Feasibility Study for Bilboes Gold Project

AI SummaryClose X

Caledonia Mining Corporation Plc has announced its decision to proceed with the Bilboes Gold Project following the publication of its feasibility study, which confirms a single-phase development approach. The project boasts proven and probable mineral reserves of 1.749 million ounces of gold at a grade of 2.26 g/t, with measured and indicated resources of 532,000 ounces and inferred resources of 984,000 ounces. The study projects a life of mine production of 1.55 million ounces over 10.8 years, with an all-in sustaining cost of $1,061 per ounce, and anticipates first production in late 2028. Economic analysis at a consensus forecast gold price of $2,548/oz yields a post-tax NPV of $582 million and an IRR of 32.5%, with a peak funding requirement of $484 million, expected to be financed primarily through non-recourse senior debt.