FEED and Early Works Progress Update

Summary by AI BETAClose X

Cora Gold Limited is advancing its Sanankoro Gold Project towards construction with significant progress in the Front-End Engineering Design (FEED) process, which is on track for completion in Q4 2026. Key equipment suppliers are engaged, and negotiations for main infrastructure are underway, while geotechnical work for the process plant, power station, and tailings storage facility is completed or commencing. The company has also finalized land compensation for the tailings storage facility and upgraded its exploration camp. Permitting efforts with the Government of Mali are ongoing, with a positive interim renewal of an exploration permit. The project has a Probable Reserve of 531 koz and is fully funded for development through a binding US$120 million gold stream secured in April 2026.

Disclaimer*

Cora Gold Limited
21 September 2026
 

Cora Gold Limited / EPIC: CORA.L / Market: AIM / Sector: Mining

21 September 2026

Cora Gold Limited ('Cora' or 'the Company')

 

FEED and Early Works Progress Update:

Advancing the Sanankoro Gold Project Towards Construction

 

Cora Gold Limited, the West African focused gold company, is pleased to provide an update on the progress of the Front-End Engineering Design (‘FEED’) process and early works programme at the Company’s flagship Sanankoro Gold Project (‘Sanankoro’ or the ‘Project’) in southern Mali as it moves towards construction.

 

Highlights

 

        FEED process, led by New SENET (Pty) Ltd (‘SENET’; a DRA Global group company), advancing well with many workflows, including 3D plant modelling and all field work, now concluded.

        Key equipment suppliers engaged across the comminution, carbon in leach (‘CIL’) and elution circuit, with design information feeding directly into the FEED process.

        Key facilities supplier negotiations in progress for the supply of the main infrastructure, including buildings and new mining camp.

        Geotechnical drilling and test excavations completed at the process plant and power station areas to support detailed foundation design.

        Tailings storage facility (‘TSF’) land compensation process has been completed, with final geotechnical work due to commence imminently on the TSF site.

        Exploration camp upgrade completed, including new security perimeter fencing, refurbished accommodation and upgraded facilities, readying the site for the next phase of activity.

 

Bert Monro, Chief Executive Officer of Cora Gold, commented: “Sanankoro is rapidly moving towards construction readiness, with the FEED going very well and all field work now completed.  3D plant modelling has now been completed, and key equipment suppliers are actively engaged on comminution, CIL and elution circuit packages.

 

“Alongside the engineering work, the exploration camp upgrade is complete, providing a suitable base for the next phase of activity. The TSF land compensation process is complete, and we are due to commence further geotechnical work at site, in advance of the final detailed design, imminently.  These parallel work streams are designed to compress the timeline to first gold once we are in receipt of the mining permit.

 

“This work is progressing in tandem with our resource expansion work, which has yielded highly positive initial results. The programme is targeting extensions to existing deposits and near-mine greenfield targets, with the aim of expanding the current JORC-compliant mineral resource of over one million ounces.  This is setting the stage for a low-cost, high-margin, long-life mine at Sanankoro and we continue to engage actively with the Government of Mali and look forward to sharing further progress on permitting in the near future.”

 

FEED Progress

The FEED process, announced in May 2026 and led by SENET, is progressing well and work remains on target to be completed in Q4 2026.  Updated technical proposals and design information have been submitted to SENET, enabling good progress with 3D plant modelling and selective detailed drawing development across all major process areas, including the run-of-mine (‘ROM’) area, crushing and transfer to milling, the scrubber and ball mill circuit, the CIL and elution circuits, including the carbon regeneration circuit.

 

Design input has been received from key equipment suppliers, including for the mineral sizer, rotary drum scrubber and ball mill.  This supplier engagement is progressing in parallel with the FEED process to support long lead item decision-making once the mining permit is received.

 

Metallurgical verification test work to confirm the comminution circuit design is underway at Independent Metallurgical Operations Pty Ltd (‘IMO’; an SGS group company) laboratories in Perth, Australia.  The test programme covers bulk and variability composite characterisation, scrubber optimisation, gravity concentration and cyanide leach testing.

 

Geotechnical drilling and test excavations have been completed at the process plant and power station areas, to provide foundation design parameters for the FEED.

 



 

Pre-Construction Activities

Alongside the FEED process, the Company is advancing a number of pre-construction work streams to ensure Sanankoro is ready to move into full construction as quickly as possible once the mining permit is received.

 

The land compensation process for the TSF area, covering 174 hectares, has been completed.  The Company is about to commence final geotechnical work on the TSF site in advance of detailed design.

 

The exploration camp upgrade has now been completed with works including the installation of a new security perimeter fence and gates, refurbishment of accommodation blocks, new ceilings, doors and painting throughout, upgraded ablution facilities, and the installation of additional water storage capacity. The upgraded camp provides a suitable operational base as Sanankoro transitions into the construction phase.

 

Permitting

The Company continues to engage actively with the Government of Mali on the exploitation permit application and the permit reshaping exercise to consolidate all mining infrastructure under a single mining permit area. As announced by the Company on 24 August 2026, Mali's Council of Ministers has approved the first interim renewal of the Sanankoro II exploration permit, representing a positive step in this process.

 

**ENDS**

 

For further information, please visit http://www.coragold.com or contact:

Bert Monro
Craig Banfield

Cora Gold Limited

info@coragold.com

Derrick Lee
Pearl Kellie

Cavendish Capital Markets Limited
(Nomad and Broker)

+44 (0)20 7220 0500

Matt Hasson

Andrew Chubb

Hannam & Partners

(Broker)

+44 (0) 20 7907 8500

Susie Geliher
Charlotte Page

St Brides Partners
(Financial PR)

cora@stbridespartners.co.uk

 

Notes

 

Cora is a West African gold developer with de-risked project areas within two known gold belts in Mali and Senegal. Led by a team with a proven track-record in making multi-million-ounce gold discoveries that have been developed into operating mines, Cora's primary focus is on developing the Sanankoro Gold Project in the Yanfolila Gold Belt in south Mali into an open pit oxide mine.

 

Cora has a Probable Reserve of 531 koz at 1.13 g/t Au (US$2,200/oz Au pit shell design). The 2025 Definitive Feasibility Study showed that the Project has strong economic fundamentals, including 98% IRR post tax, US$365 million NPV8 post tax and all-in sustaining costs of US$1,623/oz based on a gold price of US$3,500/oz.

 

In April 2026, the Company secured a binding US$120 million gold stream which, together with existing equity, fully funds the development of Sanankoro through to production. The agreement also provides flexibility and was amended in August 2026 to allow up to 50% of the stream to be replaced with traditional senior debt by the later of 30 October 2027 and 6 months after the date on which the mining rights permit is granted by the Government of Mali, enabling optimisation of the financing structure. With funding in place, the Company is advancing the finalisation of the permitting process with the Government of Mali to enable a swift transition into mine construction.

 

The Company continues to pursue additional value-enhancing opportunities across its broader portfolio, including the identification of large-scale gold mineralisation potential at the Madina Foulbé exploration permit, located within the Mako Gold Belt of the Kédougou-Kéniéba Inlier in eastern Senegal.

This information is provided by RNS, the news service of the London Stock Exchange. RNS is approved by the Financial Conduct Authority to act as a Primary Information Provider in the United Kingdom. Terms and conditions relating to the use and distribution of this information may apply. For further information, please contact rns@lseg.com or visit www.rns.com.

RNS may use your IP address to confirm compliance with the terms and conditions, to analyse how you engage with the information contained in this communication, and to share such analysis on an anonymised basis with others as part of our commercial services. For further information about how RNS and the London Stock Exchange use the personal data you provide us, please see our Privacy Policy.
 
END
 
 
UK 100

Latest directors dealings