23 September 2026
THIS ANNOUNCEMENT RELATES TO THE DISCLOSURE OF INFORMATION THAT QUALIFIED OR MAY HAVE QUALIFIED AS INSIDE INFORMATION WITHIN THE MEANING OF (A) ARTICLE 7(1) OF UK MAR IN SO FAR AS IT RELATES TO ORDINARY SHARES ISSUED BY GEORGINA ENERGY PLC
Georgina Energy plc
("Georgina", "Georgina Energy" or the "Company")
Hussar EP513 Prospect Update
Georgina Energy Plc, (LSE: GEX.L), a helium, hydrogen and natural gas exploration and development company with strategic permits in Australia, confirms that civil engineering contractors have completed all pre-drill site and road access works to enable the contracted Ensign 970 drill rig to test of this exciting prospect, which has 330 km² of areal closure and is one of the largest subsalt helium, hydrogen and hydrocarbons prospects remaining untested in onshore Australia.
Highlights
Delays for Drill program
The civil engineers and water well drillers have begun demobilising from site however there has been unseasonal record-breaking rain in the district which has prevented all of the contractors’ equipment and trucks being able to demobilise. The Company remained optimistic along with Ensign that mobilisation would occur in September as planned but the continuing road closures have further complicated the program along with flooding.
Leonora, a town close to the start of the main access road recorded a record-breaking 58.8mm of rain in the 24 hours to 9:00 am on Monday, September 7, 2026. This resulted in:
The Company have held ongoing discussions with Ensign Drilling and both parties have concluded that the mobilisation of the drilling rig to the Hussar site represents an extraordinarily high chance of being halted “en route” currently. Furthermore, the Company risks incurring material standby charges from not only Ensign but the other service contractors necessarily involved in this operation which would make any continuing delays costly especially as such time delays cannot be reliably forecast in the current circumstances.
The Company is hopeful of mobilising the drilling rig and associated service contractors in a timely fashion subject to safety constraints including the weather and road conditions to allow for the safe mobilisation of the equipment and personnel.
Further updates will follow as we progress towards a revised spud date with additional site photos which can be viewed by shareholders on the Georgina website.
Anthony Hamilton, Chief Executive Officer of Georgina Energy, commented:
“Georgina’s contractors have done an excellent job of preparing the site and access roads to enable the mobilisation of the Ensign 970 drill rig to enable the drill testing of this exciting prospect, however, unexpected heavy rainfall and road closures have caused the targeted drill program to be delayed and we look forward to making further announcements in due course.”
ENDS
Enquiries
Georgina Energy
|
Tony Hamilton |
|
|
Mark Wallace
|
|
|
|
|
Tavira Financial Ltd - Financial Adviser and Joint Broker
|
Jonathan Evans |
+44 (0)20 3833 3719 |
|
Oliver Stansfield |
|
|
|
|
|
|
|
|
|
|
|
|
|
Financial PR via georginaenergy@apcoworldwide.com
|
Violet Wilson |
+44 (0)203 757 4980 |
|
Georgia Edmonds |
|
Notes to Editors
Georgina Energy aims to become a leading player in the global energy market and is focused on establishing itself among the top producers of helium and hydrogen worldwide. With a strategic approach and leveraging the experienced management team's expertise, Georgina Energy aims to capitalize on opportunities in these critical energy sectors.
Georgina Energy has two principal onshore interests held through its wholly owned Australian subsidiary, Westmarket O&G. The first, the Hussar Prospect is located in the Officer Basin in Western Australia and Westmarket O&G holds a 100% working interest in the exploration permit. The second, the EPA155 Mt Winter Prospect, is located in the Amadeus Basin in the Northern Territory, subject to completion of the Sale Agreement Georgina Energy will hold a 100% working interest.
With the resource potential of the EP513 Hussar and the EPA155 Mt Winter projects in line with market demand trends, Georgina Energy is well-positioned to capitalize on the growing gap between supply and demand for hydrogen, helium and gaseous hydrocarbons in Australia and globally.
For more information visit https://www.georginaenergy.com