Operations Updates: Bonanza Mine

Summary by AI BETAClose X

Nativo Resources Plc has provided an operations update for its Bonanza Gold Mine, confirming temporary access to underground workings and ongoing geological sampling, with 100 surface samples dispatched and over 40 underground samples planned. A mining contractor is expected to be appointed next week, with mobilisation in January 2026, a slight delay attributed to the Christmas period and high industry activity. Explosives permit applications have been submitted, and camp refurbishment, expanding capacity from 20 to 40 personnel, is progressing. The final geological report is now forecast for February 2026, though this is not expected to delay the mining restart as operations will commence at existing faces.