Halo Minerals PLC has announced an updated Competent Person's Report for its Playa Verde copper tailings project, increasing the Ore Reserve by 5.4% to 33.94 Mt, which supports an after-tax Net Present Value (NPV10) of US$174.3 million and an Internal Rate of Return (IRR) of 45.6%. The total Mineral Resources are now 53.44 Mt at 0.24% Cu. Optimisation efforts have improved the Ore Reserve case NPV10 to US$190.6 million and the full-resource management case NPV10 to US$295.5 million, with preliminary potential to increase Ore Reserves by 25% to 30% through further technical work.

Disclaimer*

Halo Minerals PLC
16 October 2026
 


HALO MINERALS PLC

("Halo Minerals", the "Company" and, together with its subsidiaries, the “Group”)

 

Increased Ore Reserve and improved project economics

Halo Minerals plc (AIM: HALO), the copper development company focused on recovering critical minerals from legacy mining waste, announces an updated Competent Person’s Report (“CPR”) for its Playa Verde copper tailings project in Chile. The CPR increases the Ore Reserve by 5.4% to 33.94 Mt and, on the Ore Reserve alone, supports an after-tax NPV10 of US$174.3 million and an after-tax IRR of approximately 46%.

Key highlights

  • Ore Reserves increased by 1.74 Mt, or approximately 5.4%, to 33.94 Mt at 0.25% Cu, containing 83,626 tonnes of in-situ fine copper.
  • The Ore Reserve base case produces an after-tax NPV10 of US$174.3 million and an after-tax IRR of 45.6% with project level average annual free cashflows of US$56 million.
  • Total Mineral Resources are 53.44 Mt at 0.24% Cu, inclusive of Ore Reserves, containing 127,911 tonnes of in-situ fine copper.
  • A separate full-resource management case, using the full 53.44 Mt onshore Mineral Resource, produces an after-tax NPV10 of US$267.5 million and an after-tax IRR of 48%.
  • Identified CAPEX and reagent-cost optimisation increases the after-tax NPV10 to US$190.6 million for the Ore Reserve case and US$295.5 million for the full-resource management case.
  • EMI identifies preliminary potential to increase Ore Reserves by approximately 25% to 30% in the short term, subject to further technical work and confirmation of modifying factors.

 

The CPR was prepared by EMI-Ingenieros y Consultores S.A. (“EMI”). It incorporates the 2026 basic engineering update and Class 3 capital and operating cost estimates prepared by BIOS Mining & Infrastructure, together with updated Mineral Resource and Ore Reserve classifications. The Mineral Resource and Ore Reserve estimates are reported in accordance with the JORC Code (2012).

Economic cases at a glance

The cases below are presented separately so that the current Ore Reserve economics are not confused with management assumptions or potential future upside.

Case

Basis

After-tax NPV10

After-tax NPV8

After-tax IRR

Ore Reserve base case

33.94 Mt Ore Reserve; US$6.20/lb Cu; US$3,700/oz Au; US$92.8m initial CAPEX; acid at US$200/t

US$174.3m

US$195.9m

45.6%

Optimised Ore Reserve case

Ore Reserve base case plus US$6m CAPEX saving and acid at US$150/t

US$190.6m

US$212.7m

51%

Full-resource management case

Full 53.44 Mt onshore Mineral Resource; not based solely on Ore Reserves

US$267.5m

US$307.4m

48%

Optimised full-resource management case

Full-resource management case plus US$6m CAPEX saving and acid at US$150/t

US$295.5m

US$337.7m

54%

 

Andrew Dennan, Chief Executive Officer of Halo Minerals, commented:

“The updated CPR provides an independent reassessment of Playa Verde. The declared Ore Reserve has increased to 33.94 million tonnes and, on that Ore Reserve alone, the updated work supports an after-tax NPV10 of US$174.3 million and an after-tax IRR of approximately 46%.

“The CPR also sets out the potential beyond the current Ore Reserve. This includes the wider onshore Mineral Resource, identified capital and operating cost improvements, and the potential to convert further resources into reserves. These costed opportunities demonstrate the potential to deliver a project NPV10 in the orders of magnitude of around $300 million. The project also has a longer-term ambition to incorporate the surf and bay zones, which host the potential to significantly increase the project resource base, and will be modelled at an appropriate time in the future.

“With the updated technical work substantially advanced, Halo is focused on completing the remaining optimisation, commercial and financing work required to progress Playa Verde towards a final investment decision.”

Mineral Resources and Ore Reserves

The updated statement is summarised below. Mineral Resources are inclusive of Ore Reserves and must not be added to them.

 

Mineral Resources and Mineral Reserves Statement 2026 Update

Summary of Reserves and Resources by Categorisation


 

The September 2026 recategorisation incorporated an additional 1.74 Mt of Measured and Indicated Resources into the extraction plan without changing the deposit geometry or mine-plan envelope. This increased Ore Reserves by approximately 5.4%.

Ore Reserve base case

The principal economic assessment is based on the declared Ore Reserve of 33.94 Mt only. It uses a 10% discount rate and the assumptions and results below.

Parameter

Value

Ore Reserve plant feed – life of mine

33.94 Mt

Weighted average copper grade

0.243% Cu

Overall copper recovery

72.0%

Copper price

US$6.20/lb

Gold price

US$3,700/oz

Initial CAPEX

US$92.8m

Recovered copper – life of mine

59.4 kt

Total revenue – life of mine

US$774.6m

Total OPEX – life of mine

US$292.5m

Operating cash flow – life of mine

US$482.1m

Pre-tax NPV10

US$234.2m

Pre-tax IRR

55.5%

After-tax NPV10

US$174.3m

After-tax NPV8

US$195.9m

After-tax IRR

45.6%

 

The sensitivity analysis indicates that project economics are most sensitive to copper price, copper recovery and operating costs.

Production programme

The production programme assumes a consolidated extraction and processing rate of approximately 5.0 Mtpa and an initial operating period of seven years. The current schedule sends approximately 34.8 Mt to the plant, comprising the declared Ore Reserve and approximately 0.86 Mt of Inferred Resource. The 0.86 Mt of Inferred Resource is not included in the declared Ore Reserve or in the Ore Reserve economic case summarised above.

Capital and operating costs

The 2026 Class 3 engineering update, authored by BIOS Mining and Infrastructure (“BIOS MI”) as announced by the Company on 28 September 2026, estimates initial project capital expenditure of US$92.8 million, excluding VAT. The estimate assumes a third-party dredging service model, under which dredging equipment is treated as an operating cost rather than initial capital expenditure. BIOS MI has also noted the opportunity to reduce initial CAPEX by US$6 to 10 million via value engineering and competitive procurement tendering processes which would represent an upside for the Company to capture versus the below analysis.

 

Investment category

US$ million

Dredging operation

1.8

Process plant

9.7

Leaching plant

32.8

Flotation

19.8

Infrastructure

3.0

Services

2.6

Facilities and other

0.6

G&A

8.8

Total EPC contract

79.0

Indirect costs

5.8

Owner’s costs

1.9

Contingency

6.1

Total investments

92.8

 

Base-case operating costs are estimated at approximately US$2.20/lb of copper produced and marketed. Sulphuric acid is the dominant reagent cost. The base case assumes US$200/t; BIOS MI has identified potential to reduce this to US$150/t through a long-term supply contract.

Potential reserve growth and further upside

EMI considers that the geometry and mineralogical continuity of the artificial tailings deposit indicate potential, on a preliminary basis, to increase Ore Reserves in the short term by approximately 25% to 30%. This is subject to statistical review, infill drilling, block-model updating, resource recategorisation and confirmation of the relevant modifying factors. On that basis, potential Ore Reserves could increase to approximately 42.4 Mt to 44.1 Mt.

The current JORC Mineral Resource covers the beach area only. Historical subsea drilling and bathymetry indicate additional mineralised tailings in the surf and bay zones, subject to further exploration, sampling and regulatory approvals.

Further NPV upside of approximately US$4.4 million may be available through optimisation of the dredging starting point and extraction sequence, subject to operational and community constraints.

Ore processing and extraction

The process route combines acid leaching, solvent extraction and electrowinning with flotation. Weathering and oxidation have converted a substantial proportion of the copper into acid-soluble oxides and chlorides, while the sulphide component is recovered through flotation. The combined flowsheet has an estimated overall copper recovery of approximately 72%.

Tailings extraction is planned by dredging, using an electric dredging wheel in a controlled multi-lane pond. Reprocessed tailings are intended to be redeposited behind the advancing dredging operation. The design reflects the non-cohesive nature of the tailings and is intended to balance technical feasibility, operating continuity and cost control.

Qualified Person

The information in this announcement relating to Mineral Resources, Ore Reserves, mine planning, metallurgy and economic evaluation for the Playa Verde Copper Tailings Project is extracted from the updated CPR prepared for Halo Minerals PLC by EMI-Ingenieros y Consultores S.A., dated 15 October 2026. EMI is an independent Chilean mining engineering and consulting firm with experience in resource and reserve audits and feasibility-level studies.

The CPR was compiled under the supervision of Mr Orlando Rojas Vercelotti, Civil Mining Engineer, a Competent Person as defined in the JORC Code (2012) and acts as a Qualified Person under the AIM Rules - Note for Mining, Oil & Gas Companies, who has sufficient experience relevant to the style of mineralisation and type of deposit under consideration and to the activity being undertaken.

Mr Rojas Vercelotti has reviewed the information contained in this announcement, to the extent that it relates to matters summarised from the CPR, and has consented to the inclusion of such information in the form and context in which it appears.

This announcement contains inside information for the purposes of article 7 of the UK Market Abuse Regulation. The Directors of the Company are responsible for the release of this announcement.

 

Enquiries:

Halo Minerals PLC

Via Tavistock below

Andrew Dennan, Chief Executive Officer

Frank Jackson, Chief Financial Officer

 

Information@HaloMinerals.co.uk

 

www.halominerals.co.uk

 

 

 

Cairn Financial Advisers LLP (NOMAD)

+44 20 7213 0880

Ludovico Lazzaretti

Liam Murray

James Western

 

 

 

Global Investment Strategy (Broker)

+44 20 7048 9045

Christopher Kipling

 

 

 

Tavistock (Public Relations)

+44 20 7920 3150

Nick Elwes

Gareth Tredway

Jack Seward

 

 

Appendix A - Glossary Technical Terms

 

Chemical Elements

Au – Gold

Cu – Copper

 

Exploration, Mining and Reporting Terms

Competent Person (CP) – Individual responsible for the technical report who meets experience, competence and professional membership requirements.

CPR – Competent Person Report.

CRM – Certified Reference Material.

Exploration Target (JORC 2012) – Statement of exploration potential expressed as ranges of tonnes and grade where insufficient information exists to estimate a Mineral Resource.

IP – Induced Polarisation.

M&I Resources – Measured and Indicated Resources.

QA/QC – Quality Assurance / Quality Control. RC – Reverse Circulation drilling.

 

Units, Symbols and Financial Abbreviations

Metric Units

t – Metric tonne (1,000 kg) kt / Kton – Thousand tonnes

Mt – Million tonnes

%Cu – Copper grade by weight

 

Imperial / U.S. Customary Units

oz (troy) – 31.1035 g lb – 0.453592 kg short ton (st) – 907.185 kg

long tonne (lt) – 1,016.05 kg Financial

US$ – United States dollars

K US$ – Thousand U.S. dollars

M US$ / US$M / Mill US$ – Million U.S. dollars

CAPEX – Capital Expenditure

OPEX – Operating Expenditure

 

AIM (Alternative Investment Market) Terminology

AIM – Growth market of the London Stock Exchange

AIM Rules – Regulatory framework for AIM-listed companies

AIM Admission Document – Required disclosure for listing

AIM Nomad – Nominated Adviser ensuring compliance

AIM-listed Company – Company admitted to AIM

 

 

 

Forward Looking Statements

This announcement contains forward-looking statements relating to expected or anticipated future events and anticipated results that are forward-looking in nature and, as a result, are subject to certain risks and uncertainties, such as general economic, market and business conditions, competition for qualified staff, the regulatory process and actions, technical issues, new legislation, uncertainties resulting from potential delays or changes in plans, uncertainties resulting from working in a new political jurisdiction, uncertainties regarding the results of exploration, uncertainties regarding the timing and granting of prospecting rights, uncertainties regarding the Company's ability to execute and implement future plans, and the occurrence of unexpected events. Actual results achieved may vary from the information provided herein as a result of numerous known and unknown risks and uncertainties and other factors.

This information is provided by RNS, the news service of the London Stock Exchange. RNS is approved by the Financial Conduct Authority to act as a Primary Information Provider in the United Kingdom. Terms and conditions relating to the use and distribution of this information may apply. For further information, please contact rns@lseg.com or visit www.rns.com.

RNS may use your IP address to confirm compliance with the terms and conditions, to analyse how you engage with the information contained in this communication, and to share such analysis on an anonymised basis with others as part of our commercial services. For further information about how RNS and the London Stock Exchange use the personal data you provide us, please see our Privacy Policy.
 
END
 
 
UK 100

Latest directors dealings