Hindlip Project Significant Construction Progress

AI SummaryClose X

Mast Energy Developments PLC announced significant construction progress at its 7.5 MW Hindlip flexible generation power project, which is fully funded in partnership with Powertree. The Rolls-Royce mtu low-carbon reciprocating gas turbine engines have arrived, marking a critical step towards the commercial operations date. These engines, secured through Yellow Power, offer approximately 42% electrical efficiency. The project remains on track to complete construction and reach commercial operations in Q2 2026. Additionally, the company has applied for a block listing of 245,200,000 ordinary shares at par value of £0.001 each, related to the exercise of cash warrants issued pursuant to the Equity Fundraise announced on 11 July 2025. Admission is expected to be effective on 8 October 2025.