Dubhe-1 Operational Update - Ready for Completion

Summary by AI BETAClose X

Pantheon Resources announced that hydraulic fracture stimulation at the Dubhe-1 well is scheduled to commence around the week of September 29th and is expected to take approximately two weeks. The Dubhe-1 horizontal lateral was drilled to a total measured depth of 15,800 ft, with approximately 5,200 ft within the SMD-B target reservoir, exceeding the pre-drill target of 3000-4000 ft. Production testing will follow the stimulation, utilizing a temporary production system, with an initial cleanup phase anticipated to last up to ten days. The company plans an extended flow test to gather crucial data for future development decisions.