Resilient underlying operational performance, with a growing pipeline of opportunities
Corilis Digital Infrastructure Limited (the Company), the FTSE 250 specialist owner and operator of digital infrastructure, announces its unaudited interim results for the six months ended 30 September 2026, its first as Corilis.
Highlights:
|
– |
Portfolio EBITDA up 3.5%, on revenue growth of 18.1%, on a constant currency basis1, to £87.3 million and £212.9 million. Revenue growth was driven by contractual price escalators, new multi-year contracts, project revenue and acquisitions, partially offset by anticipated customer churn and project phasing. EBITDA growth was partly diluted by the lower-margin connectivity business acquired from BT Ireland but supported by continued cost discipline. |
|
– |
Total return of 4.3% before the impact of FX, 1.4% after (six months to 30 September 2025: 5.6% and 10.0%). Every portfolio company recorded a positive local currency return, even after increases in discount rates (weighted average increase of 25 basis points). A stronger pound produced a net FX loss of £31.2 million in the period, but the cumulative net FX gain on investments since IPO was still positive at period end. NAV per share was 145.8p (31 March 2026 ex-dividend: 143.7p). |
|
– |
NAV total return of 75.8% since IPO in February 2021, or 10.6% a year against a target of 9%2. |
|
– |
Supportive markets. Data sovereignty and scarce secured power in the traditional major data centre hubs are driving demand towards the Company’s national markets, where its platforms hold leading positions. Poland is again expected to be the fastest-growing major EU economy, and the Czech Republic continues to outperform the EU average and its largest economies. |
|
– |
Demand from AI workloads and data sovereignty is converting into contracts. CRA has signed GPU-as-a-service3 contracts worth about £7.1 million a year and two new colocation contracts at its Žižkov data centre in Prague; DCU signed a 3MW high-density contract in Belgium; and new contracts put Hudson on course for run-rate EBITDA breakeven next financial year. Revenue directly attributable to AI use cases was under 1% of the total in the period but represents a new and attractive source of growth. |
|
– |
Demand for Prague Gateway is growing. Letters of intent now exceed 45MW, from AI and sovereign cloud providers, enterprises and governments, and the site is the Czech candidate for the EU AI Gigafactory bid. |
|
– |
A highly attractive pipeline of growth opportunities, with funding options being evaluated. Costed opportunities across all sub-sectors total at least £400 million of growth capital expenditure and bolt-on acquisitions, with double-digit return potential. Capital is being committed in a disciplined manner, balancing risk, return and contractual terms. |
|
– |
The portfolio is well positioned for the second half, with recently signed contracts beginning to contribute and the pipeline converting, supported by a highly contracted, inflation-linked revenue base. |
|
– |
A well-covered dividend and a solid balance sheet. First interim dividend of 2.225p per share, half of the 4.45p current annual target, payable on 22 December 2026 and covered 1.8x by AFFO before scheduled debt repayments and 1.6x after4. Gearing of 40.2%, net leverage of 4.5x and liquidity of £186.4 million5. 75% of drawn debt is fixed or hedged, and CRA and Emitel have hedged most of their 2026 energy and around half of 2027. |
|
– |
Total shareholder return of 25.4% for the six months. At close on 20 November 2026 the shares traded at a discount of 18.7% to NAV. Independent directors, Cordiant Capital Inc (the Investment Manager) and the Corilis Digital Infrastructure Management (CDIM) team own 2.3% of issued share capital. |
|
– |
New name, same strategy, portfolio and advisory team. The Corilis name was approved on 11 November 2026, after Steven Marshall acquired Cordiant Capital Inc’s interest in CDIM. |
Shonaid Jemmett-Page, Chairman of Corilis Digital Infrastructure Limited, said:
“These are sound results for a period of geopolitical and market volatility. Our focus is on disciplined growth underpinned by prudent leverage. The portfolio has a highly attractive pipeline of opportunities, and we are evaluating how best to fund more of it, creating value at returns above target while protecting shareholders’ interests. The Board welcomes Steven Marshall’s increased ownership of and investment in CDIM, which demonstrates his commitment to the business and is a strong positive for shareholders.”
Steven Marshall, Executive Chairman of Corilis Digital Infrastructure Management, said:
“The portfolio delivered robust operational growth in the period. Most of our platforms lead their core markets, with secured power and difficult-to-replicate networks, and the structural drivers of demand, including AI, cloud, data sovereignty and mobile data growth, are converting into contracted revenue across our portfolio.”
Interim Report and results webcast for analysts
The Interim Report for the six months ended 30 September 2026 will be available to download at www.corilisdigital.com/investors from 24 November 2026. The Company will host a meeting for research analysts at 10:00am GMT on 24 November 2026 at the offices of Investec Bank plc, 30 Gresham Street, London EC2V 7QP. Those wishing to attend should contact Celicourt at cdi@celicourt.uk. A webcast will be held for investors at 11:30am GMT on 24 November 2026. Those wishing to attend can register on SparkLive here: https://sparklive.lseg.com/home.
For further information, please visit www.corilisdigital.com or contact:
|
Cordiant Capital Inc (Investment Manager) Corilis Digital Infrastructure Management LLP Stephen Foss |
cord@corilis.com |
|
Aztec Financial Services (Guernsey) Limited (Company secretary and administrator) |
+44 (0)1481 749 700 cord@aztecgroup.co.uk |
|
Investec Bank plc (Joint corporate broker) Lucy Lewis, Tom Skinner |
+44 (0)20 7597 4000 |
|
Deutsche Numis (Joint corporate broker) Hugh Jonathan, George Shiel |
+44 (0)20 7260 1000 |
|
Celicourt (Financial communications adviser) Philip Dennis, Kathleen Beams |
+44 (0)20 7770 6424 cdi@celicourt.uk |
Notes to editors:
About the Company
Corilis Digital Infrastructure Limited (formerly Cordiant Digital Infrastructure Limited) is a FTSE 250, sector-focused, specialist owner and operator of assets in one of the fastest-growing infrastructure sectors, comprising communications towers, data centres and fibre-optic networks. The Company’s strategy can be summarised as acquiring and expanding cash generative digital infrastructure platforms through growing managed assets, growth capital expenditure and bolt-on acquisitions across Europe, North America, Australia and New Zealand. Listed on the London Stock Exchange under the ticker CORD, the Company has invested in six platforms: CRA, Hudson, Emitel, Speed Fibre, Belgian Tower Company and Datacenter United. Further details are available at www.corilisdigital.com.
About the Investment Manager and CDIM
Cordiant Capital Inc (CCI) is the Company’s current Investment Manager. The Company is in the process of appointing an FCA-authorised alternative investment fund manager as its new Investment Manager, with the transition from CCI expected to complete before the end of the current financial year, subject to due diligence and regulatory approval. Corilis Digital Infrastructure Management (CDIM) has supported CCI on the Company’s portfolio since IPO and will continue as investment advisor to the new Investment Manager. CDIM was co-founded by Steven Marshall, former president of American Tower’s US Tower Division, who chairs the major portfolio companies. The CDIM team, largely based in London, consists of 20 professionals with hands-on investing and operating expertise, focused on acquiring and expanding cash generative digital infrastructure platforms across developed markets.
Chairman’s statement
I am pleased to present the Company’s interim report for the six months to 30 September 2026 – the first under the Corilis name, and the first since its admission to the Official List and the FTSE 250 earlier this year.
Performance
The portfolio performed robustly in the six months as revenue grew 18.1% and EBITDA 3.5% over the prior comparable period on a constant currency basis. Before the impact of changes in FX since year end, the Company delivered a total return of 4.3% on its ex‑dividend opening NAV, with the value of every portfolio company increasing in local currency despite higher government bond yields, which raised the discount rates applied in the valuations. Headline results were, however, held back by a stronger pound, which produced an FX loss of £31.2 million. NAV per share at 30 September 2026 was 145.8p (31 March 2026 ex-dividend: 143.7p), producing a total net return of 1.4% on ex-dividend opening NAV. This is a sound outcome for a period of geopolitical and market volatility, with key growth drivers making significant progress during the period across data centres, radio broadcasting, multimedia, smart cities and other emerging businesses.
Capital allocation
The Board’s priorities remain unchanged: disciplined growth investment in the portfolio; a progressive, well‑covered dividend; and prudent leverage. The second interim dividend of 2.275p in respect of the prior year was paid on 30 July 2026. The current target dividend for this financial year, as announced in June 2026, is 4.45p, and the Board has declared a first interim dividend of 2.225p, representing half of the annual target, payable in December 2026. Committed growth projects are being funded from portfolio company cash flows and debt facilities, with minority co-investment being explored for the first phase of Prague Gateway. Beyond these, a highly attractive and accretive pipeline of growth opportunities across the portfolio exceeds the capital available to pursue all of it, and the Board and the management team continue to evaluate funding options.
Share price
The shares delivered a total shareholder return of 25.4% between 1 April and 30 September 2026, and at the close on 20 November 2026 traded at a discount of 18.7% to the 30 September 2026 NAV. The Board remains dissatisfied with the persistent discount, which it considers reflects conditions across the wider UK listed market, including but not limited to the investment company sector, rather than the Company’s performance. The Board believes that continued operational delivery, value-creating capital expenditure, disciplined acquisition pricing, active investor engagement and the significant alignment of interests between shareholders, the Board and the management team should be recognised as sector conditions improve.
Sustainability
Sustainability and resilience remain central to the Company’s long-term strategy. DCU became the first portfolio company to adopt independently verified science-based emissions‑reduction targets, and the Investment Manager is supporting the other portfolio companies in developing their own credible emissions reduction plans. In the period, energy-efficiency and water‑circularity upgrades at the data centres progressed, measurement of emissions and climate risk improved, and construction of Prague Gateway commenced, with the data centre expected to achieve up to 100% renewable electricity matching. Emitel’s street lighting contract in Warsaw targets substantial energy savings of up to 30%. Hudson strengthened its governance framework and obtained SOC 2 Type I attestation, which provides independent assurance that Hudson’s data security controls are suitably designed.
Investment management arrangements
In September 2026 Steven Marshall acquired Cordiant Capital Inc’s (CCI) interest in Corilis Digital Infrastructure Management LLP (formerly Cordiant Digital Infrastructure Management LLP (CDIM)), the entity that has advised CCI, the Company’s Investment Manager since IPO, on the portfolio. The Company is in the process of appointing an FCA-authorised alternative investment fund manager (AIFM) as its new Investment Manager, with CDIM as its appointed representative and investment advisor, and expects the transition from CCI to complete before the end of the financial year, subject to completion of due diligence by the new AIFM and regulatory approval. The strategy, portfolio and core team are unchanged. The Board regards Mr Marshall’s increased commitment as a strong positive for shareholders and we thank CCI for its support since the Company’s inception. Reflecting these changes, shareholders approved the Company’s new name, Corilis Digital Infrastructure Limited, at an extraordinary general meeting on 11 November 2026. Corilis combines ‘core’, the physical assets of the digital economy, with ‘Iris’, the messenger of the Greek gods, whose role was uninterrupted transmission. The new brand, highlighting connected nodes, is introduced in this interim report.
Governance
The Board met regularly with the Investment Manager during the period and gave particular attention to the funding of the growth pipeline and the recent changes to the investment management arrangements.
Outlook
The structural demand for digital infrastructure in the Company’s markets is strong, and the portfolio is well positioned to capture it. While currency and discount rate movements have impacted NAV growth in the period, the Board is confident that the portfolio’s contracted and recurring cash flows, the pipeline of opportunities and the strength of the management team provide a solid foundation for continued growth in the second half and into the next financial year.
Financial and operational review
The portfolio delivered robust operational growth in the period. Most of our platforms are leaders in their core markets, with secured power, extensive and difficult-to-replicate networks and medium- to long-term contracts with blue-chip and government customers. The structural drivers of demand, including AI, cloud, data sovereignty, national security and resilience, and mobile data growth, are converting into contracted revenue across the portfolio. The pipeline of attractive growth opportunities exceeds the capital available to us, and we continue to evaluate options to raise further funding in a disciplined way to enhance returns for shareholders.
Introduction
The portfolio delivered robust operational performance in the six months to 30 September 2026, with portfolio revenue growing 18.1% and EBITDA 3.5% on the prior comparable period on a constant currency basis. Excluding the impact of FX, the Company generated a total return of 4.3% on the ex‑dividend opening NAV in the period, driven by income from the portfolio and unrealised value gains at every portfolio company. Overall returns were held back by macroeconomic headwinds linked to geopolitical developments. Higher government bond yields increased the portfolio’s weighted average WACC by 25 basis points, while the appreciation of sterling against the portfolio currencies contributed to a net FX loss of £31.2 million. After the effect of FX, NAV per share was 145.8p at 30 September 2026 (31 March 2026 ex-dividend: 143.7p), representing a total net return of 1.4% on the ex‑dividend opening NAV.
|
Figure 1: Headline portfolio financial performance for the six months ended 30 September 2026 | ||||
|
|
30 Sept 2026 £m |
30 Sept 2025 £m |
Change £m |
Change %4 |
|
Portfolio revenue1 |
|
|
|
|
|
At actual FX rates2 |
212.9 |
179.0 |
33.9 |
18.9 |
|
At constant currency3 |
212.9 |
180.2 |
32.7 |
18.1 |
|
Portfolio EBITDA1 |
|
|
|
|
|
At actual FX rates2 |
87.3 |
83.8 |
3.5 |
4.1 |
|
At constant currency3 |
87.3 |
84.3 |
3.0 |
3.5 |
|
Figure 2: NAV movements for the period |
||||||||
|
|
Period ended 30 Sept 2026 |
Period ended 30 Sept 2025 | ||||||
|
|
£m |
p/share |
%5 |
£m |
p/share |
%5 | ||
|
Opening NAV |
1,117.9 |
146.0 |
|
992.5 |
129.6 |
| ||
|
Second interim dividend paid |
(17.4) |
(2.3) |
|
(17.2) |
(2.2) |
| ||
|
Ex-dividend opening NAV |
1,100.5 |
143.7 |
|
975.3 |
127.4 |
| ||
|
Net profit for the period |
15.7 |
2.1 |
1.4 |
97.0 |
12.7 |
10.0 | ||
|
Closing NAV |
1,116.2 |
145.8 |
|
1,072.3 |
140.0 |
| ||
|
Figure 3: NAV bridge for the six months to 30 September 2026
| |
|
£m |
|
|
Opening NAV as at 1 April 2026 |
1,117.9 |
|
Second interim dividend paid |
(17.4) |
|
Opening ex-dividend NAV |
1,100.5 |
|
Accrued income |
29.0 |
|
Value movement |
35.5 |
|
Foreign exchange movement |
(31.2) |
|
Fund expenses |
(6.6) |
|
Interest expenses |
(11.0) |
|
Closing NAV as at 30 September 2026 |
1,116.2 |
Market
The Polish and Czech economies remain robust. Poland is again expected to be the fastest-growing major economy in the EU, with GDP growth forecast at around 3.5% in 2026, supported by resilient private consumption, EU-funded investment and unemployment of c.3%. The Czech Republic grew 2.6% in 2025 and, while growth is expected to moderate to around 2% in 2026 as higher energy prices weigh on activity, it continues to run one of the lowest unemployment rates in the EU, at under 3%. Sterling strengthened against the euro in the period as expectations for UK interest rates rose. The Czech koruna weakened modestly against sterling, while the Polish zloty weakened by more, reflecting the more accommodative stance of the National Bank of Poland. In our view, these movements reflect sterling strength and relative interest rate expectations.
The structural drivers of demand for the Company’s assets continue to develop. AI is a key driver of new demand but an overlay on the sector’s established growth drivers, with the portfolio’s earnings underpinned by contracted and recurring demand for essential digital infrastructure. Revenue directly attributable to AI use cases is estimated at less than 1% of portfolio revenue in the six months to 30 September 2026 but represents a new and attractive source of growth with new contracts recently signed. Data sovereignty has become a strategic priority for European governments and enterprises, with policy increasingly directed at keeping data and compute capacity within the jurisdiction. Secured power is now the principal constraint on new data centre capacity, and the Company’s data centre platforms are well placed with access to power in their respective markets. Mobile data growth continues to drive tenancy demand on the Company’s towers, with low Earth orbit satellites extending coverage to remote areas as a complement to terrestrial networks rather than a substitute for them.
The geopolitical environment is also creating opportunities for the portfolio. In Poland and the Czech Republic, terrestrial broadcasting remains a key form of television and radio distribution, providing resilient, one-to-many infrastructure with near-universal coverage. Governments are increasingly looking to this national infrastructure for emergency warning and crisis communications, as demonstrated by the nationwide DAB+ and 5G broadcast emergency alert tests carried out by CRA with the Czech public broadcasters in September 2026. Heightened security concerns are also generating new demand for the portfolio’s sites and networks, including Emitel’s contract to install drone monitoring infrastructure across 114 sites for the Polish Air Navigation Services Agency.
Finally, the Company’s core geographic markets such as the Czech Republic, Poland and Belgium are smaller and less mature digital infrastructure markets than the principal European data centre hubs, with lower installed capacity per capita and fewer established competitors. As data sovereignty, latency and power constraints in the major hubs drive demand towards national and regional markets, these countries offer significant growth potential, and the Company’s platforms hold leading positions and secured power in each of them. This backdrop, and the demand it is generating across the portfolio, informs the capital allocation priorities of the Company.
Key portfolio highlights
At CRA, construction of Prague Gateway began in September 2026, with letters of intent agreed to date exceeding 45MW of capacity. CRA had signed GPU-as-a-service (GPUaaS) contracts with seven customers by the period end, representing contracted annualised revenue of approximately CZK 200 million (£7.1 million). CRA is expanding DC Lužice to meet further demand, and continued to sell capacity at its recently expanded Žižkov tower data centre in Prague, where two multi-year contracts were agreed in the period.
Emitel added further tenancies across its 777-site tower portfolio, with mobile operators having installed equipment on 51 sites and other tenants on 31 sites since the start of the company’s financial year. Emitel also began delivery of the Warsaw city lights programme, and is trading ahead of plan at its newly acquired data centre. Speed Fibre’s integration of ECL progressed broadly to plan, with most transitional arrangements with BT exited, and it began delivery of a new national fibre ring.
DCU signed a 3MW high-density contract at Machelen, due to commence billing in April 2027, and submitted a final proposal for a new anchor tenant-backed data centre campus. Hudson completed its two new data halls and signed contracts increasing utilised capacity, putting it on course for run-rate EBITDA breakeven next financial year.
Capital allocation strategy
The Company’s balanced approach to capital allocation aims to maximise overall returns to shareholders while recognising current limits on capital availability. Capital is being directed to growth capital expenditure at, and bolt-on acquisitions by, the portfolio companies, underpinned by disciplined balance sheet management, while continuing to support a progressive dividend policy.
Track record of Buy, Build & Grow
The Company’s record of value creation from bolt-on acquisitions and growth capital expenditure illustrates the return potential of its pipeline. Recent examples include:
DCU’s conversion of its Machelen data centre to high‑density capacity in 2026, at a cost of approximately €11 million (£9.6 million). 3MW of the new capacity has already been contracted to a Dutch managed services provider on a five‑year term. The project is expected to deliver an IRR in excess of 20%.
Emitel’s acquisition of PSN, TDF’s former Polish towers business, in November 2024. Site and service synergies have more than trebled acquired EBITDA, from PLN 1.6 million in 2024 to an expected PLN 5.6 million in 2026. The post‑synergy enterprise value is estimated at approximately 3.5x the consideration paid, lifting the IRR from 16% to over 40%.
CRA’s acquisition of cloud business C4C in January 2024 for approximately £48 million (excluding DC Lužice). EBITDA over the 12-month earn-out period nearly doubled the target agreed at acquisition, implying an effective entry multiple of approximately 11x EBITDA against 20x at signing. DC Lužice, acquired with the business, now hosts CRA’s highly accretive GPUaaS operation.
CRA’s development of the Cukrák data centre, with capital expenditure of approximately £2 million, is on track to deliver an IRR of approximately 14%.
CRA’s expansion of its Žižkov tower data centre in Prague, completed in 2026 at a cost of CZK 227.9 million (£8.1 million), which added 680kW of IT capacity; with most of the space already sold or reserved, the project is expected to generate incremental EBITDA of approximately CZK 24.5 million (£0.9 million) a year and an IRR of approximately 13%; and
CRA’s roll-out of its commercial DAB+ radio network, which reached full utilisation in 2026. The network has performed ahead of budget on both revenue and cost and is expected to deliver an IRR of approximately 17%.
Pipeline of opportunities
Committed growth capital expenditure has increased since the year end and is already beginning to deliver returns. Key committed projects include:
Prague Gateway: the first phase (core and shell for all three modules and a first 4MW module) at a cost of up to CZK 2.1 billion (£75 million), where construction began in September 2026;
CRA GPUaaS: approximately CZK 304 million (£10.9 million) had been committed to GPU purchases by the period end; a further 40 nodes were ordered in October 2026 for approximately CZK 444 million (£15.9 million), and DC Lužice is being expanded from 200kW to up to 900kW to accommodate the programme;
Speed Fibre: the new national fibre ring in Ireland, on which delivery has begun, with capital expenditure of approximately €30 million (£26.1 million) over 2026 to 2028, to be partly financed by a proposed new €20 million (£17.4 million) capex facility from its lenders, and where dark fibre IRU sales under discussion would lift returns significantly;
Hudson: the build-out of the final two data halls on the sixth floor to serve its pre-sold capacity; and
DCU: the 4MW high-density conversion at the Machelen site already under way and upgrades across its other facilities.
GPUaaS is expanding rapidly, with CRA establishing itself as a leader in the Czech market. The service is delivered from DC Lužice, and the remaining capacity at CRA’s recently expanded Žižkov data centre in Prague has been earmarked for further GPUaaS growth. Contracts typically run for two to three years, often with extension options, against a GPU useful economic life of around five years; assuming no residual value, the business model targets EBITDA margins above 70%, short payback periods and unlevered project IRRs comfortably above 20%. CRA is assessing a significant pipeline of further opportunities, some of which can be accommodated in its own data centres.
Beyond the committed projects, the portfolio has a growing pipeline of near- to medium-term growth capital expenditure opportunities with the potential to deliver attractive double-digit returns, including, but not limited to:
Prague Gateway: the subsequent phases of the development comprising the second and third modules, taking the total cost of the full project to at least c.CZK 3.9 billion (£139 million) and potentially significantly more depending on use case and the outcome of the EU AI Gigafactory bid;
Emitel: a pipeline of over PLN 600 million (£122.2 million) of growth capital expenditure to 2030 mostly in towers and data centres; and
DCU: the long-term development and operation of a new data centre campus in Belgium, for which DCU submitted a final proposal in October 2026. The project would be underpinned by an anchor tenant, built out in phases in line with customer demand and would give DCU access to significant additional secured power; the initial phase is expected to be funded from DCU’s existing debt facilities and operating cash flow, and the outcome is expected shortly.
Costed opportunities, both committed and uncommitted, represent at least £400 million of potential growth capital expenditure and bolt-on acquisitions over the coming years, and including the EU AI Gigafactory and DCU’s proposed new campus, the total pipeline could be larger. The management team remains conscious of the need to deploy growth capital expenditure in a disciplined manner, balancing risk and return, with particular attention to the credit quality of prospective customers and to ensuring that appropriate contractual and structural mitigants are in place before capital is committed. Constrained by available capital, the Company has had to pass on several attractive major platform acquisitions that would have complemented the existing portfolio well.
The Board and the management team see significant opportunity to secure additional compelling medium- to long‑term returns from this pipeline, which exceeds the capital currently available to pursue all of it, and are evaluating the full range of options to fund more of it. In doing so, they will seek to maintain leverage at a prudent level, calibrated to the risk and return profile of the underlying investments and the visibility of their cash flows; preserve the Company’s governance and control over its platforms; and ensure that shareholders retain an appropriate share of the value the pipeline is expected to create.
Valuation
The Investment Manager prepares semi-annual DCF valuations of each portfolio company in accordance with the IPEV Guidelines and IFRS 13, using market information from reputable third-party sources. These are reviewed by the Board, which engages a Big Four valuations team to carry out independent valuations at each valuation date.
Between 31 March 2026 and 30 September 2026, the Company’s average WACC, weighted by the investments held, increased by 25 basis points to 9.56%. The increase was driven by a higher cost of equity, reflecting a rise in government bond yields across Europe and the US, with the WACCs of Emitel, CRA, Hudson and BTC each increasing by between 10 and 30 basis points. DCU’s WACC increased by 50 basis points, reflecting higher observed betas and borrowing costs for comparable data centre companies, while Speed Fibre’s was unchanged as the higher risk-free rate was offset by a reduction in its size premium and changes in other market variables.
Emitel’s equity value increased by 2.5% in local currency terms after distributions in the period, or 7.1% before distributions, with the roll forward of the DCF model and trading ahead of the business plan more than offsetting an increase in WACC.
CRA’s equity value was broadly unchanged in local currency terms after distributions, as the roll forward of the DCF model was broadly offset by an increase in WACC.
Speed Fibre’s equity value increased by 6.0% in local currency terms, with WACC unchanged, supported by the roll forward of the DCF model and the inclusion of the new national fibre ring project.
DCU’s equity value increased by 7.7% in local currency terms, as the roll forward of the DCF model and the 3MW high-density contract signed at Machelen, which brings forward the business plan, more than offset an increase in WACC.
Hudson’s increase in equity value generated a total return of 7.3% in local currency terms after taking account of the $7.0 million (£5.2 million) of shareholder loans advanced in the period. The faster lease-up of the sixth floor following the new contracts signed and the roll forward of the DCF model more than offset an increase in WACC. Hudson represents 3.3% of the total fair value of investments.
BTC, the smallest portfolio company, delivered a total return of 12.6% in local currency terms, principally reflecting the €0.8 million (£0.7 million) dividend paid in July 2026; its equity value increased by 2.1%, with the roll forward of the DCF model and a normalisation of working capital more than offsetting the lower cash balance after the dividend and an increase in WACC.
At 30 September 2026, the portfolio’s GAV was equivalent to approximately 10.5x LTM portfolio EBITDA (before Company‑level costs). Recent transactions involving mobile tower assets and data centres in other markets have occurred at multiples comfortably exceeding this number.
|
Figure 4: Reconciliation of Statement of Comprehensive Income to Figure 3 | ||||||
|
Six months to 30 September 2026 (£m) |
Accrued income |
Value movement |
Net foreign exchange movement |
Fund expenses |
Interest expense |
IFRS P&L |
|
Movement in fair value of investments |
28.4 |
35.5 |
(35.1) |
(0.1) |
(11.0) |
17.8 |
|
Management fee income |
0.4 |
– |
– |
– |
– |
0.4 |
|
Management fee expenses |
– |
– |
– |
(4.4) |
– |
(4.4) |
|
Other expenses |
– |
– |
– |
(2.1) |
– |
(2.1) |
|
FX movements on working capital |
– |
– |
3.9 |
– |
– |
3.9 |
|
Finance income |
0.2 |
– |
– |
– |
– |
0.2 |
|
|
29.0 |
35.5 |
(31.2) |
(6.6) |
(11.0) |
15.7 |
|
Figure 5: Breakdown of unrealised value movement in the period | ||||
|
Unrealised value movement (£m) |
|
|
|
|
|
Emitel |
|
|
|
14.9 |
|
CRA |
|
|
|
6.5 |
|
Speed Fibre |
|
|
|
6.8 |
|
DCU |
|
|
|
4.1 |
|
Hudson |
|
|
|
2.7 |
|
BTC |
|
|
|
0.1 |
|
Other |
|
|
|
0.5 |
|
Total unrealised value movement |
|
|
|
35.5 |
|
Figure 6: Weighted average discount rates over time |
|
|
31 March 2022 |
8.05% |
|
30 September 2022 |
8.52% |
|
31 March 2023 |
9.60% |
|
30 September 2023 |
9.78% |
|
31 March 2024 |
9.60% |
|
30 September 2024 |
9.50% |
|
31 March 2025 |
9.32% |
|
30 September 2025 |
9.29% |
|
31 March 2026 |
9.31% |
|
30 September 2026 |
9.56% |
|
Figure 7: Underlying components of Statement of Financial Position | ||||||||||||
|
At 30 September 2026 (£m) |
Emitel |
CRA |
Speed Fibre |
DCU |
Hudson |
BTC |
Total fair value of investments |
Cash |
Inter-company balances |
Other assets and liabilities |
Holding company debt |
IFRS Total |
|
Investment at fair value through profit or loss |
613.7 |
515.7 |
120.0 |
57.8 |
44.3 |
6.6 |
1,358.2 |
0.7 |
195.6 |
5.9 |
(260.7) |
1,299.8 |
|
Trade and other receivables |
– |
– |
– |
– |
– |
– |
– |
– |
0.9 |
8.6 |
– |
9.5 |
|
Cash and cash equivalents |
– |
– |
– |
– |
– |
– |
– |
4.7 |
– |
– |
– |
4.7 |
|
Accrued expenses and other creditors |
– |
– |
– |
– |
– |
– |
– |
– |
– |
(1.2) |
– |
(1.2) |
|
Loans and borrowings |
– |
– |
– |
– |
– |
– |
– |
– |
(196.5) |
– |
– |
(196.5) |
|
|
613.7 |
515.7 |
120.0 |
57.8 |
44.3 |
6.6 |
1,358.2 |
5.5 |
– |
13.2 |
(260.7) |
1,116.2 |
|
Figure 8: Weighted average cost of capital at 30 September 2026 | |||
|
|
Range low point |
Range high point |
Weighted average mid-point |
|
Cost of equity |
10.8% |
13.8% |
11.8% |
|
Cost of debt |
5.5% |
8.0% |
6.9% |
|
WACC |
8.3% |
11.0% |
9.6% |
|
Weighted average cost of capital at 31 March 2026 |
||||
|
|
Range low point |
Range high point |
Weighted average mid-point | |
|
Cost of equity |
10.7% |
13.5% |
11.5% | |
|
Cost of debt |
5.0% |
8.0% |
6.8% | |
|
WACC |
8.3% |
11.0% |
9.3% | |
Foreign exchange
The Company recognised a net FX loss in the period mainly due to appreciation of sterling to the Czech koruna and the Polish zloty. FX losses on euro-denominated investments were offset by depreciation in the value of the Company’s euro-denominated holding company debt. While the Company typically hedges cash distributions from the portfolio companies through forward contracts, no balance sheet hedging has been undertaken to date. The cost of doing this continues to be disproportionate to the benefit, such that the aggregate cost of hedging would over several years consume the gain being protected. The Investment Manager and Board keep the Company’s hedging strategy under regular review. The Company is a long-term investor in the portfolio and currently does not seek to manage balance sheet foreign exchange exposure from reporting period to reporting period. At 30 September 2026, the Company’s cumulative net FX gain on investments was positive.
Operating costs of the Company
Management fees for the period represented 0.79% of NAV on an annualised basis and have increased on the prior comparable period as management fees, payable monthly, are calculated on the Company’s average market capitalisation in each month. The ongoing costs ratio, calculated in accordance with the guidelines published by the AIC, is 1.08% on an annualised basis. Non‑recurring costs largely include fees relating to the Company’s migration to the Official List of the FCA and project costs.
|
Figure 9: Summary of Company-level operating costs
| ||||||||||
|
Six months ended 30 September 2026 |
Six months ended 30 September 2025 | |||||||||
|
£m |
The Company |
Intermediate holding companies |
Total |
% of NAV6 |
The Company |
Intermediate holding companies |
Total |
% of NAV6 | ||
|
Management fees |
4.4 |
– |
4.4 |
0.39% |
3.4 |
– |
3.4 |
0.33% | ||
|
Directors’ fees |
0.1 |
– |
0.1 |
0.01% |
0.1 |
– |
0.1 |
0.01% | ||
|
Audit fees |
0.1 |
0.1 |
0.2 |
0.02% |
0.1 |
0.1 |
0.2 |
0.02% | ||
|
Other recurring costs |
1.2 |
0.1 |
1.3 |
0.11% |
0.9 |
0.3 |
1.2 |
0.12% | ||
|
Recurring operating costs |
5.8 |
0.2 |
6.0 |
0.54% |
4.6 |
0.4 |
5.0 |
0.48% | ||
|
Non-recurring costs |
0.7 |
(0.1) |
0.6 |
0.05% |
(0.2) |
0.2 |
(0.0) |
0.00% | ||
|
Total operating costs |
6.5 |
0.1 |
6.6 |
0.59% |
4.4 |
0.6 |
5.0 |
0.48% | ||
Financial gearing and liquidity
Consolidated gearing across the group, as measured by net borrowings (loans from banks and other institutions) to GAV, has remained broadly unchanged since year end. As measured by net borrowings to LTM EBITDA (factoring Company-level recurring operating costs), consolidated group net leverage was 4.5x. 75% of drawn debt is currently on a fixed-interest basis through fixed-rate coupons or interest rate swaps, with the remainder floating. The weighted average remaining tenor of the group’s fixed rate debt and swaps is approximately two years. The weighted average margin across all facilities is approximately 3% above the relevant interbank or swap rates. Total external net borrowings in the group have increased since year end as debt drawdowns have been made to fund growth investments across the group.
|
Figure 10: Group consolidated external borrowings and liquidity position at 30 September 2026
|
||||||||
|
|
Currency of borrowings |
Gross borrowings £m |
Maturity year |
Cash £m |
Undrawn debt £m |
Total liquidity £m | ||
|
Emitel |
PLN & EUR |
286.9 |
2030 |
42.8 |
8.3 |
51.1 | ||
|
CRA |
CZK |
146.9 |
2030 |
7.7 |
28.0 |
35.7 | ||
|
Speed Fibre |
EUR |
106.2 |
2029 |
8.5 |
5.0 |
13.5 | ||
|
Hudson |
n/a |
– |
n/a |
1.4 |
– |
1.4 | ||
|
BTC |
n/a |
– |
n/a |
1.5 |
– |
1.5 | ||
|
The Company7 |
EUR |
260.7 |
2029 |
5.5 |
59.8 |
65.3 | ||
|
Total |
|
800.7 |
|
67.3 |
101.1 |
168.5 | ||
|
|
|
|
|
|
|
| ||
|
DCU (100%) |
EUR |
50.0 |
2030 |
4.6 |
43.1 |
47.8 | ||
|
DCU (37.4%)8 |
|
18.7 |
|
1.7 |
16.1 |
17.9 | ||
|
Total including DCU at 37.4% |
|
819.4 |
|
69.1 |
117.3 |
186.4 | ||
|
Figure 11: Group consolidated gearing ratio at 30 September 2026 | ||||
|
|
30 September 2026 £m |
Percentage of |
31 March 2026 £m |
Percentage of GAV % |
|
Total cash |
69.1 |
|
74.3 |
|
|
Total gross borrowings |
819.4 |
|
823.3 |
|
|
Total net borrowings |
750.3 |
40.2% |
749.1 |
40.1% |
|
NAV |
1,116.2 |
|
1,117.9 |
|
|
GAV |
1,866.5 |
|
1,867.0 |
|
Dividend coverage
The Company’s dividend remains covered by AFFO, which represents the portfolio’s recurring free cash flow before growth‑related investments, net working capital movements and certain extraordinary expenses. The AFFO dividend cover ratio before scheduled debt repayments remained broadly stable over the period. Cover after scheduled debt repayments reduced through amortisation of Emitel’s term debt, which represents an efficient use of capital for the business, which held the equivalent of £42.8 million of cash at 30 September 2026. Figure 12 shows the calculation of AFFO for the 12 months to 30 September 2026.
In the 12 months to 30 September 2026, £59.8 million was invested across the portfolio companies in growth capital expenditure on the strategic initiatives highlighted in this report (12 months to 31 March 2026: £49.4 million), the largest share relating to data centres, cloud and AI-related investments. In the same period, £22.0 million of maintenance capital expenditure was spent (12 months to 31 March 2026: £20.0 million).
|
Figure 12: Calculation of adjusted funds from operations (AFFO)
| ||
|
|
|
12 months to |
|
Portfolio revenues10 |
|
429.8 |
|
Portfolio normalised EBITDA10 |
|
177.8 |
|
Dividend coverage, EBITDA basis |
|
5.2x |
|
Net Company-specific costs11 |
|
(11.4) |
|
Net finance costs |
|
(51.1) |
|
Net taxation, other |
|
(30.7) |
|
Free cash flow before all capital expenditure |
|
84.7 |
|
Maintenance capital expenditure12 |
|
(22.0) |
|
AFFO before scheduled debt repayments |
|
62.7 |
|
Scheduled repayments of borrowings |
|
(9.8) |
|
AFFO after scheduled debt repayments |
|
52.9 |
|
Dividend at 4.45p per share |
|
(34.1) |
|
AFFO dividend cover before scheduled debt repayments |
|
1.8x |
|
AFFO dividend cover after scheduled debt repayments |
|
1.6x |
Management team
Following the changes to the investment management arrangements announced in September 2026, the CDIM team remains substantially the same: a team of now 20 professionals, led by Steven Marshall, combining deep operating experience of world-class digital infrastructure businesses with decades of private equity and investment banking experience in the sector.
Alignment of interests
Since 18 June 2026, the CDIM team has made further purchases of the Company’s shares. On 22 June 2026, Steven Marshall, Executive Chairman of CDIM, acquired a further 240,000 shares at an average price of 125p, bringing his total personal holding to 15.6 million shares. At the date of this report, the Directors, the Investment Manager and CDIM staff owned a combined 17.4 million shares, representing 2.3% of the ordinary issued share capital of the Company.
|
Figure 13: Summary of insider ownership |
|||||||||
|
|
23 November 2026 |
18 June 2026 |
Change | ||||||
|
|
Number of shares owned thousands |
% of shares outstanding |
Number of shares owned thousands |
% of shares outstanding |
Number of shares owned thousands |
Increase/ | |||
|
Steven Marshall |
15,568.0 |
2.0% |
15,328.0 |
2.0% |
240.0 |
1.6% | |||
|
Other staff members of CDIM |
966.7 |
0.1% |
980.7 |
0.1% |
(14.0) |
(1.4)% | |||
|
Cordiant Capital Inc. and its shareholders |
406.8 |
0.1% |
560.6 |
0.1% |
(153.8) |
(27.4)% | |||
|
The Board of Directors |
495.7 |
0.1% |
495.7 |
0.1% |
– |
–% | |||
|
Total |
17,437.2 |
2.3% |
17,365.0 |
2.3% |
72.2 |
0.4% | |||
Outlook
Operational momentum across the portfolio is encouraging, with the group well positioned for the second half of the year as recently signed contracts begin to contribute and the pipeline converts. The portfolio’s exposure to energy price volatility is actively managed. CRA and Emitel hedged most of their 2026 energy requirements and around half of those for 2027, and power costs at the data centres are largely passed through to customers. With a highly contracted, inflation‑linked revenue base, a solid balance sheet, a covered dividend and an attractive pipeline of organic growth opportunities, the Company is well positioned for solid, broad‑based growth across the portfolio.
Review of portfolio companies
|
GAV breakdown of portfolio |
NAV (£m) |
Net borrowings (£m) |
GAV (£m) |
Percentage of GAV |
|
Emitel |
613.7 |
244.1 |
857.9 |
46.0% |
|
CRA |
515.7 |
139.2 |
654.9 |
35.1% |
|
Speed Fibre |
120.0 |
97.7 |
217.7 |
11.6% |
|
DCU (37.4%)1 |
57.8 |
17.0 |
74.8 |
4.0% |
|
Hudson |
44.3 |
(1.4) |
42.9 |
2.3% |
|
BTC |
6.6 |
(1.5) |
5.2 |
0.3% |
|
Other assets and liabilities including CDH UK debt |
(242.0) |
255.2 |
13.2 |
0.7% |
|
Total |
1,116.2 |
750.3 |
1,866.5 |
100.0% |
Note: certain financial information in this report has been rounded to the nearest £ million or one decimal place. As a result, totals may not cast, and percentage movements may not be exactly reconcilable to the figures shown.
Emitel multi-asset platform Poland (acquired November 2022)
|
Emitel overview |
£m |
|
Original cost |
353.0 |
|
Value at 1 April 2026 |
623.0 |
|
Unrealised value gain/(loss) |
14.9 |
|
Unrealised FX gain/(loss) |
(24.2) |
|
Value at 30 September 2026 |
613.7 |
|
Cash distributions in the period |
28.6 |
|
Cash distributions since acquisition |
121.8 |
|
MOIC1 at 30 September 2026 |
2.1x |
|
|
PLN millions |
GBP2 millions |
|
| ||
|
|
Six months to 30 September 2026 |
Six months to 30 September 2025 |
Six months to 30 September 2026 |
Six months to 30 September 2025 |
% change |
% change |
|
Revenue |
359.3 |
346.5 |
72.1 |
69.9 |
3.7% |
3.3% |
|
EBITDA |
245.4 |
236.2 |
49.3 |
47.6 |
3.9% |
3.5% |
|
|
30 September 2026 |
31 March 2026 |
30 September 2026 |
31 March 2026 |
|
|
|
Gross borrowings |
1,463.4 |
1,407.5 |
286.9 |
287.2 |
|
|
|
Cash |
218.4 |
204.8 |
42.8 |
41.8 |
|
|
|
Undrawn debt |
42.5 |
123.5 |
8.3 |
25.2 |
|
|
Emitel’s revenue growth for the half year was supported by inflation-linked price increases, growth in radio broadcasting, higher tower rental income from new site entries, project revenue and its new data centre business, while continued cost discipline benefited the EBITDA margin. As anticipated in the Company’s most recent Annual Report, growth has been moderated by certain TV broadcast contracts on MUX-8 reaching the end of their term in December 2025.
In TV broadcasting, Emitel launched the Newsmax channel in July 2026 as a virtual channel on MUX-8, delivered using HbbTV technology. Radio transmission contracts continue to be renewed at higher prices: during 2026, new contracts came into effect for over 100 Polskie Radio emissions, with prices 4-9% higher (including indexation).
In mobile towers, MNOs added equipment at 51 sites and non-MNO tenants were added at a further 31 sites since the start of Emitel’s financial year. Further new tenancies are expected in the coming months. Emitel’s portfolio stood at 777 towers at 30 September 2026, and the tenancy ratio on its rental sites was 1.9x for mobile network operators and 2.4x in total. Emitel continues to develop new towers under its multi-year build‑to-suit agreement with Orange Polska covering hundreds of new sites. The company is also pursuing bolt-on tower acquisitions.
In August 2026, Emitel completed delivery of the PLN 14.2 million (£2.8 million) contract to install drone monitoring infrastructure across 114 sites for the Polish Air Navigation Services Agency (PANSA). Emitel also began delivering the PLN 64 million (£12.5 million) city lights management contract awarded by the Warsaw municipality in April 2026, which includes a further PLN 21.5 million (£4.2 million) of optional scope. In June 2026, Emitel completed the next stage of its car park management project at Katowice Airport, and its IoT network now connects approximately 93,000 sensors.
The Tier III+ colocation data centre near Warsaw acquired in March 2026 has built a strong customer pipeline, revenues are running ahead of the acquisition business plan, and Emitel is planning to expand its capacity.
Emitel’s orderbook remained robust at 30 September 2026, with PLN 2.3 billion (£468.9 million) of contracted revenue. This excludes evergreen mobile tower contracts, which have no fixed end date but are long‑term in practice with low churn rates, valued at PLN 89 million (£18.1 million) per annum, as well as new contracts under negotiation.
Emitel has a pipeline of over PLN 600 million (£122.2 million) of growth capital expenditure opportunities to 2030, principally in towers and data centres, which will support expansion and diversification of the business. Net leverage, as reported to senior lenders, was 2.8x at 30 September 2026.
CRA multi-asset platform Czech Republic (acquired April 2021)
|
CRA overview |
£m |
|
Original cost |
305.9 |
|
Value at 1 April 2026 |
524.2 |
|
Unrealised value gain/(loss) |
6.5 |
|
Unrealised FX gain/(loss) |
(9.7) |
|
Repayment of share capital |
(5.3) |
|
Value at 30 September 2026 |
515.7 |
|
Cash distributions in the period |
5.3 |
|
Cash distributions since acquisition |
35.9 |
|
MOIC at 30 September 2026 |
1.8x |
|
|
CZK millions |
GBP1 millions |
|
| ||
|
|
Six months to 30 September 2026 |
Six months to 30 September 2025 |
Six months to 30 September 2026 |
Six months to 30 September 2025 |
% change |
% change |
|
Revenue |
1,432.5 |
1,394.2 |
50.9 |
48.5 |
2.7% |
5.0% |
|
EBITDA2 |
691.2 |
693.6 |
24.5 |
24.1 |
(0.3)% |
1.8% |
|
|
30 September 2026 |
31 March 2026 |
30 September 2026 |
31 March 2026 |
|
|
|
Gross borrowings |
4,199.0 |
3,999.0 |
146.9 |
142.6 |
|
|
|
Cash |
219.5 |
292.4 |
7.7 |
10.4 |
|
|
|
Undrawn debt |
801.0 |
1,001.0 |
28.0 |
35.7 |
|
|
CRA’s EBITDA for the period was marginally below the prior comparable period. This principally reflects the phasing of certain project revenue, which CRA is working to realise in the second half of the financial year, together with a provision relating to a single customer account. Positive progress has been made to recover a substantial portion of the loss incurred on this customer. Despite the provision, management is encouraged by the growth and sales pipeline it is seeing across the wider business, particularly in data centres, cloud, AI and over‑the‑top (OTT) media services, which collectively grew 14.0% on the prior comparable period.
Construction of Prague Gateway, CRA’s flagship data centre project, began in September 2026; the project and its funding are covered separately later in this section.
CRA continues to sell capacity in its recently expanded Žižkov data centre in Prague, where 100kW has been contracted to an insurance company under a five-year contract. CRA has also signed a four-year contract with a technology customer for a 160kW private hall, ramping from 60kW in November 2026 to full capacity by June 2027. The remaining capacity at the facility is earmarked for GPUaaS.
By 30 September 2026, CRA had signed GPUaaS contracts with seven customers covering 29 GPU nodes, 16 of which were in service, with contracted monthly revenue of CZK 16.7 million (£0.6 million), equivalent to annualised contracted revenue of approximately CZK 200 million (£7.1 million), and with a weighted average remaining contract term of 2.5 years. The service runs predominantly on NVIDIA B300 GPUs, and CRA has a growing pipeline of further opportunities.
GPUaaS is delivered from CRA’s DC Lužice which, given the strong demand, CRA is expanding from 200kW to up to 900kW, targeted for mid-2027. CRA has committed approximately CZK 304 million (£10.9 million) to GPU purchases to date and in October 2026 ordered a further 40 nodes for approximately CZK 444 million (£15.9 million).
Revenue from OTT and streaming services grew by approximately 40%, supported by the acquisitions of Nangu.TV, an IPTV and OTT platform provider serving telecoms operators, in December 2025 and Play.cz, the leading Czech radio streaming platform, in April 2026.
In TV broadcasting, JOJ Group began nationwide distribution of two channels on CRA’s multiplex in September 2026, extending their reach to viewers beyond their previous footprint and underlining the continued value of terrestrial broadcasting as a wide-reaching, free and stable distribution platform.
CRA continued to extend broadcasting’s role in public safety: in September 2026, CRA and CRo, the public radio broadcaster, performed a successful nationwide test of DAB+ Automatic Safety Alert emergency warnings, and CRA and Czech Television publicly tested emergency warning via 5G Broadcast, both generating extensive media coverage.
CRA’s orderbook in broadcast and mobile towers remained robust at 30 September 2026, with CZK 6.7 billion (£239.3 million) of contracted revenue. This figure excludes contracted revenue in CRA’s other divisions such as data centres, cloud and GPUaaS. Reported net leverage to banks at 30 September 2026 was 2.7x. In October 2026, CRA sold its Liblice site for CZK 38 million (£1.4 million), with all proceeds to be received by December 2026.
The appeal process in the long-running dispute relating to the valuation of a family’s purported former shareholding in a predecessor entity to CRA remains ongoing. The file remains with the Court of Appeal, with no substantive update since the Company’s first quarter trading update in September 2026.
Case study: Building Central Europe’s AI-ready data centre
Prague Gateway is CRA’s flagship new-build data centre on the edge of Prague, designed for high-density AI, cloud and enterprise workloads. Construction began in September 2026 and the site is the proposed location for the Czech bid to host an EU AI Gigafactory.
Construction
The site now has 50MW of secured utility power from two separate grid connections. Used in full as primary supply, this can serve AI workloads that do not require 2N redundancy. Alternatively, with the second connection held as back-up, 22MW is fully redundant (2N), supporting 17.3MW of redundant IT capacity across three modules to a Tier III+ design. The site offers up to 100% renewable electricity matching and has a target PUE of 1.25.
The EPC contract signed with Skanska in August 2026 covers the core and shell for all three modules and the fit-out of the first fully redundant 4MW module with a capped contract price. Phase 1 will cost up to CZK 2.1 billion (£75 million), including the core and shell for all three modules, with the potential to be up to 15% lower depending on final scope and configuration. The fit-out of Modules 2 and 3 is currently estimated at a further CZK 1.8 billion (£64 million) or more, giving a total of at least c.CZK 3.9 billion1 (£139 million) for the full build, although construction terms for these phases are yet to be agreed. Modules 2 and 3 are currently being designed to have the option to accommodate liquid-cooled GPUs. Site preparation was completed earlier in 2026 and main construction is now under way, with the first module expected to be ready for service as early as mid-2028. The design is modular: later modules will be fitted out in line with customer demand, phasing capital expenditure in line with revenue.
Customers
Letters of intent have been signed with prospective anchor customers, including the public sector, Bull, Cloudflare, Era4 Limited and Polarise, a European provider of sovereign AI cloud solutions seeking up to 15MW. Discussions are under way with other interested parties. Bull, the French state-owned high‑performance computing supplier, has indicated its intention to commit GPU workloads to the site. In aggregate, letters of intent exceed 45MW of capacity, with strong interest from AI and sovereign cloud providers as well as enterprise and government users, and a wider pipeline of enterprise, government and hyperscale requirements is being actively developed. Prague Gateway is the only near-ready, large‑scale site in Prague able to serve this demand.
Competitive positioning
The Czech data centre market remains relatively undeveloped, with around 50MW of live colocation capacity nationally, a fraction of the main Western European hubs. Prague Gateway will be the largest data centre in the country and accounts for the great majority of capacity currently under construction, with no other project of comparable scale or maturity. New entrants face significant barriers: high-voltage grid connections can take years to secure, suitably zoned land is scarce and permitting is slow and unpredictable. With all the required infrastructure already in place, Prague Gateway holds a position that would be difficult to replicate within a reasonable timeframe.
AI Gigafactory
The EU’s AI Gigafactory programme will support up to seven large AI computing facilities across Europe, tendered in two categories of 100MW and 50MW. The EU and member states will commit up to €10 billion (£8.7 billion) of public funding, principally by purchasing computing capacity from the selected facilities as an anchor customer, with the aim of attracting more than €20 billion (£17.4 billion) of private investment. CRA is leading the Czech bid in the 50MW category, centred on Prague Gateway, and is positioning itself as a leading candidate to host the facility serving the CEE region. Awards are expected next year. CRA is investigating expanding site power to over 100MW over the next few years. No value from the bid is included in the valuation.
Implications
On the basis that Prague Gateway is let as conventional enterprise colocation at pricing broadly in line with current market benchmarks, with energy costs passed through and no AI or GPU upside, once all 17.3MW redundant IT power is built and let over the next few years, the development is expected to represent a significant driver of EBITDA growth. CRA is currently funding Phase 1 from debt and free cash flow and is exploring a range of options to support the funding of the project, including minority equity and additional loans, supported by the carve-out of its data centre and cloud business into a dedicated subsidiary.
Speed Fibre fibre infrastructure platform Ireland (acquired October 2023)
|
Speed Fibre overview |
£m |
|
Original cost |
80.51 |
|
Value at 1 April 2026 |
116.3 |
|
Unrealised value gain/(loss) |
6.8 |
|
Unrealised FX gain/(loss) |
(3.0) |
|
Value at 30 September 2026 |
120.0 |
|
Cash distributions since acquisition |
0.9 |
|
MOIC at 30 September 2026 |
1.3x2 |
|
|
EUR millions |
GBP3 millions |
|
| ||
|
|
Six months to 30 September 2026 |
Six months to 30 September 2025 |
Six months to 30 September 2026 |
Six months to 30 September 2025 |
% change |
% change |
|
Revenue |
83.5 |
50.8 |
72.0 |
43.4 |
64.5% |
65.9% |
|
EBITDA4 |
13.9 |
13.2 |
12.0 |
11.3 |
5.6% |
6.6% |
|
|
30 September 2026 |
31 March 2026 |
30 September 2026 |
31 March 2026 |
|
|
|
Gross borrowings |
124.2 |
124.2 |
106.2 |
108.9 |
|
|
|
Cash |
9.9 |
6.0 |
8.5 |
5.2 |
|
|
|
Undrawn debt |
5.8 |
5.8 |
5.0 |
5.1 |
|
|
Revenue and EBITDA growth were supported by the acquisition of Enet Communications Limited (ECL, formerly BT Communications Ireland Limited), the wholesale and B2B connectivity business acquired from BT Ireland in September 2025. Within the enlarged business, core connectivity revenues have been stable over the period and churn has been lower than anticipated. As previously disclosed, ECL includes several legacy revenue segments that operate at a lower EBITDA margin than Speed Fibre’s existing businesses, Enet and Magnet+, which, together with higher energy costs, reduced the blended margin. Continued discipline on operating costs partly offset this, and the integration synergies and service rationalisation now under way are expected to support margin improvement in coming periods. EBITDA is stated before integration and restructuring costs, which continued during the period in line with plan.
The integration of ECL is progressing broadly to plan. ECL’s customers and systems are being migrated onto Speed Fibre’s single operating platform, with operations being consolidated while legacy lower-margin products are being withdrawn. Cost synergies remain on track against the integration plan. By 30 September 2026, most of the transitional service agreements with BT had been exited, with the remaining items scheduled to close by mid-2027. With the integration well advanced, management is developing a medium‑term plan for the combined business to build on its enlarged national network, customer base and contracted revenues. Cash flow benefits are expected to arise between the second half of 2027 and early 2029 as a result of the delivery of the owned national fibre ring described below and the delivery of further cost synergies.
The completion accounts process for the ECL acquisition was concluded in September 2026 following an independent accountant’s determination under the sale agreement. The final consideration was fixed at approximately €8.3 million (£7.2 million), compared to the €16.3 million (£14.2 million) at close, reflecting agreed working capital and other completion adjustments. Funds held in escrow were released back to Speed Fibre.
Speed Fibre has begun delivery of an owned national fibre ring, combining approximately 425km of existing ECL duct with a further approximately 400km to be secured through construction, duct swaps and third-party access, allowing ECL’s core network to migrate off leased third-party dark fibre ahead of a licence expiry in 2028. Remediation of existing duct, fibre procurement and route surveys commenced in the second half of 2026. Capital expenditure is estimated at approximately €30 million (£26.1 million) over 2026 to 2028. On cost savings alone the project is expected to deliver an IRR of around 10% over the first 10 years, with potential for materially higher returns if dark fibre IRU (indefeasible right of use) sales under discussion for the new ring are secured. Speed Fibre has received credit-approved terms to finance up to €20 million (£17.4 million) of the project through an additional capex facility from its lenders based on an opening margin of 2.5%, with the remainder to be funded by cash on hand and free cash flow.
Speed Fibre’s orderbook remained robust at 30 September 2026, with €106.1 million (£92.3 million) of contracted revenue on a nominal basis. Its net leverage ratio as reported to its senior lenders was 4.06x (31 March 2026: 4.08x), with substantial covenant headroom.
Looking ahead, Speed Fibre expects demand for core connectivity from hyperscalers, carriers and enterprise customers to continue to outpace the wider Irish wholesale market, although near-term performance will be affected by the planned run-off of legacy voice and wireless services, anticipated customer churn and inflation in energy and other operating costs. Management’s priorities are to grow the core wholesale connectivity business, including converting its existing pipeline of hyperscaler and carrier fibre infrastructure and IRU opportunities, to complete the national fibre ring, to continue the expansion of Magnet+ in the enterprise market, and to optimise the cost base of the combined group.
DCU data centre business Belgium (acquired February 2025)
|
DCU |
£m |
|
Original cost |
59.41 |
|
Value at 1 April 2026 |
55.1 |
|
Unrealised value gain/(loss) |
4.1 |
|
Unrealised FX gain/(loss) |
(1.4) |
|
Value at 30 September 2026 |
57.8 |
|
Cash distributions since acquisition |
12.42 |
|
MOIC at 30 September 2026 |
1.2x |
|
|
EUR millions4 |
GBP3 millions4 |
|
| ||
|
|
Six months to 30 September 2026 |
Six months to 30 September 2025 |
Six months to 30 September 2026 |
Six months to 30 September 2025 |
% change |
% change |
|
Revenue |
22.1 |
20.6 |
19.1 |
17.6 |
7.5% |
8.5% |
|
EBITDA5 |
7.9 |
6.6 |
6.8 |
5.6 |
19.5% |
20.6% |
|
|
30 September 2026 |
31 March 2026 |
30 September 2026 |
31 March 2026 |
|
|
|
Gross borrowings6 |
58.5 |
52.5 |
50.0 |
46.1 |
|
|
|
Cash |
5.4 |
1.7 |
4.6 |
1.5 |
|
|
|
Undrawn debt6 |
50.5 |
56.5 |
43.1 |
49.6 |
|
|
In September 2026, DCU signed a contract with a provider of high-performance computing infrastructure for approximately 3MW of high‑density capacity at its Machelen data centre, on a five-year term with extension options. The contract will be served from the 4MW high-density, liquid-cooled conversion at Machelen approved earlier this year. The conversion is on track for completion in the first quarter of 2027 and, with billing expected to commence in April 2027, is expected to deliver a meaningful uplift in DCU’s recurring revenue. The customer paid a set-up fee on signing.
Demand in Belgium continues to shift towards high-density, AI-related deployments, as the country emerges as a secondary hub to the main European markets and data sovereignty requirements grow. Secured power is increasingly the decisive factor in winning this business, and DCU’s ability to offer it is a growing commercial advantage; DCU is in discussions with several AI and cloud providers on multi-megawatt requirements. Beyond Machelen, DCU is investing across its estate: cooling and efficiency upgrades at Oostkamp are complete and those at Antwerp are due to complete in the fourth quarter of 2026; land for a new facility at Ghent was acquired in July 2026; and an additional grid connection at Antwerp has been contracted for delivery in 2028.
In October 2026, DCU submitted a final proposal for the long-term development and operation of a new data centre facility in Belgium. The project would be underpinned by an anchor tenant, would be built out in phases in line with customer demand and would give DCU access to significant additional secured power. The outcome is expected shortly.
During the period DCU invested €5.4 million (£4.7 million) of growth capital expenditure in its capacity expansion programme. At 30 September 2026, DCU had €96.5 million (£83.9 million) of contracted revenue outstanding, and its net leverage under its facility agreement was 3.7x, comfortably within covenant levels. DCU’s committed expansion projects, including the initial phase of the new facility should it be awarded, are expected to be funded from its existing debt facilities and operating cash flow. The larger expansion opportunities DCU is evaluating across its sites are expected to be highly accretive but would require additional debt and potentially further equity from its shareholders, which the Company will evaluate alongside its other capital allocation priorities.
Looking ahead, DCU’s recurring revenue is expected to step up once the Machelen contract begins billing in April 2027, with further growth from the conversion of the multi-megawatt pipeline described above. Management’s focus is on securing those opportunities, delivering the capacity upgrades under way on schedule and maintaining cost discipline.
Hudson interconnect data centre New York (acquired January 2022)
|
Hudson |
£m |
|
Original cost |
55.8 |
|
Value at 1 April 2026 |
36.7 |
|
Unrealised value gain/(loss) |
2.7 |
|
Unrealised FX gain/(loss) |
(0.2) |
|
Further investment |
5.2 |
|
Value at 30 September 2026 |
44.3 |
|
MOIC at 30 September 2026 |
0.5x1 |
Construction of the two new data halls announced in 2025 was completed within budget. These two new data halls have added 1.5MW of IT capacity to Hudson, some of which had already been pre-sold.
In July 2026, Hudson signed a five-year, inflation-linked contract with a specialist provider of high-density GPU cloud infrastructure for AI workloads, covering 1.8MW of capacity with a right of first refusal over a further 2MW, and received an expansion order from an existing customer. Billing on an initial 450kW deployment commenced in October 2026, with the balance targeted for delivery by the end of 2026, and Hudson is building out the final two data halls on the sixth floor to support this pre-sold capacity, at a lower cost than the initial two data halls excluding customer‑specific capital expenditure.
A further contract for 288kW for a term of three years was subsequently closed with an existing customer, a compute-as-a-service platform which also utilises cross-connect services in the data centre, and in October 2026 Hudson signed a contract with another existing customer for 550kW for a term of five years. As a result of these new agreements, Hudson is expected to reach EBITDAaL breakeven in the next financial year on a run-rate basis once the contracted capacity is fully deployed.
As anticipated in the Annual Report, headline growth this financial year is being impacted by one customer opting to exit one of its core businesses that utilises capacity in Hudson. The customer, which is in the final year of its contract, filed for an expedited pre-structured bankruptcy to facilitate that exit. Hudson has therefore ceased to recognise revenue from this customer and has lodged a claim in the proceedings for the full amount due under the contract. The company’s budget for the current financial year already assumed early termination by this customer, and while some recovery is expected through the bankruptcy process and/or the sale of the customer’s equipment, its timing and quantum cannot yet be estimated reliably. Once the equipment is removed, Hudson can re-lease the space and is currently in discussions with potential customers for it.
Supported by its track record of service delivery, the customer relationships it has built and favourable market conditions, management is evaluating options to secure additional space, including brownfield and greenfield sites with connectivity to 60 Hudson Street, to serve growing demand and support further revenue growth.
Revenue for the six months to 30 September 2026 increased by 0.8% over the prior comparable period to $12.1 million (£9.0 million), while the EBITDAaL loss widened by 13.2% to $(2.2) million (£(1.6) million), reflecting the loss of revenue from the customer in bankruptcy, the contractual escalation of rent under the 60 Hudson Street lease and higher power costs as new customers were onboarded ahead of billing, partly offset by lower operating costs.
During the period the Company advanced $7.0 million (£5.2 million) of shareholder loans to Hudson to fund the data hall build-out and operating cash requirements. Management continues to explore various strategic initiatives to optimise the value of the asset.
BTC colocation services Belgium (acquired January 2024)
|
BTC |
£m |
|
Original cost |
5.2 |
|
Value at 1 April 2026 |
6.7 |
|
Unrealised value gain/(loss) |
0.1 |
|
Unrealised FX gain/(loss) |
(0.2) |
|
Value at 30 September 2026 |
6.6 |
|
Cash distributions in the period |
0.7 |
|
Cash distributions since acquisition |
1.2 |
|
MOIC at 30 September 2026 |
1.5x |
BTC continues to play a key role in the development of the 5G broadcast ecosystem with manufacturers and clients. BTC recently extended a contract with VRT, a national public service broadcaster, until December 2027. The extension was agreed to align with VRT’s multi-year budgeting cycle as a public service broadcaster, and BTC expects the contract, relating to the provision of passive infrastructure for radio broadcasting, to be extended for a longer term in 2027. BTC remains cash generative and paid a dividend of €0.8 million (£0.7 million) in July 2026 and held cash of €1.7 million (£1.5 million) at 30 September 2026.
Risk management
Principal risks and uncertainties
1. The capital markets may remain effectively closed to the Company for a significant period. As a consequence, the Company may be unable to raise new capital and it may therefore be unable to progress investment opportunities.
How we mitigate risk
The Company has acquired a portfolio of cash‑generating assets with significant organic growth prospects, which together are capable of providing returns meeting the investment objective without further acquisitions. The Investment Manager also continues to consider potential alternative sources of capital, including debt and coinvestment.
How the risk is changing
Share price discounts to NAV in the LSE-listed investment trust sector have continued to reduce, but most, including the Company, still trade at a discount and the gradual improvement over the last two years appears to have slowed somewhat. It remains impossible to predict whether or when market conditions may improve sufficiently for new equity issuance to be undertaken.
Movement in the period - Level
2. There is a risk that, even when the capital markets are open, insufficient numbers of investors are prepared to invest new capital, or that investors are unwilling to invest sufficient new capital, to enable the Company to achieve its investment objectives.
How we mitigate risk
The Company has established a five-year track record of successful investments, which together are capable of providing returns meeting the investment objective without further acquisitions. The Investment Manager has deep sector knowledge and investment expertise and is well-known and respected in the market.
How the risk is changing
Although conditions in the equity market for investment trusts are still quite weak, potentially indicating a lack of available capital for investment or lack of appetite for investment in the investment trust sector, the Company’s move to the Official List in April 2026 should help make its shares more attractive to a wider range of investors.
Movement in the period - Level
3. The Company may lose investment opportunities if it does not match investment prices, structures and terms offered by competing bidders. Conversely, the Company may experience decreased rates of return and increased risk of loss if it matches investment prices, structures and terms offered by competitors.
How we mitigate risk
The Investment Manager operates a prudent and disciplined investment strategy, participating in transaction processes only where it can be competitive without compromising its investment objectives.
How the risk is changing
The Investment Manager has been able to identify and pursue bilateral opportunities rather than auction processes, where competition for those assets has been a less significant factor. However, there can be no guarantee that suitable further bilateral opportunities will arise. In addition, current equity market conditions and the consequent limitations on the Company’s ability to access equity capital markets may mean that it continues to be unable to pursue certain investment opportunities.
Movement in the period - Level
4. There can be no guarantee or assurance the Company will achieve its investment objectives, which are indicative targets only. Investments may fail to deliver the projected earnings, cash flows and/or capital growth expected at the time of acquisition, and valuations may be affected by foreign exchange fluctuations. The actual rate of return may be materially lower than the targeted rate of return.
How we mitigate risk
The Investment Manager performs a rigorous due diligence process with internal specialists and expert professional advisors in fields relevant to the proposed investment before any investment is made. The Investment Manager also carries out a regular review of the investment environment and benchmarks target and actual returns against the industry and competitors.
How the risk is changing
The results of our investments to date continue to be materially in line with our projections at the time of their acquisition and with the target return for the Company. Furthermore their aggregate fair value has increased significantly during the Company’s period of ownership. This demonstrates the Investment Manager’s ability to manage the investments to deliver returns and growth.
Movement in the period - Level
5. Actual results of portfolio investments may vary from the projections, which may have a material adverse effect on NAV.
How we mitigate risk
Senior members of the Investment Manager’s team work closely with the local management teams of the portfolio companies. The Investment Manager provides the Board with at least quarterly updates of portfolio investment performance and detail around any material variation from budget and forecast returns.
How the risk is changing
The results of our investments to date continue to be materially in line with our projections at the time of their acquisition and with their budgets for the current year. This demonstrates the quality of the Investment Manager’s projections and its ability to manage the investments to deliver the expected results.
Movement in the period - Level
6. The Company invests in unlisted digital infrastructure assets, and such investments are illiquid. There is a risk that it may be difficult for the Company to sell the digital infrastructure assets and the price achieved on any realisation may be at a discount to the prevailing valuation of the relevant digital infrastructure asset.
How we mitigate risk
The Investment Manager has considerable experience across relevant digital infrastructure sectors, and senior members of the team have had leadership roles in over $80 billion of relevant transactions. The Company seeks a diversified range of investments so that exposure to temporary poor conditions in any one market is limited.
How the risk is changing
The Company is a longer-term investor and is not currently seeking a full divestment of any asset. The Company’s prudent leverage position, as regards both the quantum and terms of its debt, mean that the risk of a forced divestment is very low. Exposure to divestment risk is limited in the short to medium term.
Movement in the period - Level
7. The Company may invest in digital infrastructure assets which are in construction or construction‑ready or otherwise require significant future capital expenditure. Digital infrastructure assets which have significant capital expenditure requirements may be exposed to cost overruns, construction delay, failure to meet technical requirements or construction defects.
How we mitigate risk
The Investment Manager has significant experience of managing construction risks arising from digital infrastructure assets and will also engage third parties where appropriate to oversee such construction.
How the risk is changing
In pursuance of the Company’s Buy, Build & Grow model, it will undertake significant capital construction projects. This risk has been very low to date, and remains low, but will continue to increase as capital investment increases. In particular, the Prague Gateway project currently being undertaken by CRA, and on a smaller scale the data halls being constructed by Hudson, involve some construction risk.
Movement in the period - Higher
8. The Company operates in markets in Europe and North America which are affected by global events. Supply chain disruption may be caused by conflicts (e.g. in Ukraine), political change (e.g. the rise of political populism), trade barriers, climate change and public health crises.
How we mitigate risk
The Company has acquired a geographically diverse portfolio of assets in various segments of the digital infrastructure market, and will continue to seek further diversification, reducing the impact of specific events on the Company as a whole.
How the risk is changing
Policy uncertainty, as measured by the Global Economic Policy Uncertainty index, has decreased significantly since its peak in April 2026, but remains very high compared to a longer-term average. Equity market volatility as measured by the VIX index is lower than its long-term average, but debt markets are more volatile, with UK 10-year gilt yields having risen by c.100bps since March 2026.
Movement in the period - Level
9. The Company and its portfolio companies, in common with most businesses, face a diverse array of cyber threats, including ransomware, phishing and supply chain attacks. Cyber incidents can have severe financial and reputational consequences.
How we mitigate risk
The Investment Manager and each portfolio company has an IT function whose remit specifically includes cybersecurity. The nature of the portfolio companies’ business is such that there is significant in-house experience and expertise in the field of cybersecurity, and cybersecurity is a standing agenda item for the board of each portfolio company.
How the risk is changing
The incidence of reported cyber attacks continues to rise, with high-profile cases of cyber incidents in the news recently causing major companies significant disruption and cost.
Movement in the period - Level
10. The Company is dependent on key personnel within the Investment Manager to make and manage investments, and could be adversely affected if those individuals left or were incapacitated.
How we mitigate risk
The Investment Manager regularly considers succession planning, and discusses this with the Company’s Management Engagement Committee. The Investment Manager has one of the largest specialist digital infrastructure teams in the market and so has considerable strength in depth. The investment process is well understood and documented, and investment decisions are made by an investment committee and the Board, not by one or a small number of individuals.
How the risk is changing
The Investment Manager has a dedicated, specialist digital infrastructure team, with strength in depth. Despite the recently announced changes in the Investment Manager arrangements, the same expert digital infrastructure team continues to manage the investments and to explore new opportunities.
Movement in the period - Level
Statement of Directors’ responsibilities
The Directors are responsible for preparing this Interim Report in accordance with the Disclosure Guidance and Transparency Rules of the UK’s Financial Conduct Authority.
In preparing the unaudited condensed set of interim financial statements included within the Interim Report, the Directors are required to:
prepare and present the condensed set of interim financial statements in accordance with IAS 34 Interim Financial Reporting issued by the International Accounting Standards Board (IASB) and the DTRs;
ensure the condensed set of interim financial statements has adequate disclosures;
select and apply appropriate accounting policies; and
make accounting estimates that are reasonable in the circumstances.
The Chairman’s statement and the Financial and operational review meet the requirements of an Interim Managers’ Report, and include a fair review of the information required by:
DTR 4.2.7R, being an indication of important events during the first six months and description of principal risks and uncertainties for the remaining six months of the year; and
DTR 4.2.8R, being the disclosure of related parties’ transactions and changes therein.
The Directors are responsible for designing, implementing and maintaining such internal controls as they determine are necessary to enable the preparation of the condensed set of interim financial statements that is free from material misstatement whether due to fraud or error.
On behalf of the Board
Shonaid Jemmett-Page
Chairman
23 November 2026
Unaudited Condensed Statement of Financial Position
As at 30 September 2026 (unaudited)
|
|
Note |
As at |
As at |
|
Non-current assets |
|
|
|
|
Investments at fair value through profit or loss |
5 |
1,299,778 |
1,276,825 |
|
|
|
1,299,778 |
1,276,825 |
|
Current assets |
|
|
|
|
Trade and other receivables |
6 |
9,471 |
10,617 |
|
Cash and cash equivalents |
|
4,734 |
10,038 |
|
|
|
14,205 |
20,655 |
|
Current liabilities |
|
|
|
|
Loans and borrowings |
7 |
(196,538) |
(177,440) |
|
Accrued expenses and other creditors |
|
(1,229) |
(2,091) |
|
|
|
(197,767) |
(179,531) |
|
Net current liabilities |
|
(183,562) |
(158,876) |
|
Net assets |
|
1,116,216 |
1,117,949 |
|
|
|
|
|
|
Equity |
|
|
|
|
Share capital |
8 |
774,218 |
774,218 |
|
Retained earnings – Revenue |
|
20,714 |
26,670 |
|
Retained earnings – Capital |
|
321,284 |
317,061 |
|
Total equity |
|
1,116,216 |
1,117,949 |
|
|
|
|
|
|
Number of shares in issue |
|
|
|
|
Ordinary shares |
8 |
765,718,165 |
765,718,165 |
|
|
|
765,718,165 |
765,718,165 |
|
Net asset value per ordinary share in pence |
10 |
145.77 |
146.00 |
The unaudited condensed interim financial statements were approved and authorised for issue by the Board on 23 November 2026 and signed on their behalf by:
Shonaid Jemmett-Page Sian Hill
Chairman Director
The accompanying notes form an integral part of these unaudited condensed interim financial statements.
Unaudited Condensed Statement of Comprehensive Income
For the six months ended 30 September 2026
|
|
|
|
For the six months ended 30 September 2026 |
|
For the six months ended 30 September 2025 | ||||||
|
|
Note |
|
Revenue £’000 |
Capital £’000 |
Total £’000 |
|
Revenue £’000 |
Capital £’000 |
Total £’000 | ||
|
Movement in fair value of investments held at fair value through profit or loss |
5 |
|
– |
17,784 |
17,784 |
|
– |
89,722 |
89,722 | ||
|
Management fee income |
|
|
359 |
– |
359 |
|
666 |
– |
666 | ||
|
Dividend income |
|
|
– |
– |
– |
|
18,867 |
– |
18,867 | ||
|
|
|
|
359 |
17,784 |
18,143 |
|
19,533 |
89,722 |
109,255 | ||
|
Operating expenses |
|
|
|
|
|
|
|
|
| ||
|
Management fees |
9 |
|
(4,409) |
– |
(4,409) |
|
(3,445) |
– |
(3,445) | ||
|
Other expenses |
4 |
|
(2,111) |
– |
(2,111) |
|
(951) |
– |
(951) | ||
|
|
|
|
(6,520) |
– |
(6,520) |
|
(4,396) |
– |
(4,396) | ||
|
Operating profit/(loss) |
|
|
(6,161) |
17,784 |
11,623 |
|
15,137 |
89,722 |
104,859 | ||
|
Foreign exchange movements on working capital |
|
|
– |
3,859 |
3,859 |
|
– |
(8,049) |
(8,049) | ||
|
Finance income |
|
|
205 |
– |
205 |
|
237 |
– |
237 | ||
|
Profit/(loss) for the period before tax |
|
|
(5,956) |
21,643 |
15,687 |
|
15,374 |
81,673 |
97,047 | ||
|
Tax charge |
|
|
– |
– |
– |
|
– |
– |
– | ||
|
Profit/(loss) for the period after tax |
|
|
(5,956) |
21,643 |
15,687 |
|
15,374 |
81,673 |
97,047 | ||
|
Total comprehensive income/(loss) for the period |
|
|
(5,956) |
21,643 |
15,687 |
|
15,374 |
81,673 |
97,047 | ||
|
|
|
|
|
|
|
|
|
|
| ||
|
Weighted average number of shares |
|
|
|
|
|
|
|
|
| ||
|
Basic – Ordinary Shares |
8,10 |
|
765,718,165 |
765,718,165 |
765,718,165 |
|
765,715,477 |
765,715,477 |
765,715,477 | ||
|
Diluted – Ordinary Shares |
8,10 |
|
765,718,165 |
765,718,165 |
765,718,165 |
|
765,715,477 |
765,715,477 |
765,715,477 | ||
|
|
|
|
|
|
|
|
|
|
| ||
|
Earnings per share |
|
|
|
|
|
|
|
|
| ||
|
Basic – Earnings/(loss) from continuing operations in pence |
10 |
|
(0.78) |
2.83 |
2.05 |
|
2.01 |
10.67 |
12.67 | ||
|
Diluted – Earnings/(loss) from continuing operations in pence |
10 |
|
(0.78) |
2.83 |
2.05 |
|
2.01 |
10.67 |
12.67 | ||
The accompanying notes form an integral part of these unaudited condensed interim financial statements.
Unaudited Condensed Statement of Changes in Equity
For the six months ended 30 September 2026
|
|
Note |
|
Share capital |
Retained earnings-Revenue |
Retained earnings-Capital |
Total equity |
|
Opening net assets attributable to shareholders at 1 April 2025 |
|
|
774,214 |
(162) |
218,467 |
992,519 |
|
Shares repurchased in the period |
8 |
|
– |
– |
– |
– |
|
Dividends paid in the period |
11 |
|
– |
– |
(17,229) |
(17,229) |
|
Profit and total comprehensive income for the period |
|
|
– |
15,374 |
81,673 |
97,047 |
|
Closing net assets attributable to shareholders at 30 September 2025 |
|
|
774,214 |
15,212 |
282,911 |
1,072,337 |
|
|
Note |
|
Share capital |
Retained earnings-Revenue |
Retained earnings-Capital |
Total equity |
|
Opening net assets attributable to shareholders at 1 April 2026 |
|
|
774,218 |
26,670 |
317,061 |
1,117,949 |
|
Shares repurchased in the period |
8 |
|
– |
– |
– |
– |
|
Dividends paid in the period |
11 |
|
– |
– |
(17,420) |
(17,420) |
|
Profit and total comprehensive income for the period |
|
|
– |
(5,956) |
21,643 |
15,687 |
|
Closing net assets attributable to shareholders as at 30 September 2026 |
|
|
774,218 |
20,714 |
321,284 |
1,116,216 |
The accompanying notes form an integral part of these unaudited condensed interim financial statements.
Unaudited Condensed Statement of Cash Flows
For the six months ended 30 September 2026
|
|
Note |
For the six 30 September 2026 £’000 |
For the six 30 September 2025 £’000 |
|
Operating activities |
|
|
|
|
Operating profit for the period |
|
11,623 |
104,859 |
|
Adjustments to operating activities |
|
|
|
|
Net gain on investments at fair value through profit or loss |
5 |
(17,784) |
(89,722) |
|
Dividend income |
|
– |
(18,867) |
|
Reclassification of investment to investment management fees receivable |
|
– |
1,674 |
|
Decrease in receivables |
|
1,069 |
301 |
|
Decrease in payables |
|
(864) |
(436) |
|
Net cash flows used in operating activities |
|
(5,956) |
(2,191) |
|
Cash flows (used in)/generated from investing activities |
|
|
|
|
Investment additions |
5 |
(5,169) |
(6,281) |
|
Finance income |
|
21 |
243 |
|
Dividend income |
|
– |
18,867 |
|
Net cash flows (used in)/generated from investing activities |
|
(5,148) |
12,829 |
|
Cash flows (used in)/generated from financing activities |
|
|
|
|
Loan drawn down |
7 |
23,523 |
7,628 |
|
Loan repaid |
7 |
(174) |
– |
|
Finance costs paid |
|
– |
– |
|
Bank interest received |
|
184 |
11 |
|
Dividends paid |
11 |
(17,420) |
(17,229) |
|
Net cash flows generated from/(used in) financing activities |
|
6,113 |
(9,589) |
|
(Decrease)/increase in cash and cash equivalents during the period |
|
(4,991) |
1,049 |
|
Cash and cash equivalents at the beginning of the period |
|
10,038 |
6,137 |
|
Exchange translation movement |
|
(313) |
(33) |
|
Cash and cash equivalents at the end of the period |
|
4,734 |
7,153 |
The accompanying notes form an integral part of these unaudited condensed interim financial statements.
Notes to the interim financial statements
1. General information
Corilis Digital Infrastructure Limited (the Company; LSE ticker: CORD) was incorporated and registered in Guernsey on 4 January 2021 with registered number 68630 as a non-cellular company limited by shares and is governed in accordance with the provisions of the Companies (Guernsey) Law 2008. The registered office address is East Wing, Trafalgar Court, Les Banques, St Peter Port, Guernsey GY1 3PP.
2. Key accounting policies
Basis of preparation
These condensed unaudited Interim Financial Statements (the Interim Financial Statements) have been prepared in accordance with International Accounting Standard (IAS) 34 Interim Financial Reporting. The accounting policies are consistent with those set out in the Annual Report for the year ended 31 March 2026. They should be read in conjunction with the Annual Report for the year ended 31 March 2026 as they provide an update on previously reported information.
The Interim Financial Statements were authorised for issue by the Directors on 23 November 2026.
The Interim Financial Statements do not constitute statutory accounts. The financial information for the six months ended 30 September 2026, and for the six months ended 30 September 2025 are unaudited and have not been reviewed by the Company’s auditor. The Annual report and financial statements for the year ended 31 March 2026 has been published to the National Storage Mechanism and is also available at www.corilisdigital.com.
Segmental reporting
The chief operating decision maker, who is responsible for allocating resources and assessing performance of the operating segments, has been identified as the Board as a whole. The key measure of performance used by the Directors to assess the Company’s performance and to allocate resources is the Company’s NAV, as calculated under IFRS as issued by the IASB, and therefore no reconciliation is required between the measure of profit or loss used by the Board and that contained in the Interim Financial Statements.
For management purposes, the Company is organised into one main operating segment, which invests in digital infrastructure assets.
Due to the Company’s nature, it has no customers.
Going concern
The Interim Financial Statements have been prepared on a going concern basis. As at 30 September 2026, the Company had net current liabilities of £183.6 million. The Directors have assessed the Company’s financial position, including its access to group support and funding arrangements, and have a reasonable expectation that the Company has adequate resources to meet its liabilities as they fall due for at least the next 12 months.
While the ongoing conflicts and political changes in different parts of the world during the period have created some supply chain disruption and market volatility, this did not have a material direct effect on the results of the business. The Directors are satisfied that the resulting macroeconomic environment is not likely to significantly restrict business activity.
The Directors have reviewed different scenarios and stress testing of the cash flow forecasts prepared by the Investment Manager to understand the resilience of the Company’s cash flows to adverse scenarios.
The Directors and Investment Manager are actively monitoring these risks and their potential effect on the Company and its underlying investments. In particular, they have considered the following specific key potential impacts:
|
— |
increased volatility in the fair value of investments; |
|
— |
disruptions to business activities of the underlying investments; and |
|
— |
recoverability of income and principal and allowance for expected credit losses. |
In considering the key potential impacts above on the Company and its underlying investments, the Investment Manager has assessed these with reference to the mitigation measures in place. Based on this assessment, the Directors do not consider that the effects of the above risks have created a material uncertainty over the assessment of the Company as a going concern.
As further detailed in note 5 to the Interim Financial Statements, the Board uses a third-party valuation provider to perform an independent valuation of the underlying investments. Additionally, the Investment Manager and Directors have considered the cash flow forecast to determine the term over which the Company can remain viable given its current resources. On the basis of this review and, after careful consideration and making due enquiries, the Directors have a reasonable expectation that the Company has adequate resources to continue in operational existence for at least 12 months from the date of this report, being the period of assessment considered by the Directors. Accordingly, they continue to adopt the going concern basis in preparing the Interim Financial Statements.
3. Significant accounting judgements, estimates and assumptions
The preparation of the Interim Financial Statements in conformity with IFRS requires the Board to make judgements, estimates and assumptions that affect the application of policies and reported amounts of assets and liabilities, income and expenses. The estimates and associated assumptions are based on historical experience and other factors that are believed to be reasonable under the circumstances, the results of which form the basis of making the judgements about the carrying values of assets and liabilities that are not readily apparent from other sources. Actual results may differ from these estimates.
The estimates and underlying assumptions are reviewed on an ongoing basis. Revisions to accounting estimates are recognised in the period in which the estimate is revised if the revision affects only that period or in the period of the revision and future periods if the revision affects both current and future periods. All key sources of estimation uncertainty within the Interim Financial Statements are consistent with those stated in the Annual report for the year ended 31 March 2026.
Judgements
In the process of applying the Company’s accounting policies, management has made the following judgements, which have the most significant effect on the amounts recognised in the financial statements:
Assessment as an investment entity
In the judgement of the Directors, the Company qualifies as an Investment Entity under IFRS 10 and therefore its subsidiary entities have not been consolidated in the preparation of the Interim Financial Statements.
Assumptions and estimation uncertainties
Information about assumptions and estimation uncertainties that have a significant risk of resulting in a material adjustment to the carrying amounts of assets and liabilities within the period ended 30 September 2026 is included in note 5 and relates to the determination of fair value of investments with significant unobservable inputs.
Climate change
In preparing the Interim Financial Statements, the Directors have considered the impact of climate change, particularly in the context of the climate change risks identified in the ESG report section of the Interim Report.
The Directors have also considered the medium- and longer‑term cash flow impacts of climate change on a number of key estimates within the Interim Financial Statements, including:
|
— |
the estimates of future cash flows used in assessments of the fair value of investments; and |
|
— |
the estimates of future profitability used in the assessment of distributable income. |
These considerations did not have a material impact on the financial reporting judgements and estimates in the current period. This reflects the conclusion that climate change is not expected to have a significant impact on the Company’s short- or medium-term cash flows including those considered in the going concern assessment.
4. Other expenses
Other expenses in the Unaudited Condensed Statement of Comprehensive Income comprises:
|
|
|
For the six months ended |
For the six months ended |
|
Legal and professional fees |
|
750 |
262 |
|
Directors’ fees |
|
121 |
118 |
|
Fees payable to the statutory auditor |
|
109 |
109 |
|
Other expenses |
|
1,131 |
462 |
|
|
|
2,111 |
951 |
5. Investments at fair value through profit or loss
|
As at 30 September 2026 |
Loans |
Equity |
Total |
|
Opening balance |
25,227 |
1,251,598 |
1,276,825 |
|
Additions |
5,169 |
– |
5,169 |
|
Reclassification of investment to investment management fees receivable |
– |
– |
– |
|
Net (losses)/gains on investments |
(96) |
17,880 |
17,784 |
|
|
30,300 |
1,269,478 |
1,299,778 |
|
As at 31 March 2026 |
Loans |
Equity |
Total |
|
Opening balance |
12,635 |
1,112,060 |
1,124,695 |
|
Additions |
12,607 |
– |
12,607 |
|
Reclassification of investment to investment management fees receivable |
– |
(1,674) |
(1,674) |
|
Net (losses)/gains on investments |
(15) |
141,212 |
141,197 |
|
|
25,227 |
1,251,598 |
1,276,825 |
As at 30 September 2026, the equity value of Company’s investment in its subsidiary Corilis Digital Holdings UK Limited (CDH UK) and CDIL Data Centre USA LLC (Hudson Interxchange) was £1,255.5 million (31 March 2026: £1,240.1 million) and £14.0 million (31 March 2026:£11.5 million), respectively. CDH UK is the holding company for all of the Company’s investments with the exception of Hudson, which is held directly.
During the period ended 30 September 2026, the Company made loan advances to Hudson Interxchange amounting to £5.2 million (31 March 2026: £12.6 million) bringing its total loan investments to £30.3 million (31 March 2026: £25.2 million). Including the equity investments above, the total investment in Hudson Interxchange as of 30 September 2026 was valued at £44.3 million (31 March 2026: £36.7 million).
The fair value of the Company’s effective 37.4% economic (50% voting) interest in DCU Invest NV (DCU) held through its indirect 78.8% subsidiary Corilis Digital Holdings Six Limited (CDH6) as at 30 September 2026 was £57.8 million (31 March 2026: £55.1 million). In the prior period, CDH6 issued €14 million of shares in CDH6 to Cordiant Co-Invest SMA 1 SCSp (the Co-investor), resulting in the Co-investor owning 21.2% of the equity in CDH6; the Co-investor also acquired €6 million (21.2%) of the then-outstanding shareholder loan. That loan was partly repaid and partly capitalised during the prior period, and the balance at 30 September 2026 was nil (31 March 2026: nil).
The fair value of the Company’s equity investment in České Radiokomunikace a.s. (CRA) held through its indirect subsidiary Corilis Digital Holdings Two Limited (CDH Two) as at 30 September 2026 was £515.7 million (31 March 2026: £524.2 million).
The fair value of the Company’s equity investment in Emitel held through its indirect subsidiary Corilis Digital Holdings One Limited (CDH One) as at 30 September 2026 was £613.7 million (31 March 2026: £623.0 million).
The fair value of the Company’s investment in Speed Fibre held through its indirect subsidiary Corilis Digital Holdings Ireland Limited (CDH Ireland) as at 30 September 2026 was £120.0 million (31 March 2026: £116.3 million).
The fair value of the Company’s investment in Belgian Tower Company (BTC) held through its indirect subsidiary Corilis Digital Holdings UK Limited (CDH UK) as at 30 September 2026 was £6.6 million (31 March 2026: £6.7 million).
Fair value measurements
IFRS 13 requires disclosure of fair value measurement by level. The level of fair value hierarchy within the financial assets or financial liabilities is determined on the basis of the lowest level input that is significant to the fair value measurement. Financial assets and financial liabilities are classified in their entirety into only one of the following three levels:
Level 1 – quoted prices (unadjusted) in active markets for identical assets or liabilities;
Level 2 – inputs other than quoted prices included within Level 1 that are observable for the assets or liabilities, either directly (i.e. as prices) or indirectly (i.e. derived from prices); and
Level 3 – inputs for assets or liabilities that are not based on observable market data (unobservable inputs).
The determination of what constitutes ‘observable’ requires significant judgement by the Company. The Directors consider observable data to be market data that is readily available, regularly distributed or updated, reliable and verifiable, not proprietary, and provided by independent sources that are actively involved in the relevant market.
The Company’s investments have been classified within Level 3 as the investments are not traded and contain unobservable inputs. The valuations have been carried out by the Investment Manager. In order to obtain assurance in respect of the valuations carried out by the Investment Manager, the Company has engaged a third-party valuations expert to carry out an independent assessment of the unobservable inputs and of the forecast cash flows of the Company’s investments.
During the period ended 30 September 2026, there were no transfers of investments at fair value through profit or loss from or to Level 3 (31 March 2026: nil).
The Company’s investments have been valued using a DCF methodology. This involves forecasting the entity’s future cash flows, taking into account the terms of existing contracts, expected rates of contract renewal and targeted new contracts, and the economic and geopolitical environment. These cash flows are discounted at the entity’s estimated weighted average cost of capital (WACC). This method also requires estimating a terminal value, being the value of the investment at the end of the period for which cash flows can be forecast with reasonable accuracy, which is March 2033 for CRA, December 2032 for Emitel, December 2033 for Speed Fibre, December 2035 for DCU, March 2040 for Hudson and March 2033 for BTC. The terminal value is calculated using an assumed terminal growth rate (TGR) into perpetuity based on anticipated industry trends and long-term inflation rates.
In forming a view on the valuations, the Directors have considered the potential impact of an ongoing legal dispute within one of the portfolio companies.
The DCF valuation methodology requires estimation of unobservable inputs. The following table summarises the effect on the valuation of the Company’s portfolio of reasonably possible alternative investment assumptions with regards to those estimates; these are calculated using the DCF valuation models referred to above.
|
30 September 2026 |
|
|
|
|
|
|
Unobservable input |
Range |
Valuation if rate increases by 1% (£m) |
Movement in valuation (£m) |
Valuation if rate decreases by 1% (£m) |
Movement in valuation (£m) |
|
WACC |
8.875%-10.55% |
1,126 |
(232) |
1,659 |
301 |
|
TGR |
0.00%-3.00% |
1,565 |
207 |
1,199 |
(159) |
|
31 March 2026 |
|
|
|
|
|
|
Unobservable input |
Range |
Valuation if rate increases by 1% (£m) |
Movement in valuation (£m) |
Valuation if rate decreases by 1% (£m) |
Movement in valuation (£m) |
|
WACC |
8.80%-10.45% |
1,140 |
(222) |
1,652 |
290 |
|
TGR |
0.00%-3.00% |
1,558 |
196 |
1,212 |
(150) |
The DCF valuations derived by the Investment Manager and those derived by the third-party valuation expert were not materially different from each other, and the other valuation techniques used provided assurance that the DCF valuations are reasonable.
Changes to WACC and TGR could be driven by, among other factors: market movements in interest rates, inflation rates and other macroeconomic indicators; perception of risk and volatility in debt and equity markets affecting general market returns; and political and societal changes and technological developments affecting the operations of the portfolio companies and the countries in which they operate. These sensitivity measures exclude the working capital balances of investee companies in the structure.
Both the Investment Manager and the third-party valuation expert use a combination of other valuation techniques to verify the reasonableness of the DCF valuations, as recommended in the International Private Equity and Venture Capital (IPEV) Valuation Guidelines:
earnings multiple: applying a multiple, derived largely from comparable listed entities in the market, to the forecast EBITDA of the entity to calculate an enterprise value, and then deducting the fair value of any debt in the entity;
DCF with multiple: calculating a DCF valuation of the cash flows of the entity to the end of the period for which cash flows can be forecast with reasonable accuracy, and then applying a multiple to EBITDA at the end of that period to estimate a terminal value; and
dividend yield: forecasting the entity’s capacity to pay dividends in the future and applying an equity yield to that forecast dividend, based on comparable listed entities in the market.
6. Trade and other receivables
|
|
As at 30 September 2026 |
As at 31 March 2026 |
|
Cash collateral |
8,491 |
8,556 |
|
Other debtors |
60 |
564 |
|
Amounts receivable from related parties |
896 |
1,440 |
|
Prepayments |
24 |
57 |
|
|
9,471 |
10,617 |
Cash collateral relates to one security deposit held in money market accounts. An amount of USD 11.3 million (£8.5 million) relates to collateral for a letter of credit relating to the lease of the building occupied by Hudson, and during the period ended 30 September 2026, the cash collateral generated interest at a rate of 2% per annum (31 March 2026: 3.8% per annum).
7. Loans and borrowings
|
|
As at 30 September 2026 |
As at 31 March 2026 |
|
Opening balance |
177,440 |
147,591 |
|
Drawdown of principal during the period |
23,523 |
21,664 |
|
Repayment of principal during the period |
(174) |
(3) |
|
Exchange (gains)/losses |
(4,251) |
8,188 |
|
|
196,538 |
177,440 |
Loans and borrowings relates to the intercompany liability to CDH UK which is interest-free and repayable on demand. During the period ended 30 September 2026, an additional and separate loan of £23.5 million (31 March 2026: £21.7 million) was issued and drawn down. As at 30 September 2026, the total outstanding balance of these loans was equivalent of £196.5 million (31 March 2026: £177.4 million).
8. Share capital
Subject to any special rights, restrictions, or prohibitions regarding voting for the time being attached to any shares, holders of ordinary shares have the right to receive notice of and to attend, speak and vote at general meetings of the Company and each holder being present in person or by proxy shall upon a show of hands have one vote and upon a poll shall have one vote in respect of each ordinary share that they hold.
Holders of ordinary shares are entitled to receive and participate in any dividends or distributions of the Company in relation to assets of the Company that are available for dividend or distribution. On a winding-up of the Company, the surplus assets of the Company available for distribution to the holders of ordinary shares (after payment of all other debts and liabilities of the Company attributable to the ordinary shares) shall be divided amongst the holders of ordinary shares pro rata according to their respective holdings of ordinary shares.
Ordinary shares
|
|
30 September 2026 Number of shares |
£’000 |
31 March 2026 Number of shares |
£’000 |
|
Issued and fully paid |
773,559,707 |
780,104 |
773,559,707 |
780,104 |
|
Shares held in treasury |
(7,841,542) |
(5,886) |
(7,841,542) |
(5,886) |
|
Outstanding shares at period/year end |
765,718,165 |
774,218 |
765,718,165 |
774,218 |
Holders of ordinary shares are entitled to all dividends paid by the Company on the ordinary shares and, on a winding up, provided the Company has satisfied all of its liabilities, ordinary shareholders are entitled to all of the surplus assets of the Company attributable to the ordinary shares.
Treasury shares
|
|
30 September 2026 Number of shares |
31 March 2026 Number of shares |
|
Opening balance |
7,841,542 |
7,844,230 |
|
Shares reissued during the period/year |
– |
(2,688) |
|
Closing balance at period/year end |
7,841,542 |
7,841,542 |
The Company has not undertaken any market buybacks during the period ended 30 September 2026 (31 March 2026: nil).
9. Management and performance fees
Under the Investment Management Agreement, the Investment Manager is entitled to receive an annual management fee and a performance fee, plus any applicable VAT, in addition to the reimbursement of reasonable expenses incurred by it in the performance of its duties.
Management fee
The Investment Manager receives from the Company an annual management fee, based on the average market capitalisation of the Company, calculated using the closing market capitalisation for each LSE trading day for the relevant month, and paid monthly in arrears. The management fee has been payable since 30 April 2021, being the date on which more than 75% of the IPO proceeds were deployed in investment activities.
The annual management fee is calculated on the following basis:
1.00% of the average market capitalisation up to £500 million;
0.90% of the average market capitalisation between £500 million and £1 billion; and
0.80% of the average market capitalisation in excess of £1 billion.
Until 18 August 2025, the Investment Manager was required to apply an amount equal to 10% of the annual management fee to purchase or subscribe for ordinary shares in the Company, either through new issuance or market purchases, depending on the trading price relative to NAV. Following the amendment and restatement of the Investment Management Agreement on 18 August 2025, this requirement has been removed. The Investment Manager is no longer required to reinvest any portion of the management fee into shares. However, it must maintain at all times the same number of shares as it would have been required to hold if the previous reinvestment requirement had remained in place.
For the period ended 30 September 2026, the Investment Manager has charged management fees of £4.4 million (30 September 2025: £3.4 million) to the Company, with £nil (31 March 2026: £0.8 million) owed at period/year end.
Performance fee
The Investment Manager may in addition receive a performance fee on each performance fee calculation date, dependent on the performance of the Company’s NAV and share price. The first performance fee calculation date was 31 March 2024 and subsequent calculation dates are on 31 March each year thereafter. The fee is equal to 12.5% of the excess return over the target of 9% for the NAV return or share price return, whichever is the lower, multiplied by the time-weighted average number of ordinary shares in issue (excluding any ordinary shares held in treasury) during the relevant period.
Any performance fee is to be satisfied as follows:
|
— |
as to 50% in cash; and | |
|
— |
as to the remaining 50% of the performance fee, subject to certain exceptions and the relevant regulatory and tax requirements: | |
|
|
a) |
if the average trading price, calculated over the 20 trading days immediately preceding the performance fee calculation date, is equal to or higher than the last reported NAV per ordinary share (as adjusted to reflect any dividends reflected in the average trading price) the Company will issue to the Investment Manager such number of new ordinary shares (credited as fully paid) as is equal to the performance fee investment amount divided by the average trading price (rounded down to the nearest whole number of ordinary shares); or |
|
|
b) |
if the average trading price is lower than the last reported NAV per ordinary share (as adjusted to reflect any dividends reflected in the average trading price) then the Company shall (on behalf of, and as agent for, the Investment Manager) apply the performance fee investment amount in making market purchases of ordinary shares, provided any such ordinary shares are purchased at prices below the last reported NAV per ordinary share. |
Any ordinary shares subscribed or purchased by the Investment Manager pursuant to the above arrangements will, subject to usual exceptions, be subject to a lock-up of 36 months from the date of subscription or purchase.
For the period ended 30 September 2026, no performance fee is due to the Investment Manager (31 March 2026: £nil) and no amount has been accrued as the share price performance hurdle has not been met.
10. Earnings per share and net asset value per share
|
|
For the six months ended 30 September 2026 | ||
|
|
Basic |
Diluted | |
|
Allocated profit attributable to this share class – £’000 |
15,687 |
15,687 | |
|
Weighted average number of shares in issue |
765,718,165 |
765,718,165 | |
|
Earnings per share from continuing operations in the period in pence |
2.05 |
2.05 | |
|
|
For the six months ended 30 September 2025 | ||
|
|
Basic |
Diluted | |
|
Allocated profit attributable to this share class – £’000 |
97,047 |
97,047 | |
|
Weighted average number of shares in issue |
765,715,477 |
765,715,477 | |
|
Earnings per share from continuing operations in the period in pence |
12.67 |
12.67 | |
Following the final exercise date in February 2026, all remaining unexercised Subscription Shares were cancelled. Accordingly, no Subscription Shares remain in issue.
|
|
As at |
Year ended |
|
Weighted average number of shares used in basic earnings per share |
765,718,165 |
765,715,698 |
|
Weighted average number of shares used in diluted earnings per share |
765,718,165 |
765,715,698 |
|
Net asset value – £’000 |
1,116,216 |
1,117,949 |
|
Number of ordinary shares issued |
765,718,165 |
765,718,165 |
|
Net asset value per share in pence |
145.77 |
146.00 |
11. Dividends declared and paid with respect to the year/period
|
Dividends paid during the period ended 30 September 2026 |
Dividend |
Total dividend | |
|
Second interim dividend in respect of the period ended 31 March 2026 |
2.275 |
17,420 | |
|
|
|
| |
|
Dividends paid during the period ended 30 September 2025 |
Dividend |
Total dividend | |
|
Second interim dividend in respect of the period ended 31 March 2025 |
2.25 |
17,229 | |
On 23 November 2026, the Board approved the interim dividend of 2.225 pence per share with respect to the six months ended 30 September 2026. The record date for this dividend is 4 December 2026 and the payment date is 22 December 2026.
12. Related party transactions
Directors
The Company has four non-executive Directors, each of whom is considered to be independent. Directors’ fees for the period ended 30 September 2026 amounted to £121,260 (30 September 2025: £117,500), of which £nil (31 March 2026: £nil) was outstanding at the period/year end.
The shares held by the Directors at 30 September 2026 are shown in the table below:
|
|
Ordinary shares held at |
Ordinary shares held at |
|
Shonaid Jemmett-Page |
132,404 |
108,651 |
|
Sian Hill |
102,711 |
92,711 |
|
Marten Pieters |
160,625 |
160,625 |
|
Simon Pitcher |
100,000 |
90,000 |
Investment Manager
The Investment Manager charged management fees of £4.4 million (30 September 2025: £3.4 million) to the Company during the period, with nil (31 March 2026: £0.8 million) outstanding at period end.
Investment
The Company has provided additional funding of £5.2 million (USD 7.0 million) as a loan to its subsidiary, CDIL Data Centre USA LLC during the period ended 30 September 2026. The balance of the loan investment at 30 September 2026 was £30.3 million (31 March 2026: £25.2 million).
Company subsidiaries
During the period ended 30 September 2026, an additional and separate loan of £23.5 million (31 March 2026: £21.7 million) was issued and drawn down. As at 30 September 2026, the total outstanding balance of these loans was equivalent of £196.5 million (31 March 2026: £177.4 million), with no interest accrued or payable.
During the period ended 30 September 2026, the Company charged management fees amounting to £0.4 million (30 September 2025: £0.7 million) for services provided to its investments.
13. Ultimate controlling party
In the opinion of the Board, on the basis of the shareholdings advised to them, the Company has no ultimate controlling party.
14. Subsequent events
Apart from dividend declaration, as disclosed in Note 11, there were no other significant events following the reporting period ending 30 September 2026.
Glossary of capitalised defined terms
Administrator means Aztec Financial Services (Guernsey) Limited
AFFO means adjusted funds from operations
AIC means the Association of Investment Companies
Board means the board of Directors of the Company
Belgian Tower Company or BTC means Belgian Tower Company NV, formerly Norkring België NV.
Company means Corilis Digital Infrastructure Limited (formerly Cordiant Digital Infrastructure Limited)
Company’s Annual Report 2026 means the Company’s annual report for the year ended 31 March 2026
Companies Law means the Companies (Guernsey) Law 2008 (as amended)
Company’s Prospectus means the prospectus issued by the Company on 29 January 2021 in relation to its IPO
Corilis Digital Infrastructure Management or CDIM formerly Cordiant Digital Infrastructure Management LLP
means the Investment Manager’s Digital Infrastructure team
CRA means České Radiokomunikace a.s.
DAB+ means digital audio broadcasting plus, an advanced digital radio standard that provides higher audio quality and more efficient spectrum use compared to traditional FM broadcasting
DCF means discounted cash flow
Datacenter United or DCU means DCU Invest NV.
Digital Infrastructure means the physical infrastructure resources that are necessary to enable the storage and transmission of data by telecommunications operators, corporations, governments and individuals. These predominantly consist of mobile telecommunications/broadcast towers, data centres, fibre-optic networks, in-building systems and, as appropriate, the land under such infrastructure. Digital Infrastructure assets do not include switching and routing equipment, servers and other storage devices or radio transmission equipment or software
Directors means the directors of the Company
DTRs means the Disclosure Guidance and Transparency Rules issued by the FCA
EBITDA means earnings before interest, taxation, depreciation and amortisation
ECL means Enet Communications Limited, formerly BTCIL
Emitel means Emitel S.A.
ESG means environmental, social and governance
FCA means the UK Financial Conduct Authority
FX means foreign exchange.
GPU means graphics processing unit, a specialised processor designed to accelerate graphics rendering and parallel computing tasks, widely used in artificial intelligence and high‑performance computing
GPUaaS means GPU-as-a-service, a cloud computing delivery model that lets users rent high-performance GPUs on demand.
Hudson means Hudson Interxchange (previously operating under the name DataGryd Datacenters and a trading name of CDIL Data Centre USA LLC)
IAS means international accounting standards as issued by the Board of the International Accounting Standards Committee
IASB means the International Accounting Standards Board
IFRS means the International Financial Reporting Standards, being the principles-based accounting standards, interpretations and the framework by that name issued by the International Accounting Standards Board
Interim Report means the Company’s half yearly report and unaudited condensed interim financial statements for the six-month period ended 30 September 2026
Investment Entity means an entity whose business purpose is to make investments for capital appreciation, investment income, or both.
Investment Manager means Cordiant Capital Inc.
IoT means the Internet of Things
IPEV Valuation Guidelines means the International Private Equity and Venture Capital Valuation Guidelines
IPO means the initial public offering of shares by a company to the public
LSE means the London Stock Exchange
LTM means the last twelve months
MNO means mobile network operator
MOIC means multiple on invested capital
MUX means multiplex, a system that combines multiple digital TV or radio channels into a single signal for transmission over one frequency
NAV or net asset value means the value of the assets of the Company less its liabilities as calculated in accordance with the Company's valuation policy and expressed in pounds sterling
PUE means power usage effectiveness, an industry metric for measuring the energy efficiency of a data centre, calculated as the ratio of total facility energy to IT equipment energy
Speed Fibre means Speed Fibre Designated Activity Company
Subscription Shares means redeemable subscription shares of no par value each in the Company, issued on the basis of one Subscription Share for every eight ordinary shares subscribed for in the IPO
UK or United Kingdom means the United Kingdom of Great Britain and Northern Ireland
US or United States means the United States of America, its territories and possessions, any state of the United States and the District of Columbia
USD means United States dollars.
WACC means weighted average cost of capital.
Directors and general information
Directors (all appointed 26 January 2021)
Shonaid Jemmett-Page Chairman
Sian Hill Audit Committee Chairman and Senior Independent Director
Marten Pieters
Simon Pitcher
All independent and of the registered office below.
Website www.corilisdigital.com
ISIN (ordinary shares) GG00BMC7TM77
Ticker (ordinary shares) CORD
SEDOL (ordinary shares) BMC7TM7
Registered Company Number 68630
|
Registered office East Wing Trafalgar Court Les Banques St Peter Port Guernsey GY1 3PP |
Legal advisors to the Company Gowling WLG (UK) LLP 4 More London Riverside London SE1 2AU |
|
Investment manager Cordiant Capital Inc. 28th Floor Bank of Nova Scotia Tower 1002 Sherbrooke Street West Montreal QC H3A 3L6 |
Carey Olsen (Guernsey) LLP Carey House Les Banques St Peter Port Guernsey GY1 4BZ |
|
Company secretary and administrator Aztec Financial Services (Guernsey) Limited East Wing Trafalgar Court Les Banques Guernsey GY1 3PP |
Registrar Computershare Investor Services (Guernsey) Limited 1st Floor Tudor House Le Bordage St Peter Port Guernsey GY1 1DB |
|
Auditor BDO LLP 55 Baker Street London W1U 7EU |
Brokers Investec Bank plc 30 Gresham Street London EC2V 7QP |
|
Principal banker and custodian The Royal Bank of Scotland International Limited Royal Bank Place 1 Glategny Esplanade St Peter Port Guernsey GY1 4BQ |
Deutsche Numis 45 Gresham Street London EC2V 7BF |
|
Receiving agent Computershare Investor Services PLC The Pavilions Bridgwater Road Bristol BS99 6AH |
|
Cautionary Statement
This document may include statements that are, or may be deemed to be, ‘forward-looking statements’. These forward-looking statements can be identified by the use of forward‑looking terms or expressions, including ‘believes’, ‘estimates’, ‘anticipates’, ‘expects’, ‘intends’, ‘may’, ‘plans’, ‘projects’, ‘will’, ‘explore’ or ‘should’ or, in each case, their negative or other variations or comparable terminology or by discussions of strategy, plans, objectives, goals, future events or intentions. These forward-looking statements include all matters that are not historical facts. They may appear in a number of places throughout this document and may include, but are not limited to, statements regarding the intentions, beliefs or current expectations of the Company, the Directors and/or the Investment Manager concerning, amongst other things, the investment objectives and investment policy, financing strategies, investment performance, results of operations, financial condition, liquidity, prospects and distribution policy of the Company and the markets in which it invests.
By their nature, forward-looking statements involve risks and uncertainties because they relate to future events and depend on circumstances that may or may not occur in the future. Forward‑looking statements are not guarantees of future performance. The Company’s actual investment performance, results of operations, financial condition, liquidity, distribution policy and the development of its financing strategies may differ materially from the impression created by, or described in or suggested by, the forward-looking statements contained in this document. Further, this document may include target figures for future financial periods.
Any such figures are targets only and are not forecasts. Nothing in this document should be construed as a profit forecast or a profit estimate. In addition, even if actual investment performance, results of operations, financial condition, liquidity, distribution policy and the development of its financing strategies, are consistent with any forward-looking statements contained in this document, those results or developments may not be indicative of results or developments in subsequent periods. A number of factors could cause results and developments of the Company to differ materially from those expressed or implied by the forward‑looking statements including, without limitation, general economic and business conditions, industry trends, inflation and interest rates, the availability and cost of energy, competition, changes in law or regulation, changes in taxation regimes, the availability and cost of capital, currency fluctuations, changes in its business strategy and political and economic uncertainty. Any forward-looking statements herein speak only at the date of this document.
As a result, you are cautioned not to place any reliance on any such forward-looking statements and neither the Company nor any other person accepts responsibility for the accuracy of such statements. Subject to their legal and regulatory obligations, the Company, the Directors and the Investment Manager expressly disclaim any obligations to update or revise any forward‑looking statement contained herein to reflect any change in expectations with regard thereto or any change in events, conditions or circumstances on which any statement is based.
Certain financial information contained in this report has been rounded. Accordingly, figures shown as totals in certain tables may not be an exact arithmetic aggregation of the figures that precede them and percentage movements may not be exactly reconcilable to the figures shown.