Completion Jetstream 5 & Mobilization Jetstream 6

AI SummaryClose X

Pulsar Helium Inc. has completed drilling Jetstream #5 at its Topaz Project in Minnesota to a depth of 3,839 feet, encountering multiple pressurized gas influxes with the highest recorded bottom-hole pressure at 2,857 feet reaching approximately 1,292 psi. The company has mobilized to commence drilling Jetstream #6, aiming to increase the Topaz resource size. A coordinated testing program for Jetstream #3 and #4 is anticipated to begin in late February 2026, lasting approximately six weeks per well. Despite encountering difficulties with 1,239 feet of drill string left in Jetstream #5, the company plans to address this in April to allow for full logging and flow testing.