Key Permit Approval for Andacollo

AI SummaryClose X

Galantas Gold Corporation has secured the final key permitting approval from Chile's National Geology and Mining Service for the operational reactivation of the Ripios Dumps at its Andacollo Gold Project, extending the validity of existing permits for facilities VII, VIII, and IX. This approval confirms approximately 16.4 million tonnes of authorized capacity remain, representing 81% of the total approved capacity, and allows for continued operation under previously approved conditions for up to four years or until capacity is reached. The company is proceeding with operational readiness activities, prioritizing local engagement, and has all necessary regulatory approvals to resume operations, though a production decision is still subject to further review, financing, and board approval.