Operational Update

AI SummaryClose X

Goldstone Resources reported encouraging progress at its Homase Mine, with a recent gold pour of 11.06 kilograms, equivalent to approximately 355.6 ounces of gold doré, during the week of August 18, 2025. The company is maintaining focus on delivering 48,000 tonnes of agglomerated stacked ore per month and moving back into Pit 1, expecting to maintain an average grade of 1 g/t. Expansion plans for the heap leach are progressing, with civil engineering design complete and awaiting a construction permit. The geotextile and geomembrane liner have been ordered and paid for, with delivery anticipated by the end of September 2025.