Reabold's Stage 1 feasibility study supports an integrated gas-to-power and co-located data centre at West Newton, indicating site generation of ~130 MWe (twelve 15 MWe engines, ten duty) to supply a ~67 MW IT data centre (peak demand ~103 MW) with first power targeted H2 2030. Concept capital expenditure is ~£1.1bn (£385m plant; £726m data centre); running power cost £44–58/MWh (£107–121/MWh all-in including capital recovery) versus UK grid reference £217.8/MWh for extra-large users, implying illustrative annual savings of £70–80m on ~719 GWh consumption. Costs are Class 5 concept estimates and development will be considered alongside gas-to-grid options.