Silverking Project Phase 2 Drilling Update

Summary by AI BETAClose X

Xtract Resources Plc announced the completion of Phase 2 drilling at the Silverking Project, totaling 1,483.50 meters across 8 holes. Drilling focused on the Kopje prospect and infilling areas of the Main Body. Hole SKIDD025 intercepted approximately 3 meters of visible malachite within the Main Body. At the Kopje prospect, SKIDD022 intercepted roughly 8 meters of native copper stringers from 82 meters downhole, while SKIDD024 intercepted about 23 meters from 102 meters downhole of mixed copper mineralization. The company has met its initial expenditure commitment of US$500,000, allowing it to earn a 51% interest in the project. Xtract has the option to increase its interest to 70% by expending an additional US$1,000,000 over the subsequent two years.