Hussar EP513 Equipment Procurement

Summary by AI BETAClose X

Georgina Energy has completed long‑lead procurement for the Hussar EP513 well — including approximately 3,200 metres of surface, intermediate and production casing and production tubing, a VersaFlex expandable liner hanger and float/cementing equipment — and had previously ordered the wellhead; Ensign 970 has been notified to mobilise with drilling planned for ~50 days to ~3,200m once rig mobilisation and rig‑up are complete. Site works are finished, formal DMPE and Traditional Owner approvals are pending for a ~30‑day seismic survey (budget proposed to be funded by Harlequin Energy), and an independent report estimates unrisked net 2U resources of 283 BCF helium, 315 BCF hydrogen and 2.93 TCF gas (c. US$152bn in‑situ).