Hussar EP513 Drill Operations Site Inspection

Summary by AI BETAClose X

Georgina Energy PLC has provided an update on its Hussar EP513 drill operations, with technical consultants commencing RFQs for the planned drilling program and preliminary indications that the Explorer Rig is suitable and potentially available by February 25th. Company representatives will conduct site inspections on February 12th, 2026, to evaluate work programs including airstrip repairs, road access, and pad preparation, which are crucial for commencing drilling to test the Townsend Formation and fractured basement lithologies. The drilling program and necessary site infrastructure works will be funded non-dilutively by Harlequin and their partners through a structured Offtake funding arrangement, with drilling anticipated in Q3 2026.