Implementation of Mine Plan at Molefe

Summary by AI BETAClose X

Jubilee Metals Group PLC has announced an updated near-term mine plan for its Molefe Mine, integrating Pit 2 and 3 to increase the mining rate of the copper reef to 60,000 tonnes per quarter from the current 15,000 tonnes per quarter, following approximately four months of development work involving the removal of 400,000 cubic metres of overburden. This expansion aims to deliver an average copper grade of 1.4% TCu to surface, with high-grade ore trucked to the Sable refinery and medium-grade ore processed on-site before refining. The company is also initiating a Phase 2 drilling programme to define the eastern extension of the resource, targeting construction and production within the next 12 months.