TSXV Final Acceptance for Helium & CO2 Plant

Summary by AI BETAClose X

Pulsar Helium has received TSXV final acceptance for an equipment-supply Proposal with Chart for a helium liquefaction plant (861 litres/hour; ~7.5 million litres liquid helium/year; ~200 million scf/year) and a CO2 capture plant (300 tonnes/day; >100,000 tonnes liquid CO2/year); aggregate equipment-supply price is US$85.5 million payable in stages, with US$5,025,000 already paid from cash (5% initial milestone US$4,275,000 plus US$750,000 LNTP; total LNTP credited US$1,000,000); Milestone 2 of US$8.55 million is due 31 Jan 2027 (company intends to fund from existing cash), equipment manufacture is scheduled over ~two years after Milestone 2, the price excludes installation/taxes/site costs, and cancellation charges can reach up to 70%.