Cora Gold Limited announced an updated Definitive Feasibility Study for its Sanankoro Gold Project, featuring an updated Probable Reserve of 531 koz at 1.13 g/t gold, based on a gold price of US$2,200/oz. The 2025 DFS economics, post-tax and based on a gold price of US$2,750/oz, include a 65% internal rate of return and a 1.1 year payback period. The project anticipates US$479m in free cash flow over the life of mine, with an average of US$67m per year in the first 5 years, and a NPV8 of US$221m. The LOM cash cost is projected at US$948/oz and AISC at US$1,478/oz, with a 10.2-year reserve mine life and average production of 47 koz per year, increasing to 64 koz per year for the first 5 years, with pre-production capital costs of US$124m.