Pulsar Helium Inc. announced that Jetstream #1 flowed over 1.3 million cubic feet per day under well-head compression. The company has secured a drilling contract with Timberline Drilling Inc. to drill up to ten wells at the Topaz project, with drilling commencing in late September and targeting depths up to approximately 3,937 feet. Gas samples from Jetstream #1 have been collected over a 9-day interval, totaling 14 samples for laboratory analysis. The Jetstream #1 dataset will be delivered to Chart Industries for production scenario modeling. An advance payment of US$70,000 has been paid to secure the rig and crew availability. Jetstream #2 exhibited an initial gas flow of roughly 40-50 thousand cubic feet per day.