Cindrigo Holdings Limited is revising its strategy for its Finnish operations, focusing on a direct role in the biomass value chain through Kaipolan Energia Oy to support the Kaipola 110 MW biomass combined heat and power plant's commercial start-up. Instead of selling heat to industrial customers by December 2025, the company plans to commence wood pellet production with sales to other biomass plants targeted for Q1 2026, aiming to reduce reliance on third-party off-takers and enhance earnings visibility. Cindrigo is in advanced discussions with potential joint venture partners and funding parties for this expansion, which will integrate upstream biomass production with downstream heat and power generation, while its geothermal development plans remain unaffected.