THIS ANNOUNCEMENT CONTAINS INSIDE INFORMATION AS STIPULATED UNDER THE UK VERSION OF THE MARKET ABUSE REGULATION NO. 596/2014 WHICH IS PART OF ENGLISH LAW BY VIRTUE OF THE EUROPEAN UNION (WITHDRAWAL) ACT 2018, AS AMENDED. UPON PUBLICATION OF THIS ANNOUNCEMENT VIA A REGULATORY INFORMATION SERVICE, THIS INFORMATION IS CONSIDERED TO BE IN THE PUBLIC DOMAIN.
24 November 2026
Total Graphite plc
('Total Graphite' or the 'Company')
Vatomina Optimisation Update
Encouraging Initial Results as Restart Preparations Advance
Total Graphite plc (TGR.L), the specialist flake graphite company developing an integrated graphite mine-to-materials supply chain for the global energy transition, is pleased to provide an update on the optimisation programme at its Vatomina graphite project in Madagascar ("Vatomina" or the "Project"), following the temporary suspension of mining operations in June 2026.
The programme has substantially improved the Company's geological understanding of the areas under review and has allowed for revised preliminary pit designs. The Company is now progressing detailed operational planning and equipment readiness work, with a phased restart targeted for January 2027, subject to the completion of restart preparations.
Highlights
● Drilling programme completed: 48 diamond drill holes and 410 auger holes completed, with 1,362 samples analysed, supporting an updated geological interpretation and preliminary mine planning.
● Improved mining sequence: preliminary pit optimisation indicates opportunities to develop a more disciplined mining sequence, with improved grade control, ore blending and waste handling.
● Preliminary mine plan: the draft mine plan compilation identifies approximately 2.36 million tonnes of potentially mineable material across BK6, Pit B, Befotoroka and Tanandava at an average grade of approximately 3.55% total graphitic carbon ("TGC") and an indicative waste-to-ore strip ratio of 0.88:1.
● Targeted production: initial mine plans target a throughput of 64,000 tonnes of ore per month at 80% recovery, which would deliver approximately 1,800 tonnes of graphite per month, or approximately 22,000 tonnes per annum of saleable product.
● Exploration upside: additional planned exploration and pending assay results may provide opportunities to increase the volume of mineable material, particularly at Tanandava and Befotoroka and along the wider 4km mineralised trend.
● Restart preparations: work is focused on mine scheduling, plant readiness, maintenance, safety systems and operating plans.
● Customer engagement: sale and offtake discussions with existing and prospective customers have restarted.
● Next steps: the Company is targeting January 2027 for a phased restart of mining operations.
Operational Optimisation and Geological Work
The Company paused mining at Vatomina in June 2026 to address historical operational inefficiencies, including insufficient geological information, limited short-term mine planning, variable ore characteristics and equipment availability. Subsequent drilling, mapping and geological modelling have strengthened the basis for pit optimisation and selective mining. The work is intended to support more predictable plant feed, better waste management and more consistent processing performance.
Preliminary Whittle pit optimisation has been undertaken using the existing geological models and the additional drilling information. The Company is continuing to refine the models, pit-by-pit schedules, technical assumptions and mining parameters. The estimated mineable material is preliminary in nature and should not be construed as a formally declared Mineral Resource or Ore Reserve.
Preliminary Mine Plan
Table 1: Preliminary mine plan compilation by area
|
Area |
Ore (tonnes) |
Grade (% TGC) |
Strip ratio |
|
BK6 |
898,976 |
3.61 |
0.91 |
|
Pit B |
839,283 |
3.44 |
0.76 |
|
Befotoroka |
491,531 |
3.52 |
0.90 |
|
Tanandava |
129,184 |
4.06 |
1.51 |
|
Total |
2,358,974 |
3.55 |
0.88 |
Exploration Potential
The Company believes there is significant potential to extend the mine life of the known pits, in particular at Tanandava and Befotoroka, with a number of assay results pending and drilling ongoing. In addition, there is longer-term upside from the new areas identified by auger drilling along the 4km strike length, including the Tsaratanana prospect, as shown in Figure 1 below.

Figure 1: Vatomina Project – mining areas, 2026 drilling and prospect areas
Restart Preparation
Detailed monthly, weekly and daily mine schedules are being developed alongside the equipment rehabilitation and maintenance programme, processing plant readiness checks, road and waste-dump planning, and strengthened health, safety and environmental controls. The Company is targeting a phased restart in January 2027. In parallel, the Company has restarted conversations with existing and prospective customers, with the goal of securing purchase and sales contracts for upcoming production in the new year. A further update will be provided as the restart programme and timetable are finalised.
Graeme Chester, Head of Operations of Total Graphite plc, commented:
"The work undertaken since June has given us a much clearer understanding of the geology and the practical requirements for mining Vatomina efficiently. In particular, the additional drilling and updated pit modelling are allowing us to move away from reactive mining towards planned extraction, improved grade control and more consistent feed to the processing units. Our immediate priorities are to finalise the ore models and mine schedules, verify the key technical assumptions, restore equipment and processing readiness, and establish the operating disciplines required for a reliable restart. There remains further work to complete, but the progress made provides a significantly stronger technical basis for the next phase of operations."
Christian Dennis, Chairman of Total Graphite plc, commented:
"Our decision to pause mining at Vatomina was taken to address the operational issues that had historically constrained the Project's performance. The work completed over recent months has substantially improved our understanding of the mineralisation and has provided the foundation for a more disciplined and commercially focused mining strategy. We are encouraged by the preliminary optimisation results and the opportunities identified to improve mining efficiency and processing consistency, alongside the potential to evaluate extensions to the currently modelled areas. Our objective is not simply to restart production, but to establish an operation capable of generating sustainable positive cash flow. The team is focused on completing the necessary preparations for a phased restart targeted for January 2027, while maintaining appropriate technical and financial discipline. We look forward to updating shareholders as this work progresses."
ENDS
Enquiries:
|
Total Graphite plc Christian Dennis – Chairman Arun Somani – Chief Executive Officer Thomas Hill – Finance Director |
info@totalgraphite.com IR@totalgraphite.com |
|
AlbR Capital Limited – Financial Adviser David Coffman / Dan Harris |
+44 (0) 20 7469 0930 |