Commencement of On-Site Power & Issue of Warrants

Summary by AI BETAClose X

Sterling Digital plc has successfully commenced on-site electricity generation at its West Texas facility, utilizing two 2 MW Caterpillar natural gas generators to convert underutilised natural gas into power. These generators are currently undergoing commissioning and calibration, with each expected to deliver approximately 1.6 MW net power, sufficient to power 420 ASIC mining servers and approximately 193,500 terahashes per second of computing capacity. The company also announced the issuance of 501,000 warrants to a contractor at an exercise price of 6 pence per ordinary share, exercisable for five years.