Synergia Energy Ltd announced an update regarding its Cambay PSC, where it holds a 50% working interest. Workover operations are set to commence imminently at the Cambay C-64 wellsite with the near completion of the rig up of the Aakash XIV 50T work over rig to install the sucker rod pump. Furthermore, the Kiri drilling rig mobilization to the C-54 wellsite area is approximately 50% complete, with the rig moving to the new C-78 drilling pad near the C-54 well location. The company will announce when drilling of the new C-78 well begins.