25 November 2026
Kavango Resources plc
(“Kavango” or the “Company”)
Hillside Project Power Infrastructure Successfully Energised
Kavango Resources plc (LSE: KAV, VFEX: KAV.VX), the Southern Africa-focused metals exploration and gold development company, is pleased to announce the successful energisation of a new one megavolt-ampere (“MVA”) transformer at its Hillside Gold Project ("Hillside") in Zimbabwe.
The new transformer increases Hillside's total installed transformer capacity from 250 kilovolt-amperes (“kVA”) to 1.25MVA, a fivefold increase, and will supply grid electricity directly to the Hillside Project. The Company expects this to improve the stability of power supply to Hillside and to reduce energy costs.
Highlights
Jasper Musadaidzwa, Chief Executive Officer, commented: "The successful energisation of our new transformer represents another important milestone as we continue to build out infrastructure at Hillside. Increasing our installed transformer capacity fivefold to 1.25MVA will enable us to supply grid electricity directly to our operations, which we expect will improve power supply stability and reduce our energy costs.
"Reliable, cost-effective power is fundamental to building an efficient gold production operation. Together with our backup generation capacity, this infrastructure provides a stronger foundation for our existing operations and planned expansion of gold processing capacity."
Power Infrastructure Upgrade
The successful energisation of the new 1MVA transformer on the 19th of November increases Hillside's total installed transformer capacity from 250kVA to 1.25MVA.
The upgraded infrastructure supplies electricity from the national grid directly to the Hillside Project, which the Company expects to provide a more stable and more cost-effective source of power. As at 10 November 2026, Zimbabwe’s Minister of Energy and Power Development reported to Parliament that the country had experienced 325 consecutive days without load shedding due to insufficient power supply.
Separately, Hillside has 500kVA of backup generation capacity, providing an alternative source of electricity during interruptions to grid supply.
Supporting Future Production Growth
The power infrastructure upgrade forms part of Kavango's ongoing investment in the development of Hillside and its transition towards larger-scale gold production.
Following the successful commissioning of the Company's 50 tonne per day gold processing plant, announced on 2 November 2026, Kavango continues to strengthen the infrastructure required to support increased processing capacity.
The additional electrical capacity, combined with anticipated improvements in power supply stability and expected lower energy costs, supports the Company's strategy to develop efficient and scalable gold production operations at Hillside.
The Company will provide further updates as development progresses.
Forward-Looking Statements
This announcement contains forward-looking statements, including statements regarding the expected benefits of the Company’s power infrastructure at the Hillside Gold Project, the anticipated stability and cost of electricity supply, expected unit operating costs, the continued operation of the Company’s gold processing plant and the Company’s plans to expand gold processing capacity and develop larger-scale gold production at Hillside. Such statements reflect the Company’s current expectations and are subject to risks and uncertainties, including the availability, reliability and cost of grid electricity supply in Zimbabwe, changes in electricity tariffs and in the terms on which power is supplied, technical and operational risk, risks associated with the commissioning, operation and ramp-up of processing facilities, funding risk, licence and permitting risk, political, regulatory and country risk in Zimbabwe, foreign exchange and currency convertibility risk, and commodity price risk. Actual results may differ materially from those expressed or implied by these forward-looking statements. No assurance can be given that the anticipated benefits of the power infrastructure upgrade will be realised, that power supply stability will improve, that energy or unit operating costs will be reduced, or that any expansion of gold processing capacity will be achieved. Save as required by applicable law or regulation, the Company undertakes no obligation to update any forward-looking statement.
Further information in respect of the Company and its business interests is provided on the Company's website at www.kavangoresources.com
For further information, please contact:
|
Kavango Resources plc Donald McAlister +44 7887 481228
|
SP Angel Corporate Finance LLP
(Corporate Broker) +44 203 470 0470 |
BlytheRay Ltd |