ANOH Gas Project Achieves First Gas

AI SummaryClose X

Seplat Energy Plc has announced that its 300 MMscfd ANOH gas project has achieved first gas, with wet gas production currently delivering 40-52 MMscfd of processed gas to the Indorama Petrochemical Plant and condensate production at 2.0-2.5 kboepd. The ANOH Gas Processing Company, a joint venture between Seplat Energy and NGIC, has commenced gas supply to Indorama under sales agreements, with preparations underway to supply Nigeria LNG. This project unlocks an estimated 4.6 Tcf of condensate-rich gas and is expected to generate material income streams for Seplat, reduce its carbon intensity, and contribute to its 2030 production targets. The ANOH gas plant was developed with zero routine flares and achieved this milestone over 17.5-million-man hours without a single recordable Lost Time Incident.