Upgrade of JORC MRE For Tailings Storage Facility

Summary by AI BETAClose X

Goldplat upgraded the JORC MRE for its GPL TSF to a Measured Mineral Resource of 2.34 Mt at 1.74 g/t Au (gross 130,560 oz; net attributable 2.12 Mt and 118,330 oz, reflecting Goldplat's 90.63% interest), versus 2016's 81,959 oz in 1.43 Mt; the increase largely reflects ~1 Mt of tailings deposited through December 2023 and full-footprint drilling which classified all material as Measured. No cut-off grade applied and a bulk density of 1.34 t/m³ was used; concept study and feasibility to follow, break-even metallurgical recovery estimated at ~14% with preliminary potential 20–25% (SGS testwork ongoing), and processing remains subject to significant technical, regulatory, funding and execution uncertainty.