Update as Cabaçal Advances Towards FID

Summary by AI BETAClose X

Meridian reports Cabaçal has entered pre-construction with AFRY appointed as EPCM, licences and access secured for a 24.3 km, 138 kV power line, long‑lead orders placed and off‑site upgrades on track; the DFS shows an after‑tax NPV5 of USD 2.1 billion, IRR 108%, pre‑production CAPEX USD 322 million with capital repayment in 0.9 years, AISC USD 1,056/oz gold equivalent and average annual production of 183,526 oz gold equivalent (years 1–5). Meridian has committed USD 30.9 million to pre‑construction, holds ~USD 90 million treasury and has received >20 indicative financing proposals including several fully funded USD 400 million proposals covering debt, cost overrun funding and equity.