Hussar EP513 Update

Summary by AI BETAClose X

Georgina Energy reports progress toward drilling Hussar EP513: it has ordered wellhead equipment from Cactus Wellhead and notified Ensign for mobilisation of Ensign Rig 970, with all civil engineering and site preparation completed and site security fencing installed. The company has submitted formal seismic programme applications to DMPE and Traditional Owners for a proposed ~30-day lightweight survey (budget to be finalised and intended to be funded by Harlequin Energy) and is developing alternative heavy-equipment access routes; spud date is pending. An independent estimate shows unrisked net attributable 2U prospective resources of 283 BCF helium, 315 BCF hydrogen and 2.93 TCF gas, implying c.US$152 billion unrisked in‑situ value.