NWQ Copper Project – Big One Follow-Up Program

Summary by AI BETAClose X

New Frontier Minerals reports structural mapping and six rock-chip assays at a historical costean ~400m southwest of Big One Pit 1 that confirm a strike extension of the mineralised trachyte dyke and fault; selective results include stockpile up to 7.76% CuO, costean rubble up to 1.67% CuO and in-situ shear up to 1.30% CuO, plus a sample with 0.15% CuO and 594ppm Co; structural measurements (~80° towards 060°) align with Big One pits and the area is heritage-cleared (Sept 2020) and untested by drilling but will be included in the next drill program and further geophysics; Big One hosts a JORC MRE of 2.1Mt @ 1.1% Cu (21,886t contained Cu, 0.45% cut-off); samples are selective and not representative of the resource.