Half-year Report

AI SummaryClose X

Sound Energy PLC announced its unaudited half-yearly report for the six months ended 30 June 2025. Post-period end, the operator finalized a $25 million debt facility from a local bank to fund the change to a traditional Engineering, Procurement and Construction (EPC) contract for the Phase 1 Micro LNG project, with Sound Energy's share being $5 million. First gas is expected by year-end 2025. The operator has commissioned an update of the Front-End Engineering & Design (FEED) study and selection of EPC contractor for Phase 2 Gas development. The Group's unaudited cash balance was approximately £2.1 million as at 31 August 2025. The Company is in discussion with Mana Energy to conclude the terms under which the Company will access up to $5.0 million of the facility to fund its share of the capital expenditure.