Mendell Helium plc has provided an operational update detailing progress across its Rost 1-26, Rost 2-26, and Brobee assets. The Brobee saltwater disposal well is performing exceptionally well, operating under a full surface vacuum and permitted for up to 10,000 barrels per day, offering low-OpEx disposal for the Rost wells. At Rost 1-26, perforations have been doubled to 4ft, and a larger 640 surface pumping unit is being installed to increase fluid handling capacity to 900 barrels per day, with a sand-tolerant pump installed to extend operational life. Rost 2-26 has an optimised Halliburton Electrical Submersible Pump and VFD unit delivered, with high-capacity electrical infrastructure being installed to support ESP, surface processing, and helium purification facilities. Wellhead helium concentrations remain stable at approximately 5.1%.