Vatomina Optimisation Update

AI SummaryClose X

Total Graphite reports optimisation work at Vatomina with 48 diamond holes and 410 auger holes (1,362 samples) informing revised pit designs and improved grade control; a preliminary mine plan identifies approximately 2.36 million tonnes of potentially mineable material at an average grade of ~3.55% TGC and an indicative strip ratio of 0.88:1. Initial plans target 64,000 tonnes ore/month at 80% recovery, equating to ~1,800 tonnes graphite/month or ~22,000 tonnes per annum of saleable product, and a phased restart is targeted for January 2027, with further assays and offtake discussions underway.