Bougouni Lithium Project Quarterly Update

Summary by AI BETAClose X

Kodal Minerals Plc reported its Bougouni Lithium Project quarterly update for the three months ended 30 June 2026, with production of 26,174 dry metric tonnes (DMT) of spodumene concentrate grading 5.34% Li₂O, bringing year-to-date production to 53,195 DMT. The mining operator made an initial US$13 million loan repayment, and a third shipment of approximately 20,400 DMT of spodumene concentrate arrived at Hainan port, with an interim payment of $34.4 million received for 95% of its estimated value, calculated at US$2,304 per DMT. Mining activity improved with additional equipment, though processing plant performance was temporarily affected by crushing circuit maintenance in May, returning to normal in June. A fourth shipment of approximately 24,200 DMT departed on 11 July 2026.