Appointment of Adviser and Tulu Kapi Update

Summary by AI BETAClose X

KEFI Gold and Copper plc has appointed Stifel Nicolaus Europe Limited as financial adviser and joint broker, and announced that all key milestones for the Tulu Kapi Gold Project are on or ahead of schedule, with principal contracts now finalised. The company has replaced a US$15 million short-term working capital facility with US$15 million of long-term subsidiary level equity ranking capital, comprising a US$10 million gold royalty and US$5 million in Ethiopian preference shares, without impacting project economics. This strategic financial restructuring strengthens the balance sheet and de-risks project execution, maintaining project NPV and cash flows, while the Tulu Kapi project remains on track for commissioning in late 2027 and full production by mid-2028. Stifel will also act as sponsor for KEFI's planned move to the Main Market of the London Stock Exchange in 2027.

Disclaimer*

Kefi Gold and Copper PLC
26 May 2026
 

26 May 2026

 

KEFI Gold and Copper plc

 

("KEFI" or the "Company")

 

Appointment of Adviser and Tulu Kapi Update

 

KEFI Gold and Copper plc (AIM: KEFI), the gold and copper exploration and development company with projects in the Federal Democratic Republic of Ethiopia and the Kingdom of Saudi Arabia, is pleased to announce the appointment of Stifel Nicolaus Europe Limited ("Stifel") as financial adviser and joint broker to the Company and to provide a Tulu Kapi development update. 

 

Highlights

·    Stifel appointed as joint broker and sponsor for the Company's planned move to the Main Market of the London Stock Exchange

·    All key Project milestones at Tulu Kapi tracking at or ahead of schedule

·    All principal contracts at Tulu Kapi now finalised

·    Tulu Kapi financing packaged strengthened by eliminating the reliance on a short-term working capital facility

·    3-year working capital facility replaced by long-term funding of 8-year+ subsidiary level equity ranking capital

·    Project economics for KEFI shareholders maintained while de-risking Project execution and preserving upside

 

Tulu Kapi Update

 

KEFI is pleased to provide an update on recent developments at the Company's high-grade/high-recovery Tulu Kapi Gold Project (the "Project" or "Tulu Kapi")

 

Project implementation

·    On time and on budget: All onsite and offsite Project workstreams are tracking on or ahead of the Tulu Kapi development schedule, targeting commissioning from late 2027 for full production mid-2028

·    Engineering work progression: Lycopodium has issued 14 detailed engineering packages to KEFI for final approval, progressing the design and execution definition phase of the build

·    Procurement of long-lead items: The semi-autogenous grinding (SAG) mill, one of the highest-value and the longest-lead items in the processing plant, has been ordered

·    Community resettlement programme underway: Land for the new housing has been prepared and construction of the 350 replacement houses is underway. Once the first phase of resettlement is complete, bulk earthworks at Tulu Kapi will commence

·    Grid power linkup underway: The 47km electrical connection of the main national grid to the Project site is in construction. Construction of the first of two substations is well advanced, and all of the new towers have been delivered to the Tulu Kapi district

·    Heavy equipment access roads under construction: Two new access roads are being constructed to connect the bitumen highway to the Project site. This will enable heavy equipment mobilisation for bulk earthworks and plant construction along a shorter and more direct all-weather route

·    EPCM contract packages finalised: Detailed contract packages with Lycopodium covering engineering, procurement and construction management have been finalised

·    Mining and earthworks contract packages finalised: Detailed contract packages with BCM Group have been finalised for bulk earthworks, drilling and mining services

·    First gold production outlook maintained: Onsite, offsite, engineering, procurement and contracting milestones are all progressing in line with, or ahead of plan, and the Project remains on course for commissioning from late 2027 and for full production mid-2028. All principal contracts have now been negotiated

 

Project financing

Following the closing of the Tulu Kapi project equity capital package in March 2026, the Company has successfully executed its strategy to preserve flexibility for risk mitigation. It has replaced US$15 million of short-term working capital funding with US$15 million of long-term subsidiary level equity ranking capital without any impact on Tulu Kapi Project economics. The Project NPV and cash flows remain consistent with previous disclosure, but the Company now has far more balance sheet flexibility.

·    Elimination of requirement for short-term US$15 million working capital facility: No requirement to draw down on the existing 3-year working capital facility. Provides additional financial flexibility and risk mitigation for the Tulu Kapi ramp-up

·    US$15 million in long-term funding secured: Short-term capital replaced by 8-year+ subsidiary level equity ranking capital in the form of Ethiopian preference shares and a gold royalty. Both components have been finalised on exactly the same terms as those previously outlined in the Company's announcement on 11 February 2026:

US$10 million in equity ranking royalty at subsidiary level secured: Gold royalty arranged with Cyprus-based specialist financier Mithril Royalties Limited on the same terms as US$20 million royalty signed with Chancery Royalty, but for half the amount of gold

US$5 million in Ethiopian preference shares signed at subsidiary level: On the same terms as the US$6 million already signed

·    Economic metrics maintained: This capital structure rearrangement has no impact on the Tulu Kapi economic metrics; estimated NPV and cash flows remain consistent with previous disclosures

·    Standby liquidity preserved: The original US$15 million working capital facility remains available and is retained on standby for additional financial flexibility

·    Senior debt drawdown scheduled in Q3 2025: This minimises debt financing costs, whilst having no impact on project construction

 

Appointment of Adviser

 

In addition to its role as Joint Broker, Stifel will act as Sponsor for the Company's planned move to trading on the Equity Shares - Commercial Company segment of the Main Market of the London Stock Exchange, which is expected to occur in 2027.

 

Enquiries

 

KEFI Gold and Copper plc

 

Harry Anagnostaras-Adams (Executive Chairman)

Tel: +357 2225 6161

John Leach (Finance Director)

 

SP Angel Corporate Finance LLP (Nominated Adviser)

Tel: +44 20 3470 0470

Caroline Rowe / Adam Cowl

 

Stifel Nicolaus Europe Limited (Financial Adviser and Joint Broker)

Ashton Clanfield / Varun Talwar 

 

Tavira Financial Limited (Joint Broker)

Tel: +44 20 7710 7600

 

 

Tel: +44 20 7100 5100

Oliver Stansfield / Jonathan Evans

 

IFC Advisory Ltd (Financial PR and IR)

Tel: +44 20 3934 6632

Tim Metcalfe / Florence Staton

 

Further information can be viewed at https://www.kefi-goldandcopper.com

This information is provided by RNS, the news service of the London Stock Exchange. RNS is approved by the Financial Conduct Authority to act as a Primary Information Provider in the United Kingdom. Terms and conditions relating to the use and distribution of this information may apply. For further information, please contact rns@lseg.com or visit www.rns.com.

RNS may use your IP address to confirm compliance with the terms and conditions, to analyse how you engage with the information contained in this communication, and to share such analysis on an anonymised basis with others as part of our commercial services. For further information about how RNS and the London Stock Exchange use the personal data you provide us, please see our Privacy Policy.
 
END
 
 
UK 100

Latest directors dealings