Two additional projects receive Gate 2 offers

Summary by AI BETAClose X

Gresham House Energy Storage Fund plc has received new grid connection offers for its Lister Drive (57MW) and Ocker Hill (240MW) projects, bringing clarity to 86% of its Three-year Plan pipeline. While the first three projects totalling 397MW are expected to reach financial close and begin construction imminently for completion in 2027, the connection offers for Lister Drive and Ocker Hill are now scheduled for 2029, indicating a delay in achieving the target £150m run-rate EBITDA by the end of 2027. The company will host a Capital Markets Day on May 28, 2026, to provide updated Three-year Plan targets and discuss revised build-out phasing.