Madagascar Operations and Production Update

AI SummaryClose X

Total Graphite Plc has resumed operations at its Vatomina site in Madagascar following a successful fundraising, with shipments to international customers recommencing in April. Mining and processing activities are underway, and production from PCU1 and 2 is expected to restart in early June after relocation and facility expansions. The company has also completed the installation of a new dryer, increasing total drying capacity to 4.5 tons per hour, and is stockpiling ore to mitigate weather disruptions. A re-development plan for the Sahamamy project, potentially adding 18,000 tonnes per annum, is also in preparation. While fuel costs have risen by over 15% due to global events, the company is reviewing solar power options.