Georgina Energy PLC has announced that civil engineering contractors have completed pre-drill site and road access works for the Hussar EP513 Prospect, a significant subsalt helium, hydrogen, and hydrocarbon prospect in Australia. However, unseasonal record-breaking rainfall has caused delays in the mobilization of the Ensign 970 drill rig and associated contractors due to ongoing road closures and flooding. The company is incurring costs due to these delays and is awaiting improved weather and road conditions for safe mobilization, with further updates to follow regarding a revised spud date.

Disclaimer*

Georgina Energy PLC
23 September 2026
 

 

23 September 2026

 

THIS ANNOUNCEMENT RELATES TO THE DISCLOSURE OF INFORMATION THAT QUALIFIED OR MAY HAVE QUALIFIED AS INSIDE INFORMATION WITHIN THE MEANING OF (A) ARTICLE 7(1) OF UK MAR IN SO FAR AS IT RELATES TO ORDINARY SHARES ISSUED BY GEORGINA ENERGY PLC

 

Georgina Energy plc

("Georgina", "Georgina Energy" or the "Company")

 

Hussar EP513 Prospect Update

 

Georgina Energy Plc, (LSE: GEX.L), a helium, hydrogen and natural gas exploration and development company with strategic permits in Australia, confirms that civil engineering contractors have completed all pre-drill site and road access works to enable the contracted Ensign 970 drill rig to test of this exciting prospect, which has 330 km² of areal closure and is one of the largest subsalt helium, hydrogen and hydrocarbons prospects remaining untested in onshore Australia.

 

Highlights

 

  • The drilling pad, water well, Turkey’s nest and sump are completed and lined with waterproof sheeting.
  • The water well has been completed and tested on a long term test delivering some 260,000 litres per day.
  • The 20 inch conductor pipe has been drilled and cemented in place.
  • The Hussar airstrip has been cleared, gravelled and rolled to provide a 1,400m length airstrip capable of operation in virtually any weather.
  • Access roads have been cleared, graded and gravelled and compacted where necessary.
  • Mobilisation planning with the Ensign Rig 970 has been almost completed.

 

Delays for Drill program

 

The civil engineers and water well drillers have begun demobilising from site however there has been unseasonal record-breaking rain in the district which has prevented all of the contractors’ equipment and trucks being able to demobilise. The Company remained optimistic along with Ensign that mobilisation would occur in September as planned but the continuing road closures have further complicated the program along with flooding.

 

Leonora, a town close to the start of the main access road recorded a record-breaking 58.8mm of rain in the 24 hours to 9:00 am on Monday, September 7, 2026. This resulted in:

 

  • The wettest September day on record for a month that typically averages less than 10mm.
  • The heaviest spring daily rainfall ever recorded in Leonora.
  • The wettest day overall in nine years, delivering over a quarter of the town's average annual rainfall in just one day.
  • The second-wettest September on record for the town overall in 129 years of data collection.
  • Ongoing road closures in within the Wiluna Shire Council: www.wiluna.wa.gov.au
  • Ongoing restrictions on heavy vehicle access (RAV-Restricted Access Vehicles): www.wiluna.wa.gov.au have prevented any movement of overwidth, over length or over weight vehicles at any times when roads are wet. This means that prime movers hauling triple trailers are banned from large sections of the road network to Hussar within the Shire.

The Company have held ongoing discussions with Ensign Drilling and both parties have concluded that the mobilisation of the drilling rig to the Hussar site represents an extraordinarily high chance of being halted “en route” currently. Furthermore, the Company risks incurring material standby charges from not only Ensign but the other service contractors necessarily involved in this operation which would make any continuing delays costly especially as such time delays cannot be reliably forecast in the current circumstances.

 

The Company is hopeful of mobilising the drilling rig and associated service contractors in a timely fashion subject to safety constraints including the weather and road conditions to allow for the safe mobilisation of the equipment and personnel.

 

Further updates will follow as we progress towards a revised spud date with additional site photos which can be viewed by shareholders on the Georgina website.

 

Anthony Hamilton, Chief Executive Officer of Georgina Energy, commented:

“Georgina’s contractors have done an excellent job of preparing the site and access roads to enable the mobilisation of the Ensign 970 drill rig to enable the drill testing of this exciting prospect, however, unexpected heavy rainfall and road closures have caused the targeted drill program to be delayed and we look forward to making further announcements in due course.”

 

ENDS

 

Enquiries

 

Georgina Energy

Tony Hamilton

via georginaenergy@apcoworldwide.com

Mark Wallace

 

 

 

 

 

Tavira Financial Ltd - Financial Adviser and Joint Broker

Jonathan Evans

+44 (0)20 3833 3719

Oliver Stansfield

 

 

 

 

 

 

 

 

 

 

Financial PR via georginaenergy@apcoworldwide.com

Violet Wilson

+44 (0)203 757 4980

Georgia Edmonds

 

 

Notes to Editors

 Georgina Energy aims to become a leading player in the global energy market and is focused on establishing itself among the top producers of helium and hydrogen worldwide. With a strategic approach and leveraging the experienced management team's expertise, Georgina Energy aims to capitalize on opportunities in these critical energy sectors.

 

Georgina Energy has two principal onshore interests held through its wholly owned Australian subsidiary, Westmarket O&G.  The first, the Hussar Prospect is located in the Officer Basin in Western Australia and Westmarket O&G holds a 100% working interest in the exploration permit.  The second, the EPA155 Mt Winter Prospect, is located in the Amadeus Basin in the Northern Territory, subject to completion of the Sale Agreement Georgina Energy will hold a 100% working interest.

 

With the resource potential of the EP513 Hussar and the EPA155 Mt Winter projects in line with market demand trends, Georgina Energy is well-positioned to capitalize on the growing gap between supply and demand for hydrogen, helium and gaseous hydrocarbons in Australia and globally.

 

For more information visit https://www.georginaenergy.com

This information is provided by RNS, the news service of the London Stock Exchange. RNS is approved by the Financial Conduct Authority to act as a Primary Information Provider in the United Kingdom. Terms and conditions relating to the use and distribution of this information may apply. For further information, please contact rns@lseg.com or visit www.rns.com.

RNS may use your IP address to confirm compliance with the terms and conditions, to analyse how you engage with the information contained in this communication, and to share such analysis on an anonymised basis with others as part of our commercial services. For further information about how RNS and the London Stock Exchange use the personal data you provide us, please see our Privacy Policy.
 
END
 
 
UK 100

Latest directors dealings