Bordesley Construction Commenced and on Schedule

AI SummaryClose X

Quantum Data Energy PLC has announced that construction of its Bordesley 5 MW flexible generation power project has commenced at pace and is progressing on schedule and on budget, with commercial operations targeted for Q4 2026. The project, fully funded through a partnership with Power Balancing Services Ltd and external debt, remains within its approved capital expenditure budget of £3.6 million. Key construction milestones, including the award of civils and electrical packages, ordering of Caterpillar gensets, and initiation of gas and grid connections, were all completed in March 2026, with site mobilisation scheduled for May 2026.