Azteca Restart Update

AI SummaryClose X

Cadence Minerals plc has received the initial construction funding tranche for the Azteca Plant restart at the Amapá Iron Ore Project in Brazil, with contractor mobilization expected to commence shortly. Following the grant of the Installation Licence on May 5, 2026, refurbishment and installation works are now progressing into execution. Commissioning activities are anticipated approximately 60 days from the funding receipt on May 25, 2026, under an accelerated schedule, or 90 days with standard contingency, pushing the commissioning target to the end of July or August 2026. Cadence's total investment in the Amapá Project is approximately $16.1 million, representing a 36.2% equity stake as of the end of March 2026.