Completion of DRI Process Plant Costing

AI SummaryClose X

Zanaga Iron Ore Company Limited has completed its project development strategy programme, confirming robust project economics for its Direct Reduced Iron (DRI) pellet feed concentrates. The updated financial model, as of December 2025, shows a Stage One capital expenditure estimate of US$2.17 billion, with a Net Present Value (NPV) of US$2.54 billion and an Internal Rate of Return (IRR) of 22.5%. For combined Stage One and Two, the capital expenditure is US$4.05 billion, with an NPV of US$4.90 billion and an IRR of 24.3%. The company is progressing towards a Final Investment Decision targeted for mid-2027, and the strategic investment by Red Arc Minerals is on track for finalisation of binding agreements in July 2026.