The information contained within this announcement is deemed to constitute inside information as stipulated under the retained EU law version of the Market Abuse Regulation (EU) No. 596/2014 (the "UK MAR") which is part of UK law by virtue of the European Union (Withdrawal) Act 2018. The information is disclosed in accordance with the Company's obligations under Article 17 of the UK MAR. Upon the publication of this announcement, this inside information is now considered to be in the public domain.
Oriole Resources PLC
(“Oriole Resources” or the “Company”)
Bibemi Gold Project Update
New Ultra-fine Grinding Processing Flowsheet Shows a Significant 38% Reduction in Sulphide Only Processing Plant Capital Cost
Oriole Resources (AIM:ORR), the AIM quoted exploration and development company focused on Central and West Africa, is pleased to announce an update on its 50% owned Bibemi gold project (“Bibemi” or the “Project”) in north-eastern Cameroon. The Company’s third-party consultant, Stirling Process Engineering Limited (“Stirling”) has now completed a Scoping Study, based on low-level technical and economic assessments, on the recently reported ultra-fine grinding (“UFG”) mineral processing flowsheet for sulphide material only (see announcement dated 2 November 2026), to enable a comparison with the previously reported pressure oxidation (“POX”) mineral processing flowsheet (see announcement dated 15 May 2025).
Highlights
Table 1. Overview of key parameters between the POX and UFG processing methods
|
Parameter |
|
Units |
POX |
UFG |
Variance |
|
|
Units |
% |
|||||
|
Plant |
Throughput |
tpa |
190,800 |
207,956 |
17,156 |
+9.0 |
|
Gold recovery |
% |
85.0 |
78.7 |
-6.3 |
-7.4 |
|
|
Gold production |
Oz pa |
10,000 |
10,000 |
- |
- |
|
|
CAPEX |
Plant |
US$m |
35.8 |
22.1 |
-13.7 |
-38.3 |
|
Project total |
US$m |
60.4 |
46.7 |
-13.7 |
-22.7 |
|
|
OPEX |
Plant |
US$m |
30.1 |
29.7 |
-0.46 |
-1.5 |
|
Project Total |
US$/oz |
574.7 |
616.9 |
42.4 |
+7.3 |
|
|
Notes: All costs to scoping study levels of confidence, ±30% POX study used power cost of US$100/MWh; UFG used US$200/MWh |
||||||
Commenting Chief Executive Officer of Oriole Resources, Martin Rosser, said:
“The key economic findings of the UFG Scoping Study for Bibemi are highly encouraging. Not only are there notable operational and potential financing benefits, but there is a large capital cost saving on the processing plant of US$13.7m, with only a slightly increased processing operating cost per ounce of gold produced.
“Although the new findings mean that updating the PEA will take slightly longer than earlier forecast, once completed it could show a significant improvement in Project economics by adopting the UFG processing method. Importantly, we have been awaiting this new information and material development to bolster and support the current Bibemi exploitation licence application negotiation effort whilst we finalise the PEA in parallel, which we look forward to reporting on in due course.”
Further Details
At the 177km2 Bibemi orogenic gold project in the North region of Cameroon, the Company's exploration to date has identified shear-hosted gold mineralisation at four main prospects - Bakassi Zone 1, Bakassi Zone 2, Lawa West and Lawa East - within an approximately 12km long mineralised hydrothermal system at surface.
The Project has a Mineral Resource Estimate (“MRE”) of 6.96Mt at 2.06g/t Au for 460,000oz contained Au, 100,000oz Au of which is classified as Indicated, and the remaining classified as Inferred under the JORC Code. The MRE, which is located entirely within the BZ1-MRE zone, is calculated using a 0.40g/t Au cut-off grade and is constrained by a US$2,750/oz gold price pit shell (see announcement dated 15 May 2025). In addition to the MRE, the Company has also reported an Exploration Target across the Bibemi project of between 3.0 and 5.0Mt with an average grade of between 1.50 and 2.50g/t Au, for between 145,000 and 400,000oz contained gold. The potential quantity and grade of the Exploration Target are conceptual in nature. There has been insufficient exploration in the areas covered by the Exploration Target to estimate a Mineral Resource, and it is uncertain whether further exploration will result in the estimation of a Mineral Resource.
The Company has submitted an Exploitation Licence Application (“ELA”) for the Project, which is envisaged to be a small-scale, open pit mine that would target an optimised open-pit scenario of 89,000oz Au, largely centred on the 100,000oz Au Indicated Resource. As part of the ELA an initial PEA of this optimised scenario, assuming a 7-year mine life, at ~10,000oz pa Au average annual production, was included within the ELA (see announcement dated 16 December 2025), and is considered to be at Scoping Study level.
The initial PEA assumed an 85% gold recovery which reflected results from prior metallurgical testwork on sulphide material, at SGS South Africa between 2022 and 2024, that outlined a provisional mineral processing flowsheet to treat the gold-telluride mineralogy, comprising flotation, POX of the float concentrate, and leaching of the pressure oxidation residue (see announcement dated 15 May 2025).
Further metallurgical testwork completed this year enabled the development of an alternative processing flowsheet which comprised flotation, UFG of the float concentrate (to 80% of material passing at 10μm size or less) and then leaching of the UFG material (announcement dated 2 November 2026). The UFG flowsheet targets the sulphide material only, which contains ~97% of the gold within the ~89,000oz targeted by the optimised pit scenario at Bibemi (see announcement dated 16 December 2025). The modest amount of oxide material would be stockpiled for potential processing later.
The Company today reports that Stirling has completed a Scoping Study for the UFG flowsheet which has enabled a direct comparison between the UFG and POX flowsheets. Both flowsheets were designed based on an anticipated gold production rate of 10,000oz pa and used certain assumptions such as labour, power, and administration costs relevant at the date of each study. The information in this announcement that relates to mining, processing, metallurgical recovery, infrastructure, capital and operating cost estimates is based on data and assumptions developed for the purposes of a Scoping Study and does not constitute Ore Reserves or JORC‑reportable estimates.
A comparison of key statistics from the two estimates is presented in Table 1. The costs are presented to Scoping Study level, with ±30% accuracy. The UFG flowsheet represents a lower overall gold recovery (approximately 79%) compared to POX (approximately 85%) although this likely reflects a lower sample head grade from the most recent metallurgical testwork.
The UFG flowsheet presents a significant 38% reduction in plant CAPEX of US$13.7m, being estimated at US$22.1m compared to US$35.8m for the POX processing method, reducing total expected Project CAPEX to US$46.7m. The OPEX costs for both methods are broadly similar, with the UFG scenario being slightly cheaper per tonne compared to POX (US$29.7/t vs US$30.1/t), albeit 7% more expensive on a per oz of gold basis (~US$617/oz vs ~US$575/oz).
The Company also recognises that gold recoveries may be improved in the UFG flowsheet through further investigation and optimisation of the flotation design and leaching conditions. Optimisation studies into reducing the pre-aeration time and reducing the free cyanide level in the leach are being considered. These studies may enable a reduction in the consumption of cyanide and lime reagents, which represent a significant portion of the total processing costs.
ALS Ltd. Australia is also completing final testwork to assess whether further recovery of gold from the flotation tailings might be possible and this testwork will conclude shortly.
Considering the significant CAPEX cost savings, the potential for further gold recovery improvement and cost savings with optimisation of the flowsheet, and the logistical and technical benefits of the UFG flowsheet (see announcement dated 2 November 2026), UFG is considered to represent a more viable processing option at Bibemi than POX.
The Company is now in the process of updating the PEA based on the UFG flowsheet, refreshed earthmoving costs due to the oxide material pre-strip, increased plant throughput and slightly lower overall gold processing plant recovery. The Company aims to publish this as soon as possible.
For further information on Bibemi, including maps and a JORC Table 1, please see the following page of the Company's website https://orioleresources.com/projects/bibemi/.
Competent Persons Statement
The information in this announcement that relates to mineral processing and certain economic parameters is based on data compiled by David Lunt, an independent consultant to Oriole. Mr Lunt is a Director of Stirling Process Engineering and has senior and technical management experience within the extractive metallurgical consulting/contracting industry, including as Technical Director GRD Minproc (now Wood Ltd.), General Manager of Minproc's Sydney office and Process Manager (Minproc and Kvaerner). Mr Lunt consents to the inclusion in the report of the matters based on his information in the form and context in which it appears.
The information in this announcement that relates to Mineral Resource estimates, Exploration Targets and resource pit optimisation is based on and fairly represents information compiled by Robert Davies (EurGeol, CGeol), an independent consultant to Oriole Resources. Mr Davies is a Director of Forge International Limited and has sufficient experience that is relevant to the style of mineralisation and type of deposit under consideration, and to the activity being undertaken, to qualify as a Competent Person as defined in the JORC Code (2012 Edition). Mr Davies consents to the inclusion in this announcement of the matters based on his information in the form and context in which it appears.
Enquiries:
|
Oriole Resources Plc |
Tel: +44 (0)23 8065 1649 |
|
Martin Rosser / Bob Smeeton / Claire Bay |
|
|
Strand Hanson Limited (Nomad) |
Tel: +44 (0)20 7409 3494 |
|
Christopher Raggett / James Spinney / Edward Foulkes |
|
|
Zeus Capital Limited (Broker) |
Tel: +44 (0)20 3829 5000 |
|
Simon Johnson / James Bavister |
|
|
IFC Advisory Ltd (Financial IR & PR) |
Tel: +44 (0)20 3934 6632 |
|
Tim Metcalfe / Graham Herring / Florence Staton |
Glossary and Abbreviations
|
µm |
Micron (0.001 millimetres) |
|
Au |
Gold |
|
BZ1 |
Bakassi Zone 1 |
|
Bibemi |
Bibemi orogenic gold project |
|
CAPEX |
Capital expenditure |
|
Company |
Oriole Resources PLC |
|
ELA |
Exploitation Licence Application |
|
g/t |
Grammes per tonne |
|
JORC |
Joint Ore Reserves Committee |
|
JORC Code |
2012 Edition of the Australasian Code for Reporting of Exploration Results, Mineral Resources and Ore Reserves |
|
km |
Kilometre |
|
km2 |
Square kilometre |
|
m |
Metres |
|
Moz |
Million ounces |
|
MRE |
Mineral Resource Estimate |
|
Mt |
Million tonnes |
|
MWh |
Megawatt hour |
|
OPEX |
Operating Expenditure |
|
Oriole Resources |
Oriole Resources PLC |
|
oz |
Troy ounce of gold |
|
Oz pa |
Troy ounce per annum |
|
PEA |
Preliminary Economic Assessment |
|
POX |
Pressure oxidation |
|
Project |
Bibemi orogenic gold project |
|
SGS |
SGS South Africa (Pty) Ltd |
|
Stirling |
Stirling Process Engineering Ltd |
|
tpa |
Tonnes per annum |
|
UFG |
Ultra-fine grinding |
|
US$/oz |
US dollar per troy ounce |
|
US$/t |
US dollar per tonne |
Notes to Editors
Oriole Resources PLC is an AIM-quoted gold exploration and development company, with projects in Central and West Africa. It is currently focused on projects in Cameroon.
At its district scale Central Licence Package (CLP) in Cameroon, the Company has identified multi-kilometre long gold anomalies, including at its flagship Mbe project. At Mbe, the Company has published a global JORC Inferred MRE of 1.66Moz contained gold at MB01, consisting of 1.30Moz at 1.01g/t Au for the MB01-S deposit, and 360,000oz at 1.05g/t Au for the MB01-N deposit. Following the completion of the MB01-N drilling programme, and by meeting various financial commitments, BCM International (“BCM”) has earned a 50% interest in the Mbe project, and Oriole has recently completed a corporate restructuring to confirm the Company's and BCM's respective 50% interest in Mbe. Drafting of a JV partnership agreement is nearing completion.
The Company has also reported a Resource of 460,000oz contained gold at 2.06g/t Au in the JORC Indicated and Inferred categories at its 50% owned Bibemi project in Cameroon, where it has applied for an Exploitation Licence. In November 2025, BCM completed its earn-in to give it a 50% interest in Bibemi by meeting certain payment conditions, including spending US$4 million on exploration.
At its 85%-owned Wapouzé limestone project in north-eastern Cameroon, the Company has recently published a maiden JORC Inferred Resource of 32.2Mt with weighted average grades of 50.33wt% CaO, 1.13wt% MgO and 6.06wt% SiO₂. The Company has also recently announced the submission of an ELA and ESIA for the project and is ultimately looking to achieve an income that could be used as additional funding for Oriole's gold-focused exploration work in Cameroon.
At the Senala gold project in Senegal, AGEM Senegal Exploration Suarl (“AGEM”), a wholly owned subsidiary of Managem Group, has completed a six-year earn-in to acquire an approximate 59% beneficial interest in the Senala Exploration Licence by spending US$5.8 million. The Company has reported a Resource of 155,000oz contained gold at 1.26g/t Au (using a gold price of US$1,800/oz) in the JORC Inferred category for the Faré South prospect. Best results to date include 20.00m grading 31.13 g/t Au including 10.00m grading 60.98 g/t Au from RC drilling and 59.60m grading 2.20 g/t Au from diamond drilling. A JV agreement was signed in July 2026 with a US$2 million work programme planned for the current field season.
The Company also has several interests in companies operating in East Africa and Turkey that could give future cash payments.
For further information please visit www.orioleresources.com, @OrioleResources on X