La India Development Update

AI SummaryClose X

Metals Exploration Plc has provided an update on its La India gold project in Nicaragua, reporting that construction is 40% complete, ahead of the planned 35% by mid-March 2026. The total project budget has been revised to US$171 million, an increase from US$165 million primarily due to electrical infrastructure costs, and is funded by free cash flow from the Runruno mine and an undrawn US$30 million gold pre-pay facility, with first gold production still targeted for December 2026. Expenditure to the end of February 2026 was approximately US$80 million, in line with forecasts. A significant cost saving of US$6.2 million was achieved on the 138kV substation through a collaborative arrangement with ENATREL.