on the same terms as other investors. As Martin Knauth is a related party of the Company for the purposes of the AIM Rules, his participation in the Capital Raising was treated as a related party transaction for the purposes of Rule 13 of the AIM Rules.

*** Alongside the May 2026 Equity Raise, certain of the Company's directors agreed to convert US$888,134 of deferred director fees in aggregate into equity by the issuance of 16,426,241 new Ordinary Shares at the Issue Price of four pence per Ordinary Share.

 

Other related party transactions

On 10 February 2026, the Company announced the following:

RAM, controlled by Heeney Capital and Sir Mick Davis, a related party of ZIOC for the purposes of the AIM Rules by virtue of being an associate of a Substantial Shareholder of ZIOC[9]. RAM signed a binding term sheet ("The Binding Term Sheet") for a proposed strategic investment by RAM. Under the terms, ZIOC agreed to exclusivity provisions until 30 June 2026, a Break Fee of US$1.5m payable to RAM, and an Alternative Transaction Fee within 12 months after the exclusivity period, if applicable.

 

As the Break Fee and Alternative Transaction Fee summarised above are binding from execution of the Binding Term Sheet, the entry into the Binding Term Sheet with RAM is a related party transaction for the purposes of the AIM Rules for Companies. The Company's independent directors, being all of the directors with the exception of Philip Mitchell who is a representative of Greymont Bay, following due and careful consideration and in consultation with the Company's Nominated Adviser, Panmure Liberum Limited, consider the terms of the Break Fee and the Alternative Transaction Fee in the Binding Term Sheet to be fair and reasonable insofar as all shareholders of the Company are concerned.

On 14 May 2026, the Company announced the following:

 

The transaction with RAM is expected to conclude in July 2026, and should this occur, RAM has agreed and signed a letter with the Company that it will refund the Company any expenses incurred in connection with the bulk sampling programme and Zanaga Project in-country overheads from 1 July 2026 up to a maximum of US$2.00m (the "Side Letter"). There can be no certainty that the Transaction with RAM will be completed.

 

RAM is controlled by Heeney Capital and Sir Mick Davis, who are related parties of ZIOC for the purposes of the AIM Rules by virtue of being associates of a Substantial Shareholder of ZIOC9.

 

The entry into the Side Letter with RAM is a related party transaction for the purposes of the AIM Rules for Companies. The Company's independent directors, being all of the directors with the exception of Philip Mitchell, who is a representative of Greymont Bay, following due and careful consideration and in consultation with the Company's Nominated Adviser, Panmure Liberum Limited, consider the terms of the Side Letter to be fair and reasonable insofar as all shareholders of the Company are concerned.

 

 


[1] Compared to 2024 feasibility study update for Stage Two (12+18Mpta expansion)

[2] Based on a DRI pricing case (65% Fe CFR China US$115/t, 68% Fe CFR China US$130/t)

[3] Based on a Fe Pricing Case (65% Fe US$115/t, DRI premium per % Fe of US$5/t above 65% Fe); including twin pipeline system, thickened and dry tailings technologies, DRI product quality, 12Mtpa filter plant   and concentrate handling, and 12 Mtpa DRI hematite concentrator complex costing

[4] Based on a Fe Pricing Case (65% Fe US$115/t)

[5] Source BHP Economic and Commodity Outlook Aug 2026

[6] Stage Two process plant capital expenditure is estimated from 2024 Feasibility Study Cost Update

[7] 2024 Feasibility Study Update, estimated the total Stage One capital requirement as US$1.94 billion

[8] 2024 Feasibility Study Update, estimated the total Stage One processing cost of US$8.42 per tonne

[9] Heeney Capital controls and makes all investment decisions for Greymont Bay I LLC and Regatta HCRP I LP, which, in aggregate, own 25.26% of ZIOC's issued share capital. Therefore, RAM is a related party of ZIOC for the purposes of the AIM Rules.

This information is provided by RNS, the news service of the London Stock Exchange. RNS is approved by the Financial Conduct Authority to act as a Primary Information Provider in the United Kingdom. Terms and conditions relating to the use and distribution of this information may apply. For further information, please contact rns@lseg.com or visit www.rns.com.

RNS may use your IP address to confirm compliance with the terms and conditions, to analyse how you engage with the information contained in this communication, and to share such analysis on an anonymised basis with others as part of our commercial services. For further information about how RNS and the London Stock Exchange use the personal data you provide us, please see our Privacy Policy.
 
END
 
 
UK 100