Hindlip Enters Final Phase; Pyebridge CM Award

AI SummaryClose X

Quantum Data Energy PLC announced that its Hindlip 7.5 MW flexible generation power project is in its final construction phase, with a forecast spend of approximately £4.67 million against a £5 million capex budget, representing a saving of £330,000, though grid connection energisation is delayed to July 2026, pushing commercial operations to Q3 2026. Additionally, the company's Pyebridge 8.1 MW asset secured an additional Capacity Market contract for the 2029/2030 delivery year at a clearing price of £27.10/kW/pa, estimated to yield approximately £217,400 annually, bringing total contracted CM income to £1,924,108. The company also reported that 116,099,808 prepaid warrant shares were issued during the six-month period ending March 17, 2026, leaving 600,334 shares remaining under the block listing.