Operations Update: Gold Ore Processing Plant

Summary by AI BETAClose X

Nativo Resources Plc has signed final contracts to manage, design, complete, and operate the part-built La Patona Gold Ore Processing Plant in Peru, which will occupy approximately 15 hectares and is expected to cost $1.8 million. While contract negotiations caused a 15-week delay, the plant is now anticipated to be constructed and commissioned by H2 2026, featuring a dual circuit flotation and cyanidation operation with a smelter. Phase 1 will have a solids throughput of 220 tonnes per day, with the cyanidation circuit capable of 70 tonnes per day, and is projected to recover 1.4 kg to 1.7 kg of gold per day at full capacity, based on expected head grades.

Disclaimer*

UK 100

Latest directors dealings