Cambay PSC Update

AI SummaryClose X

Synergia Energy Limited has provided an update on its Cambay PSC operations in India, reporting that workover operations on the C-64 well are complete and the well is producing an average of 23 bopd. The C-72 well workover is also finished with an SRP installed, and stable production levels will be announced soon, after which the rig will move to the C-74 well to conclude the three-well campaign. Drilling of the C-78 well has reached 603 meters in 12 ¼ inch hole size before casing was run, and drilling has now resumed in 8.5 inch hole size.