Third FlexGen Funding & 7 MW Site Update

AI SummaryClose X

Quantum Data Energy PLC is advancing its third flexible generation power project, the 5 MW Bordersley project, towards financial close and construction by co-funding its capital expenditure with Power Balancing Services, with the project's capex estimated at £3.5m and expected to be income-generating by Q4 2026, building on the c. £290,000 per MW per annum revenue from its Pyebridge asset. Additionally, the company has completed technical and legal due diligence for the acquisition of a 7 MW brownfield flexible generation site, awaiting final grid connection confirmation expected around end March 2026. The company is also issuing broker warrants equivalent to 6% of the gross aggregate value of acceleration capital funding arranged by Fortified Securities.

Disclaimer*

UK 100

Latest directors dealings