Galactica Project Update

AI SummaryClose X

Helium One Global Ltd has provided an update on the Galactica Project, with the operator reporting that the Pinon Canyon Plant's integrated operations are scheduled to commence next week, and the amine unit will be operational for CO2 removal. The company anticipates CO2 liquefaction and load components will be added in H1 2026, and sales arrangements for spot helium have been made with discussions for long-term contracts progressing well. Tie-ins for the State-9 and State-16 wells are complete, and expansion of the gathering system for the Jackson-2 well is underway, supporting a ramp-up through 2026 aimed at increasing production and revenues.